Resolution Number CRA 86-12-16-1RESOLUTION NO. CRA 86-12-16-1
ENVIRONMENTAL IMPACT FINDINGS (PRICE CLUB)
A RESOLUTION OF THE SAN JUAN CAPISTRANO COMMUNITY
REDEVELOPMENT AGENCY MAKING CERTAIN FINDINGS
REGARDING THE ENVIRONMENTAL IMPACT OF THE PROPOSED
PRICE CLUB AND RETAIL SPACE DEVELOPMENT TO BE
DEVELOPED PURSUANT TO A DISPOSITION AND DEVELOPMENT
AGREEMENT AND ADOPTING A STATEMENT OF FINDINGS AND
OVERRIDING CONSIDERATIONS THEREFOR (PRICE CLUB)
145
WHEREAS, the City Council of the City of San Juan Capistrano, (the "City
Council") by Ordinance No. 488 on July 12, 1983, adopted and approved the
Redevelopment Plan for the San Juan Capistrano Central Redevelopment Project and
amended said Plan by Ordinance No. 509 on May 15, 1984, by Ordinance No. 547 on
July 16, 1985, and by Ordinance No. 582 on August 19, 1986 (the "Redevelopment Plan");
and,
WHEREAS, the San Juan Capistrano Community Redevelopment Agency, (the
"Agency") and the City Council certified a Final Environmental Impact Report for the
Redevelopment Plan (the "Original EIR") on July 5, 1983, by Resolution No. 83-7-5-3 and
on July 5, 1983, by Resolution No. CRA 83-7-5-2; and,
WHEREAS, the Agency (Resolution No. 86-8-5-1) and City Council (Resolution
No. 86-8-5-7) on August 5, 1986 certified a Final Focus Environmental Impact Report for
the Price Club Development within the Project area (the "Focus EIR"); and,
WHEREAS, the Agency proposes the development of a Price Club and retail
space within the Project Area by a private developer (the "Developer") and to enter into
a Disposition and Development Agreement (the "DDA") therefor; and,
WHEREAS, a duly noticed public hearing was held by the Agency and the City
Council on November 18, 1986, at which time all interested persons were given an
opportunity to be heard.
NOW, THEREFORE, BE IT RESOLVED, by the San Juan Capistrano
Community Redevelopment Agency, City of San Juan Capistrano, California, as follows:
1. The Agency hereby certifies the information contained in the Focus EIR
has been reviewed and considered by the members of the Agency with
respect to the proposed development of the site and the proposed
Disposition and Development Agreement.
The Agency hereby finds with respect to the proposed development and
the adverse environmental impacts detailed in the Focus EIR that:
a. the adverse environmental impacts pertaining to
development, including all alternatives set forth in
have been considered and recognized by the Agency;
-1-
the proposed
the Focus EIR,
146
3.
4.
b. based on information set forth in the Focus EIR and in
Attachment "A" (attached hereto and incorporated herein by this
reference) the Agency finds and determines that measures have
been incorporated into the proposed development which mitigate or
avoid adverse environmental impacts identified in the Final EIR _
and set forth in Attachment "A';
C. based on information set forth in the Focus EIR and in
Attachment "A", the adverse environmental impacts related to
traffic, noise, air pollutants and deletion of open space are
remaining impacts after mitigation which cannot be entirely
mitigated or avoided if the project is implemented;
d. that no additional adverse impacts will have a significant effect or
result in a substantial or potentially substantial adverse change in
the environment as a result of the proposed development.
The Agency hereby finds and determines that all significant
environmental effects identified in the Focus EIR have been reduced to
an acceptable level in that:
a. all significant environmental effects that can feasibly be avoided
have been eliminated or substantially lessened as determined
through the findings set forth in paragraph 2.b. of this Resolution;
b. based on the Focus EIR, the documents in the record and upon
Section IV of Attachment "A" attached hereto and incorporated
herein by this reference, specific economic, social or other
considerations make infeasible other project alternatives identified
in said Focus EIR;
C. based on the Focus EIR and the documents in the record, all
remaining, unavoidable significant effects of the proposed
development are overridden by the benefits of the project as
described in Section V of Attachment "A" and the Agency hereby
approves and adopts Section V of Attachment "A" as a Statement
of Overriding Considerations for the proposed development.
The Agency, as lead agency, hereby authorizes and directs a Notice of
Determination be filed with respect to the Focus EIR pertaining to the
-2-
147
approval of the proposed Disposition and Development Agreement for the
proposed development and all other actions taken in furtherance thereof.
