Resolution Number 16-11-15-01RESOLUTION NO. 16-11-15-01
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN JUAN
CAPISTRANO, CALIFORNIA, DECLARING WORK TO BE COMPLETED
AS TO PLANS AND SPECIFICATIONS FOR THE CAMINO
CAPISTRANO PAVEMENT REHABILITATION PROJECT, BY R. J.
NOBLE COMPANY (CIP 16109) FEDERAL PROJECT ID # STPL-5372
(016)
WHEREAS, on the 19th day of July 2016, the City of San Juan Capistrano
entered into a contract with R. J. Noble Company (15505 E. Lincoln Avenue, Orange,
CA 92865) for the Camino Capistrano Pavement Rehabilitation Project (CIP 16109)
Federal Project ID # STPL-5372 (016); and,
WHEREAS, the Public Works and Utilities Director has evaluated the final
quantities and cost figures and recommends approval.
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of
San Juan Capistrano, does resolve as follows:
SECTION 1. That the work required to be performed by said Contractor
has been completed.
-- SECTION 2. That the total cost of said work was $617,757
SECTION 3. That the work is hereby accepted and approved.
SECTION 4. That the City Clerk is directed to forward forthwith a Notice
of Completion to the County Recorder of the County of
Orange for recording.
PASSED, APPROVED, AND ADOPTS this 15th day of November 2016.
AM PATTERSON, SQ. MAYO
11/15/2016
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss.
CITY OF SAN JUAN CAPISTRANO )
I, MARIA MORRIS, appointed City Clerk of the City of San Juan Capistrano, do hereby
certify that the foregoing Resolution No. 16-11-15-01 was duly adopted by the
Cit Council of the City of San Juan Capistrano at the Regular meeting thereof, held the
15' day of November 2016, by the following vote:
MEMBERS: Reeve, Perry, Allevato, Ferguson and Mayor Patterson
NCIL MEMBERS: None
11/1512016