Resolution Number 16-05-03-02 RESOLUTION NO. 16-05-03-02
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN JUAN
CAPISTRANO, CALIFORNIA, DECLARING WORK COMPLETED AS TO
PLANS AND SPECIFICATIONS FOR THE ALIPAZ STREET DRAINAGE
IMPROVEMENT PROJECT (BOUDREAU PIPELINE CORPORATION,
CIP 16501)
WHEREAS, on the 22"d day of January 2016, the City of San Juan
Capistrano entered into a contract with Boudreau Pipeline Corporation, 463 N. Smith
Avenue, Corona, CA 92880, for construction of the Alipaz Street Drainage Improvement
Project; and,
WHEREAS, the City Engineer has evaluated the final quantities and cost
figures and recommends approval.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
San Juan Capistrano as follows:
SECTION 1. That the work required to be performed by said Contractor
has been completed.
SECTION 2. That the total cost of said work is $39,950.
SECTION 3. That the work is hereby accepted and approved.
SECTION 4. That the City Clerk is directed to forward forthwith a Notice
of Completion to the County Recorder of the County of
Orange for Recording.
PASSED, APPROVED, AND ADOPTED this 3rd day of May 2016.
Pam atterson, Esq., Mayor
f
ATTEST:
t r'
Maria M6QLsvvTy erk
i
1 05-03-2016
STATE OF CALIFORNIA }
COUNTY OF ORANGE ) ss.
CITY OF SAN JUAN CAPISTRANO )
I, MARIA MORRIS, appointed City Clerk of the City of San Juan Capistrano, do hereby
certify that the foregoing Resolution No. 16-05-03-02 was duly adopted by the
City Council of the City of San Juan Capistrano at the Regular meeting thereof, held the
5t" day of May 2016, by the following vote:
AYES: f j C�UNCIL MEMBERS: Reeve, Perry, Allevato, Ferguson and Mayor Patterson
NOES: ! q-OUNCIL MEMBERS: None
ABSENT: COUNCI-L MEMBERS: None
I
I
MARIAVIVO Als, CIY ERK
2 05-03-2016