17-0710_TAYLOR MORRISON_Staff Memo Warranty Bonds ReleaseMEMORANDUM DATE: July 10, 2017 TO: Ben Siegel, City Manager Steve May, Public Works and Utilities Director FROM: George Alvarez, City Engineer 27 r, SUBJECT: Warranty Bond Release—Campanilla, Tract 13436 The developer has completed all improvement work as required by the Conditions of Approval and the Grading Surety Agreements. The improvements have been inspected and have been found to be completed per City standards and to the satisfaction of the Public Works & Utilities Department. On November 3, 2015 City Council approved and adopted Resolution 15-11-03-01, accepting the work as complete and approval of release of sureties on the project. The City requires that the owner/developer provide a one-year warranty of this work. The developer had supplied warranty bonds totaling $317,583.10 (10% of the original improvement costs) to cover the costs of any warranty issues over the next year. Over a year has passed since the Notice of Completion for the project was recorded. No warranty issues have required the use of the warranty bonds. While normally these bonds automatically terminate after a year's time the surety and developer are requesting that the City provide a release letter. The warranty bond release is recommended as follows: SURETY COVERAGE (Lexon Insurance Company) Bond Number Type of Improvement Bond Amount 1134557 Campanilla - Common Area Offsite Landscaping $6,500.00 1134558 Campanilla- Grading Improvements $24,000.00 1134559 Campanilla - In -Tract Landscaping Improvements $65,000.00 1134560 Campanilla- Monumentation $1,650.00 1134561 Campanilla - Storm Drain $58,675.00 1134562 Campanilla, Tract 13436 - Water and related appurtenances $38,452.00 1134563 Campanilla, Tract 13436 - Sanitary Sewer Area $31,082.00 1134564 Campanilla, Tract 13436- Public Streets $1,960.00 1134565 Campanilla, Tract 13436 - Private Streets $79,464.00 Attachments: November, 2015 City Council Item Cc: Tom Toman, Assistant Public Works Director Hossein Ajideh, Senior Civil Engineer City of San Juan Capistrano Agenda Report TO: Honorable Mayor and Members of the City Council FROM: Thom Coughran, P.E., Interim Public Works and Utilities Director Prepared by: Joe Mankawich, Associate Engineer DATE: November 3, 2015 SUBJECT: Consideration of a Resolution for a Notice of Completion, Acceptance of Certain Work of Improvements and Release of Corresponding Sureties Pertaining to the Subdivision Improvement Agreement for the Campanilla Subdivision (Tract 13436) (Taylor Morrison of California, LLC) RECOMMENDATION: By motion, 1. Adopt a Resolution accepting the public street, sewer, water, landscaping, traffic signal, and storm drain improvements and the work of improvements for the onsite and offsite grading pertaining to Campanilla (Tract 13436); and, 2. Direct the City Clerk to process the recording of the Notice of Completion with the Orange County Recorder; and, 3. Authorize the City Clerk to release the corresponding bonds 35 days after the recordation of the Notice of Completion. EXECUTIVE SUMMARY: Taylor Morrison of California LLC (Developer) of Campanilla (Tract 13436) has requested that the City release the street, water, traffic signal, sewer, storm drain, and onsite and offsite improvement bonds held by the City. These improvements have been inspected and satisfactorily completed. Staff recommends adoption of a resolution accepting the work as complete, the filing of a Notice of Completion and the release of the corresponding bonds. City Council Agenda Report November 3, 2015 Page 2 of 3 DISCUSSION/ANALYSIS: Tract Map 13436 consists of six (6) numbered lots and one (1) lettered Lot on a 28.35 acre property. In 2009, Pacific Communities Builder submitted an Architectural Control (AC 09- 004) application to the Planning Commission and obtained, by Planning Commission Resolution No. 09-06-09-01, a conditional approval to construct a 132 -lot single family residential development, consisting of various sized single family detached homes and condominiums on the six (6) numbered lots within the boundaries of Tract Map 13436. Plans for the improvements were approved by the City Engineer in 2011 and 2012. On May 15, 2012, the City Council approved the Subdivision Improvement Agreement with Taylor Morrison of California. One of the Conditions of Approval for Tract 13436 requires developer participation, in the amount of $108,000 for traffic improvements. In lieu of a traffic signal, a roundabout will be constructed. The $108,000 fee will used to reimburse the Pacifica San Juan Developer who is constructing the roundabout. The developer has submitted a cash deposit to the City in the amount of $108,000 to meet this participation requirement. The developer has completed all other improvement work as required by the Conditions of Approval and the Grading Surety Agreements. The improvements have been inspected and have been found to be completed per City standards and to the satisfaction of the Public Works & Utilities Department. Staff recommends adoption of a Resolution accepting the work as complete and the recordation of a Notice of Completion for the project. With the completion of the improvements and cash deposit as noted in the summary above, the bond release is recommended as follows: SURETY COVERAGE (Developers Surety and Indemnity Company) Bond Number Type of Improvement Bond Amount Bond #1071734 Grading Performance $ 240,000.00 Bond #1071741 Monumentation $ 16,500.00 Bond #1071742 Offsite Landscaping $ 65,000.00 Bond #1071743 In -Tract Landscaping $ 650,000.00 Bond #1071744 Traffic Signal Improvements $ 108,000.00 Bond #1071745 Sanitary Sewer $ 310,818.00 Bond #1071746 Storm Drain $ 586,751.00 Bond #1071747 Private Street $ 794,642.00 Bond #1071748 Public Street $ 19,600.00 Bond #1071749 Water & Appurtenances $ 384.520.00 Total Bond Amount $3,175,831.00 The City requires that the ownerldeveloper provide a one-year warranty of this work. The developer has supplied warranty bonds totaling $317,583.10 (10% of the original improvement costs) to cover the costs of any warranty issues over the next year. City Council Agenda Report November 3, 2015 Page 3 of 3 FISCAL IMPACT: Not applicable. ENVIRONMENTAL IMPACT: Not applicable. PRIOR CITY COUNCIL REVIEW: • On May 15, 2012, the City Council approved the Subdivision Improvement Agreement for Tract 13436, Taylor Morrison of California, LLC. (Campanilla Homeowners Association). COMMISSION/COMMITTEE/BOARD REVIEW AND RECOMMENDATIONS: • On June 9, 2009, the Planning Commission approved Architectural Control 09-004 for Tract 13436 (Taylor Morrison of California, LLC). NOTIFICATION: Taylor Morrison of California, LLC ATTACHMENT(S): Attachment 1 - Resolution Attachment 2 - Notice of Completion Attachment 3 - Location Map