16-0204_BURTECH PIPELINE, INC_Construction Agreement First AmdFIRST AMENDMENT TO
CONSTRUCTION AGREEMENT
SPRING STREET STORM DRAIN REPAIR PROJECT
THIS FIRST AMENDMENT TO THE CONSTRUCTION AGREEMENT between the
CITY OF SAN JUAN CAPISTRANO ("City") and Burtech Pipeline Inc., ("Consultant") is made
and entered into, to be effective the day of fjehfitoyij , 2016, as follows:
RECITALS
WHEREAS, the City and Consultant have entered into that Construction Agreement
dated November 6, 2015 for repair of the Spring Street storm drain (the "Agreement"); and
WHEREAS, the City and Consultant desire to amend the terms of the Agreement as
provided hereunder:
AMENDMENT
NOW, THEREFORE, in consideration of the promises and mutual covenants contained
therein. City and Consultant agree to amend Section 3.1 of the Agreement as follows:
Section 3.1, Compensation Amount, is amended to add $5,255.11 to the Compensation
Amount for a total not to exceed Compensation Amount of $23,655.11.
540028.1
61147.02100\10229925.1
-1-
All other provisions of the Agreement not amended hereunder shall remain in full force and
effect.
APPROVED AS TO FORM: BURTECH PIPELINE INC.
By: By:
Jeffrey Ballinger, City Attorney Dominic Burtech, President
540028.1
61147.02100\10229925.1
-2-
All other provisions of the Agreement not amended hereunder shall remain in full force and
effect.
CITY OF SAN JUAN CAPISTRANO
By:
Keith Till, Interim City Manager
ATTEST:
By:
Maria Morris, City Clerk
APPROVED AS TO FORM: BURTECH PIPELINE INC.
By: Q -y.^ By:
Jeffrey BallingefTCity Attorney Dominic Burtech, President
540028.1
61147.02100\10229925.1
-2-
All other provisions of the Agreement not amended hereunder shall remain in full force and
effect.
CITY OF SAN JUAN CAPISTRANO
By:
ATTEST:
By:
Keith Till, Interim City Manager
Maria Morris, City Clerk
APPROVED AS TO FORM: BURTECH PIPELINE
By:
Jeffrey Ballinger, City Attorney
540028.1
61147.02100\10229925.1
-2-