Resolution Number 07-02-06-01RESOLUTION NO. 07-02-06-01
A RESOLUTION OF THE CITY OF SAN JUAN CAPISTRANO,
CALIFORNIA, DECLARING WORK TO BE COMPLETED AS TO PLANS
AND SPECIFICATIONS FOR THE PASEO CRUCERO WATERLINE
REPLACEMENT (DOTY BROTHERS EQUIPMENT, CO.)
WHEREAS, on the 28th day of November, 2006, the City of San Juan
Capistrano entered into a contract with Doty Brothers Equipment, Co. for the Paseo
Crucero Waterline Replacement project; and,
WHEREAS, Staff has found the work to be complete and recommends
approval; and,
NOW, THEREFORE, BE IT RESOLVED, by the City of San Juan
Capistrano as follows:
SECTION 1. That the work required to be performed by said Contractor
has been completed.
' SECTION 2. That the total cost of said work is in the amount of $212,965.
SECTION 3. That the work is hereby accepted and approved.
SECTION 4. That the City Clerk is directed to forthwith forward a "Notice
of Completion" to the County Recorder of the County of Orange for recording.
ATTEST:
PASSED, APPROVED, AND ADOPTED this 6th day of February 2007.
r ALLEVATO, MAYOR
1#dd91►F-11U.11 01 3
Page 1 of 1 2/6/2007
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss.
CITY OF SAN JUAN CAPISTRANO )
I, MARGARET R. MONAHAN, appointed City Clerk of the City of San Juan Capistrano, do hereby certify
that the foregoing Resolution No. 07-02-06-01 was duly adopted by the City Council of the City of San Juan
Capistrano at a Regular meeting thereof, held the 6`h day of February 2007, by the following vote:
AYES:
COUNCIL MEMBERS:
NOES:
COUNCIL MEMBER:
ABSENT:
COUNCIL MEMBER:
R. MONAHAN, City Clerk
Hribar, Uso, Soto and Mayor Allevato
None
Nielsen