03-0107_ST. PIERRE, PAUL AND NANCY_Agenda Report_D13 1/7/2003 D13 AGENDA ITEM TO: George Scarborough, City Manager FROM: William M. Huber, Director of Engineering & Building SUBJECT: Consideration of Reimbursement Agreement for Hidden Mountain/Los Corrales Drainage Facility (St. Pierre) RECOMMENDATION By motion, approve the Reimbursement Agreement for Hidden Mountain/Los Corrales Drainage Facility between the City and Paul and Nancy St. Pierre. SITUATION A. Summary and Recommendation Staff is recommending approval of a Reimbursement Agreement with Paul and Nancy St. Pierre to correct a drainage situation which exists between Tract 11826 Hidden Mountain and Tract 9373 Los Corrales. B. Background Los Corrales Tract 9373 was constructed around 1977. One of the project's public improvements was a 54-inch diameter public storm drain which collects run-off from the east of Paseo Establo Hidden Mountain Tract 11826 was constructed around 1986. One of the projects public improvements was a 24-inch diameter public storm drain which collects run-off from the Hidden Mountain development and runs in easement across the St. Pierre property 31982 Paseo Sagrado and discharges across an access road to the 54-inch diameter public storm drain in Los Corrales. By letter dated September 28, 2002, Mr. St. Pierre brought the problems of water flowing across this road to the City's attention. A City project to address this situation has been part of the 2000-2007 Capital Improvement Program. It was deleted from the program in 2001 due to lack of funding and anticipated developer participation. The lack of City funding for this :project still exists and the developer participation is not now anticipated. Mr. and Mrs. St. Pierre have agreed to fund design and construction of this drainage project subject-to a reimbursement agreement. The terms of the agreement are for construction within one year and for the City to reimburse the St. Pierre costs ten years after its completion. Agenda Item January 7, 2003 Page 2 Staff is recommending approval of this Reimbursement Agreement as a method of implementing this City drainage improvement. COMMISSIONS/BOARD REVIEW, RECOMMENDATIONS N/A FINANCIAL CONSIDERATIONS The engineer's estimate for design and construction is $35,000. The City's obligation is to reimburse this cost ten years after completion of construction.The drainage fund will be the funding source. NOTIFICATION The following parties received notifications of this Council Agenda item. Mr. & Mrs. St. Pierre* Eric H. Nelson Ronald W. Dye Jim R. Allen Thomas Wayne McDonald Gary S. Johnson Bonnie Jean Lynn John R. Benson Edward J. Both Gareth C. Nitchman * Agenda report is included. ALTERNATIVE ACTIONS 1. By motion, approve the Reimbursement Agreement for Drainage Facilities between the City and Paul and Nancy St. Pierre. 2. Do not approve the Reimbursement Agreement. 3. Request additional information from Staff. Agenda Item January 7, 2003 Page 3 RECOMMENDATION; By motion,approve the Reimbursement Agreement for Drainage Facilities between the City and Paul and Nancy St. Pierre. Respectfully submitted: Prepared by: w' ..u'A' . � y'°•a 4A William M. Huber, P.E. Brian Perry, P.E. Director, Engineering and Building Project Manager WMH/BP:sam Attachments: 1. Location Map 2. Reimbursement Agreement ,a THE CITY O 0t NSAN JUAN CAPISTRANO r REIMBURSEMENT AGREEMENT '' ✓� ' HIDDEN MOUNTAIN/LOS CORRALES (ST PIERRE) `�=`� � •`"""'-•a. .a':`b:� •F�;;,�--„,gam,�"� �d Jfo r !!% `�;< �,� v ,Po�pTC .� # ,,:4✓y�SSes'w ��” Y M��� 10 Of •,�?��"• st:i E� S�`��g •%S g. �� �s�'f'�` `..cbyyC•,��' is M. L1u..„�2,t��•+,R,ap.iCoO"'••2',. o � ?��..:".>� 'fr.ra�`��y.='�'SC!� •�iQ� �,.'%1•k >r•'" ) ,� w,r✓' � Y+f'` •' ! >�"vr�,'.Tv Y�t�, ftF :3��6,�A �j��M ���i �„F,ZL�`'' f�•/.'`� j•� Esc .�.' �" `�, �; l 14 r �. f. ; :,!t• £. ,.. 4i LOCATION ,:<''�:a;�g < :i'•' L "3°•c,owo.2 L•F,k A' N"' �)�&C�,•e'.'a`.`tie', a I��,„-i.p� •�.�,E.��'a"''Y r,!F :::•�`j� ?� �,� �Y 4,52'�»���7 7� �:`•tiy �„h DEL s�"�f r.,��,�. <C.^�;; ffff�Gf r` � � s' fi•�c��• �� ,^C tUt aw _1-4�wY: :µl'M.r`.J� •�::�: ,j, .ph �� C�/��� +p..I•w--M��Ua'�K. �-'.'RF•a% a!,t:�£ 2k: 61 .`• a'couooz�o�" �yr.Y<� ,3a. G c f �„,,,,y£/f 71 '�.,,,r: r�.���: � � ��� �.��,•.