PASSED, APPROVED, AND ADOPTED this 16th day
Of— December ,1986.
A L. HAUSDORFER, CH�IRMAN
ATTEST:
AG N Y SFj RY
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss
CITY OF SAN JUAN CAPISTRANO )
I, MARY ANN HANOVER, Secretary of the San Juan Capistrano Community
Redevelopment Agency, DO HEREBY CERTIFY that the foregoing is a true and correct
copy of Resolution No. CRA 86-12-16-1. adopted by the Board of Directors of the
San Juan Capistrano Community Redevelopment Agency, at a regular meeting thereof
held on the 16th day of December , 1986, by the following vote:
AYES: Directors Bland, Friess, Schwartze and
Chairman Hausdorfer
NOES: None
ABSENT: Director Buchheim
(SEAL)
MARY ANN XANOVER,
AGENCY SECRETARY
-3-
148
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss. AFFIDAVIT OF POSTING
CITY OF SAN JUAN CAPISTRANO )
MARY ANN HANOVER, being first duly sworn, deposes and says:
That she is the duly appointed and qualified Secretary of the San Juan
Capistrano Community redevelopment Agency;
That in compliance with State laws of the State of California and in further
compliance with City Resolution No. CRA 83-12-20-1 and on the 18th day
of December , 1986, she caused to be posted:
RESOLUTION NO. CRA 86-12-16-1 , being:
ENVIRONMENTAL IMPACT FINDINGS (PRICE CLUB)
A RESOLUTION OF THE SAN JUAN CAPISTRANO
COMMUNITY REDEVELOPMENT AGENCY MAKING
CERTAIN FINDINGS REGARDING THE ENVIRONMENTAL
IMPACT OF THE PROPOSED PRICE CLUB AND RETAIL
SPACE DEVELOPMENT TO BE DEVELOPED PURSUANT TO A
DISPOSITION AND DEVELOPMENT AGREEMENT AND
ADOPTING A STATEMENT OF FINDINGS AND OVERRIDING
CONSIDERATIONS THEREFOR (PRICE CLUB)
in three (3) public places in the City of San Juan Capistrano, to wit: City Hall; Old Fire
Station Recreation Complex; Orange County Public Library.
CHECK LIST
RES. NO. CRA k,
✓ Chairman has signed
Secretary has signed
Agency Seal stamped
/ All blanks typed in
"Absent"
"Noes" .r
"Abstain"
Copies sent to post —3
file ."
mail certified
Legal Publication ordered to be published
(date)
No. Printed copies required
Remarks
9
MARY MN/jUANOVER, Secretary
San Juan Cdpistrano Community
Redevelopment Agency
-4-
149
Exhibit "A"
STATEMENT of FINDINGS
STATEMENT of OVERRIDING CONSIDERATIONS
150
STATEMENT OF FINDINGS
PRICE CLUB DEVELOPMENT
ENVIRONMENTAL IMPACT REPORT
I. SIGNIFICANT ENVIRONMENTAL EFFECTS
A. LAND USE
1. Implementation of the proposed project will re-
quire the following approvals: a) General Plan
Amendment; b) Zone change; c) Redevelopment Plan
Amendment; d) Approval of the Development Plan;
and e) Approval by the Coastal Commission of the
Development Plan on the 12.4 acre County Parcel.
2. The proposed project will also require annexation
of the 12.4 acre County Parcel into the City; how-
ever this is a separate project and as such is
subject to a separate environmental review.
3. The proposed project is considered marginally con-
sistent with the objectives of these documents:
the City's Land Use and Community Design Element,
and both the City's and County's Zoning.
B. CIRCULATION
1. The proposed project will generate 17,830 average
weekday trips when completed, and 23,270 average
Saturday trips. At ultimate build -out the project
will generate approximately 1,638 weekday p.m.
peak hour trips and 240 weekday a.m. peak hour
trips.
2. Certain links along Camino Capistrano will operate
at LOS E&F without build -out of the areas proposed
facilities.
C. NOISE
1. Construction activities on-site will result in
short-term increases in noise levels adjacent to
site access routes and the on-site areas under
construction at any given time.
151
2. Motor vehicle noise resulting from the proposed
project will constitute a long-term acoustic im-
pact in the vicinity.
3. On-site noise impacts from off-site sources could
result from ultimate railroad operations and traf-
fic volumes using the freeway and Doheny Park
Road.
D. AIR QUALITY
1. The development of the proposed project will gen-
erate exhaust emissions from construction equip-
ment and the automobiles of the construction crew,
as well as fugitive dust during soil movement.
