16-0607_BOUDREAU PIPELINE CORPORATION_Transmittal to BoudreauJune?, 2016
Boudreau Pipeline Corporation
463 N. Smith Avenue
Corona, CA 92880
Re: Alipaz Street Drainage improvement Project (CIP 16501)
To Whom it May Concern:
At their meeting of May 3, 2016, the City Council of the City of San Juan Capistrano
adopted Resolution 16-05-03-02 accepting the work as completed for the construction of
the Alipaz Street Drainage Improvement Project (CIP 16501).
A copy of the recorded Notice of Completion is enclosed for you records.
The retention will be payable upon 35 days from recording of the Notice of Completion.
The Notice was recorded on May 23, 2016; therefore, the final payment in the amount of
$3,995.00 may be released on June 27, 2016.
If you have any questions, please do not hesitate to call.
\
Christy JakI, CMC
Assistant City Clerk
cc: Steve May, Public Works and Utilities Director
Khoon Tan, Senior Civil Engineer
Ken Al-lman, Interim Chief Financial Officer
Jeanien Marsh, Accounting Specialist
San Juan Capistrano: Preserving the Past to Enhance the Future
Pnnlod on 100% rocydnd popur