� 0 3000 6000 0000 Feet ATTACHMENT 1 REIMBURSEMENT AGREEMENT DRAINAGE FACILITIES THIS AGREEMENT,dated the day of 2003 is by and between Paul R. St. Pierre and Nancy E. St. Pierre, as co-trustees UDT of the St. Pierre Family Trust dated March 31, 1999, owners of property located at 31982 Paseo Sagrado also know as Lot 21 of Tract 11826 hereinafter referred to as "DEVELOPER"and the City of San Juan Capistrano, hereinafter referred to as "CITY". WHEREAS,in connection with development of its property at 31982 Paseo Sagrado in the City of San Juan Capistrano, DEVELOPER wishes to construct public storm drain improvements; and, WHEREAS, such improvements shall consist of extending existing 24" dia Storm Drain Line A from its terminal headwall at Sta 1+74.06 shown on "Storm Drain Plans for Tract No. 11826", Sheet No. 10 of 11 within the 20 feet wide City storm drain easement dedicated on Tract Map No. 11826. Such storm drain extension shall terminate in a new headwall within the existing inlet rip-rap to existing 54" dia Storm Drain Line A shown on "Improvement Plans for Tract No. 9373, Drain Line A", Sheet No. 18 of 18. All plans are on record in the Engineering and Building Department of CITY. WHEREAS, CITY has previously budgeted such improvements in the 2000-2007 Capital Improvement Program; and, WHEREAS, such improvements were removed from the Capital Improvement Program in 2001 due to lack of funding, as well as anticipated developer participation; and, WHEREAS,such funding is still not available and such developer participation is not now anticipated; and WHEREAS, DEVELOPER agrees to design at its sole cost and expense of an estimated amount of $7,500 and construct at its sole cost and expense of an estimated amount of$27,500, a total of$35,000 a storm drain system; and WHEREAS, DEVELOPER desires to enter into this agreement to provide means for allowing the construction of such storm drain system and related appurtenances and to provide a mechanism for crediting the DEVELOPER,forthe reimbursable costs incurred in constructing such facilities against available drainage funds collected for Drainage Assessments; and WHEREAS, the proposed storm drain system provides a benefit to the CITY, the CITY is, therefore, willing to reimburse the costs for areas of benefit to CITY. Attachment 2 Reimbursement Agreement Page 2 NOW, THEREFORE, in consideration of the premises hereinafter set forth, CITY agrees to reimburse DEVELOPER an aforesaid sum of $35,000 from drainage fees collected from Drainage Assessment under the following terms and conditions: 1. Term of Reimbursement by the City: Upon expiration of the ten (10) year term from the date of completion and acceptance of the work, CITY shall reimburse to DEVELOPER $35,000. 2. Alterations: The City Engineer of the CITY may make such changes, alterations or additions to the plans and specifications for said work and improvements which do not exceed ten percent(10%)of the total estimated cost as may be determined necessaryand desirable by him for the proper completion of said work and improvement oras required for the safety and welfare of the public and no such changes, alterations or additions shall relieve the DEVELOPER from the faithful performance of this agreement. All such additions shall be at the written direction of the City Engineer. 3. Completion Date: DEVELOPER agrees to complete all of said work and improvements within a period of one year from the execution date of this agreement. If additional time is needed, an extension may be granted by the City Engineer on the showingof good cause. Any such extension shall, however, be subject to all of the terms and conditions of this agreement, and any suretyor other security shall continue in full force Y until the work and improvement has been accepted by the CITY. 4. Liability/Insurance A. DEVELOPER agrees to pay CITY such sum as the court may adjudge ad'ud a as reasonable for the legal services of any attorney representing the CITY in any action brought to enforce or interpret the obligations of this instrument, and such sum shall be made a part of any judgment in such action against the DEVELOPER if such action is determined in favor of the said CITY. B. CITY, its officers and employees,except for their own acts,shall not be liable or responsible for any accident, loss or damage happening or occurring to the improvements specified in this agreement prior to the completion and acceptance of said improvements by the CITY. C. DEVELOPER shall perform all work in a safe workmanlike manner and shall take such precautions as may be necessary to warn and protect the public from any dangerous condition caused by the construction