Resolution Number 08-10-21-03RESOLUTION NO. 08-10-21-03
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN JUAN
CAPISTRANO, CALIFORNIA, DECLARING WORK TO BE COMPLETED
AS TO PLANS AND SPECIFICATIONS FOR THE EMERGENCY SEWER
TRUNK LINE REPLACEMENT PROJECT (BOUDREAU PIPELINE
CORPORATION (CIP No. 728 I CIP No. 716)
WHEREAS, on the 20th day of May, 2008, the City of San Juan Capistrano
entered into a contract with Boudreau Pipeline Corporation, 130 Klug Circle, Corona,
CA 92880 for construction of the Emergency Sewer Trunk Line Replacement Project,
and
WHEREAS, the Public Works Director has evaluated the final quantities and cost
figures and recommends approval.
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of San
Juan Capistrano, does resolve as follows:
0
SECTION 1. That the work required to be performed by said Contractor has
been completed.
SECTION 2. That the total cost of said work is $531,206.06
SECTION 3. That the work is hereby accepted and approved.
SECTION 4, That the City Clerk is directed to forward forthwith a Notice of
Completion to the County Recorder of the County of Orange for
Recording.
PASSED, APPROVED, AND ADOPTED this 21't day of October 2008.
CN d
JOE OTO, MAYOR
ET R. MONAHAN, CITY CLERK
Page 1 of 2 10-21-2008
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss.
CITY OF SAN JUAN CAPISTRANO }
I, MARGARET R. MONAHAN, appointed City Clerk of the City of San Juan Capistrano, do
hereby certify that the foregoing Resolution No. 08-10-21-03 was duly adopted by the City
Council of the City of San Juan Capistrano at a Regular meeting thereof, held the 21 sc day of
October 2008, by the following vote:
AYES: COUNCIL MEMBERS: Allevato, Hribar, Uso, Nielsen and Mayor Soto
NOES: COUNCIL MEMBER: None
RECUSE: CUU iq]l- MEMBER: None
. MONAHAN, City Clerk
Page 2 of 2 10-21-2008