Resolution Number 11-11-01-01RESOLUTION NO. 11-11-01-01
A RESOLUTION OF THE CITY OF SAN JUAN CAPISTRANO,
CALIFORNIA, DECLARING WORK COMPLETED PURSUANT TO
PLANS AND SPECIFICATIONS FOR THE GW TREATMENT PLANT
MODIFICATIONS—GAC FOR MTBE REMOVAL (CIP 10804)
WHEREAS, on the 12" day of July, 2010, the City of San Juan Capistrano
entered into a contract with Tetra Tech, Inc. (Contractor), for construction of the
Granular Activated Carbon System for MtBE removal at the Ground Water Recovery
Plant; and,
WHEREAS, the Utilities Director has evaluated the final quantities and
cost figures and recommends approval.
NOW, THEREFORE, BE IT RESOLVED, by the City of San Juan
Capistrano as follows:
SECTION 1. That the work required to be performed by said Contractor has
been completed.
SECTION 2. That the total cost of said work is in the amount of $1,613,991.
SECTION 3. That the work is hereby accepted and approved.
SECTION 4. That the City Clerk is directed to forthwith forward a "Notice of
Completion" to the County Recorder of the County of Orange for
recording.
PASSED, APPROVED, AND ADOPTED this 1S1 day of vember, 2011.
AM ALLEVATO, MAYOR
11/1/2011
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss.
CITY OF SAN JUAN CAPISTRANO )
I, MARIA MORRIS, appointed City Clerk of the City of San Juan Capistrano, do hereby
certify that the foregoing Resolution No. 11-11-01-01 was duly adopted by the City
Council of the City of San Juan Capistrano at a Special meeting thereof, held the 151 day
of November 2011, by the following vote:
COUNCIL MEMBERS:
Freese, Reeve, Taylor, Kramer and Mayor Allevato
OUNCIL MEMBER:
None
OUNCIL MEMBER:
None
11/1/2011