of said improvements. Reimbursement Agreement Page 3 D. DEVELOPER shall hold CITY, its officers and employees harmless from any and all claims, demands, causes of action, liability or loss of any sort because of, or arising out of, the acts or omissions of the DEVELOPER, his contractor, subcontractors, agents or employees in the performance of this agreement. E. DEVELOPER agrees to maintain liability insurance during the construction of the storm drain system in the following amounts: I. Comprehensive General Liabilitx. DEVELOPER shall maintain in full force and effect comprehensive general liability coverage, including premises operations, products/completed operations, broad form property damage, and blanket contractual liability in the following minimum amounts: $1,000,000 property damage; $1,000,000 injury to one person/any one occurrence/ not limited to contractual period; $1,000,000 injury to more than one person/ any one occurrence/ not limited to contractual period. II. Worker's Compensation. If DEVELOPER employs employees or subcontractors to perform services under this agreement, DEVELOPER shall obtain and maintain, during the life of this agreement,Worker's Compensation Employer's Liability Insurance in the statutory amount as required by state.law. These above stated policies shall not terminate, nor shall they be cancelled, nor the coverage reduced, until after 30 days written notice is given to the CITY. DEVELOPER shall provide an endorsement to CITY establishing that CITY has been legally added as an additional insured to the liability policy required under this agreement. 5. Surety Bonds The DEVELOPER shall post Labor and Material and Performance surety bonds each in an amount equal to CITY approved Engineer's construction estimate prior to commencement of any construction work or issuance of permits on standard form approved by the City Attorney to ensure all of the DEVELOPER's obligations as noted in this agreement. Reimbursement Agreement Page 4 6. Guarantee and Warranty of Work DEVELOPER guarantees that said work shall be free from defects in material or workmanship and shall perform satisfactorily for a period of one year from and after the CITY's acceptance of the work as completed in accordance with the Municipal Code. DEVELOPER agrees to correct, repair or replace at his expense any defects in said work. 7. Force Ma'eure None of the parties hereto shall be deemed to be in default if performance of the obligations required by this agreement is delayed or becomes impossible because of any act of God, earthquake, fire, strike, sickness, accident, civil commotion, epidemic, act of. government, its agencies or officers, or any legitimate cause beyond the control of thep arties. 8. Notices All notices, requests, demands, consents and other communications under this agreement shall be in writing, including telex and facsimile transmission, and shall be deemed to have been duly given on the date of service if served personally, be telex, or facsimile transmission, or 48 hours after mailing if mailed by first-class mail, registered or certified, postage prepaid, return receipt requested, and properly addressed as follows: To: Mr. Paul R. St. Pierre and Nancy E. St. Pierre 31982 Paseo Sagrado San Juan Capistrano, CA 92675 To: City of San Juan Capistrano Attention: City Clerk 32400 Paseo Adelanto San Juan Capistrano, CA 92675 9. Assignment This agreement shall be binding upon and inure to the benefit of the parties hereto and their respective representatives, assigns and successors in interest. 10. Entire Agreement This agreement contains the entire agreement between the parties hereto and supersedes any prior or concurrent written or oral agreement between said parties concerning the subject matter contained herein. There are no representations, agreements, arrangements or undertakings, oral or written, between oramong the parties hereto relating to the subject matter contained in this agreement, which have not been fully expressed herein. Reimbursement Agreement Pa e 5 IN WITNESS THEREOF, the parties hereto have executed this agreement on the date first above written. DEVEL ER PAUL R. ST. RRE CO"-TRUSTEE ST. PIERRE FAMILY TRUST DATED MARCH 31, 1999 DATE: NANCY T. PIERRE CO-TRUSTEE ST. PIERRE FAMILY TRUST DATED MARCH 31, 1999 DATE: ATTEST: CITY OF SAN JUAN CAPISTRANO MARGARET R. MONAHAN, CITY CLERK JOHN S. GELFF, MAYOR DATE: DATE: AS TO FORM: JOHN R. AW, CITY ATTORNEY XA C DATE: