Resolution Number 06-12-19-01RESOLUTION NO. 06-12-19-01
A RESOLUTION OF THE CITY OF SAN JUAN CAPISTRANO,
CALIFORNIA, DECLARING WORK TO BE COMPLETED AS TO PLANS
AND SPECIFICATIONS FOR THE PASEO ACTIVO UTILITY EASEMENT
SLOPE PROTECTION (J.C. BALDWIN CONSTRUCTION COMPANY)
WHEREAS, on the 19th day of September, 2006, the City of San Juan
Capistrano entered into a contract with J.C. Baldwin Construction Company for the
Paseo Activo Utility Easement Slope Protection project; and,
WHEREAS, the Engineer of Record has evaluated the final quantities and
cost figures and recommends approval per its letter dated November 21, 2006; and,
NOW, THEREFORE, BE IT RESOLVED, by the City of San Juan
Capistrano as follows:
SECTION 1. That the work required to be performed by said Contractor
has been completed.
' SECTION 2. That the total cost of said work is in the amount of
$164,987.17.
SECTION 3. That the work is hereby accepted and approved.
SECTION 4. That the City Clerk is directed to forthwith forward a "Notice
of Completion" to the County Recorder of the County of Orange for recording.
PASSED, APPROVED, AND ADOPTED this 19'h day of December 2006.
-ISAM ALL ATO, MAYOR
ATTST:
CLERK
Page 1 of 1 12/19/2006
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss.
CITY OF SAN JUAN CAPISTRANO )
I, MARGARET R. MONAHAN, appointed City Clerk of the City of San Juan Capistrano, do hereby certify
that the foregoing Resolution No. 06-12-19-01 was duly adopted bythe City Council of the City of San Juan
Capistrano at a Regular meeting thereof, held the 19'" day of December 2006, by the following vote:
AYES: COUNCIL MEMBERS:
NOES:/`- COUyJ�iIL MEMBER:
ABSENT O IL MEMBER:
City Clerk
Hribar, Nielsen, Uso, Soto and Mayor Allevato
None
None