Sensitive receptors near the project site will
find these air pollutant emissions a temporary
nuisance.
2. The proposed project will generate: 2,763 pounds
of carbon monoxide, 294 pounds of hydrocarbons,
342 pounds of NOx, 50 pounds of SOx, and 64 pounds
of particulates, daily once completed.
E. ARCHAEOLOGY
1. Development of
site, may yield
sits.
F. AESTHETICS
the southernmost portion of the
sub -surface archaeological depo-
1. Implementation of the proposed project will result
in the loss of undeveloped land and the construc-
tion of;three commercial buildings, with a parking
area which will cover approximately 60 percent of
the project site.
2. The proposed project is not consistent with all of
the objectives of the City's Community Design Ele-
ment.
G. WATER SERVICE
I. Water mains would have to be installed on-site, as
well as to the site.
X 5z
H. SEWER SERVICE
1. Sewer lines would have to be installed on the
site.
I. STORM WATER DRAINAGE
1. There have not been any storm drainage facilities
incorporated into the project design, which will
result in sheet flow across the site once the
project is implemented.
2. Portions of the project site are located in the
County's Floodplain Two Overlay Zone and the Fed-
eral Insurance Rate Map's 100 -year floodplain;
site design has not incorporated any flood control
measures.
J. ELECTRICITY
1. The proposed project will consume approximately
2.73 million kWh per year. Electrical lines would
have to be installed on the site.
K. NATURAL GAS
1. Implementation of the proposed project will result
in the consumption of 7.56 million cu. ft. per
year. Gas lines would have to be installed on the
site.
L. SOLID WASTE DISPOSAL
1. No significant environmental impact.
M. POLICE PROTECTION
1. Implementation of the
in increased daytime
gestion, affecting
response times.
proposed project will result
population and traffic con -
emergency and non -emergency
153
N. FIRE PROTECTION
1. Project implementation will result in an increase
in the number of incidents responded to by the
Department and will contribute to the cumulative
need for additional fire protection services.
O. HEALTH CARE SERVICES
1. No significant environmental effect.
P. TELEPHONE SERVICE
1. The telephone
vice demand of
this number, a
be required.
Q. RECREATION
company can provide an initial ser -
not more than 30 lines. To augment
4-6 month construction period will
1. Project Implementation will result in the loss of
a potential open space/recreational area for the
community.
II. MITIGATION MEASURES INCLUDED IN THE ENVIRONMENTAL
IMPACT REPORT
A. LAND USE
1. The proposed project shall be required to adhere
to all landscaping and architectural standards,
and height restrictions of the City's Municipal
Code, as well as to either the City's Architec-
tural Design Guidelines or the Capistrano Beach
Specific Plan/LCP.
2. Implementation of the proposed development plan
will require that the entire site is under one
jurisdiction, requiring the review and approval of
LAFCO.
B. CIRCULATION
1. The project sponsor should offer to dedicate suf-
ficient right-of-way to accommodate the ultimate
improvements of Doheny Park Road adjacent to the
site; Doheny Park Road should be improved to ulti-
mate full section.
154
2. The main access to the Price Club should be sig-
nalized and aligned opposite Camino Capistrano at
Doheny Park Road or moved to a point southerly of
the proposed main entrance.
3. A stop sign should be installed at each secondary
driveway from the site onto Doheny Park Road to
control traffic.
4. Secondary driveways should be right turn in and
out of the site only.
5. The internal circulation layout and aisle widths
should: (1) be consistent with the recommenda-
tions included in the internal circulation discus-
sion, and (2) be subject to the review and approv-
al of the City Engineer.
6. Landscaping and signs should be limited• to 36
inches in height within 25 feet of project drive-
ways to maximize sight distances.
7. Street lights and sidewalks should be provided in
accordance with City standards.
8. A separate truck access onto the site shall be
provided with adequate truck parking while waiting
to unload merchandise.
9. The project sponsor may be required as a condition
of approval to provide funds for areawide trans-
portation improvements.
C. NOISE
1. Construction activities should take place only
during the days and hours specified by City
Ordinance to reduce impacts during more sensitive
time periods. Adjacent to occupied residential
areas, the construction equipment hours of opera-
tion should be restricted to 7:00 a.m. through
6:00 p.m. Monday through Friday and from 8:30 a.m.
through 4:40 p.m. on Saturdays. All construction
equipment, fixed or mobile, should be equipped
with properly operating and maintained mufflers.
2. Stationary equipment should be placed such that
emitted noise is directed away from sensitive
noise receivers.
155
3. Building setbacks, building design and orientation
should be used to reduce intrusive noise levels at
each building pad on-site prior to the issuance of
building permits.
4. A perimeter wall should be constructed adjacent to
the western site boundary to ensure that patrons
of the development do not venture onto the ATSSF
railroad tracks. This wall would also reduce on-
site noise levels if it were at least 6 feet tall.
Similar walls should be constructed along the
southern and northern boundaries as well, for
noise purposes.
5. Final site design should include a truck access
route to the truck wells behind each building that
places the trucks as far as possible from the ex-
isting mobile home park located north of the site
(preferably along the southern and western site
boundaries).
6. Delivery trucks should be routed to and from the
site on Doheny Park Road to reduce impacts to sen-
sitive receptors located adjacent to Camino Capis-
trano. Delivery trucks queued to off-load prior
to 7:00 a.m. should not be allowed to idle while
waiting.
D. AIR QUALITY
1. SCAQMD Rule 403 will be adhered to, insuring the
clean up of construction related dirt on approach
routes to the site.
2. Adequate watering techniques shall be employed to
partially mitigate the impact of construction gen-
erated dust particulates.
3. Building construction shall comply with the energy
use guidelines in Title 24 of the California Ad-
ministrative Code.
E. ARCHAEOLOGY
I. An archaeological monitoring program shall be de-
veloped for the southernmost 2.5 acres. The area
to be monitored should consist of a 66 feet wide
transact across the southern boundary of the prop-
erty.
1156
2. A program for dealing with cultural remains should
be developed in the event that previously unknown
resources are discovered during construction.
F. AESTHETICS
1. The proposed project shall be consistent with all
applicable criteria outlined in the City's Commu-
nity Design Element; and all buildings located on
the site shall be designed in accordance with the
City's Architectural Design Guidelines or the Cap-
istrano Beach Specific Plan/LCP.
2. A detailed landscaping plan shall be prepared and
approved prior to or concurrent with granting of
final architectural approval. Extensive landscap-
ing with native materials is recommended along the
western boundary.
3. A comprehensive sign plan and comprehensive light-
ing plan should be submitted for City approval.
4. C,C,&R's should be reviewed by the City to ensure
that site and facility maintenance is provided.
5. All trash enclosures should be architecturally
compatible and fully enclosed; and no outside
storage or display should be permitted.
G. WATER SERVICE
1. The CVWD and the project developer shall enter
into an agreement to construct an off-site pipe-
line that would meet the fire flow requirements of
the proposed development.
2. The construction of the new off-site water facili-
ties will be funded by the District's Capital Im-
provement charges which must be paid by the devel-
oper.
3. Construction of water lines on the project site
will be the responsibility of the project develop-
er.
4. use of reclaimed waste water where appropriate
will be encouraged.
157
H. SEWER SERVICE
1. The project developer will be responsible for a
one-time sewer fee of $2,615 per 1500 square feet
of floor area.
2. At the time of building permit issuance, the
availability of sewer capacity will be verified.
I. STORM WATER DRAINAGE
1. The master planned LO1-SO3 facility or a similar
facility shall be constructed to drain the project
site and tie in to the existing L01 -S02 facility
as part of the proposed development.
2. Prior to the issuance of building permits an en-
gineer's report should be prepared and submitted
to the City Engineer for approval specifying in
detail the method of protection, materials to be
employed, and the method of maintenance of such
protective devices.
3. A water -proof barrier should be placed at the
project boundary, in this way, preventing flood
waters from flowing into the project site.
4. Building criteria outlined in the County's Zoning
Code under the FP -2 Zone shall be adhered to.
J. ELECTRICITY
1. All services and facilities built will be in ac-
cordance with the Company's policies and extension
rules on file with the California Public Utilities
Commission and federal regulatory agencies.
K. NATURAL GAS
1. All services and facilities built will be in ac-
cordance with the Company's policies and extension
rules on file with the California Public Utilities
Commission and federal regulatory agencies.
2. Easements are required for all gas mains not
installed in a public right-of-way.
1.58
L. SOLID WASTE DISPOSAL
1. The project developer shall provide sufficient ac-
cess to accommodate the maneuvers of the waste
disposal company's trucks.
2. The project developer should coordinate with the
Solag Disposal Company in the development of addi-
tional design criteria.
3. The project developer should provide trash enclos-
ures which are a minimum of five feet wide by ten
to twelve feet in length.
M. POLICE PROTECTION
No mitigation proposed.
N. FIRE PROTECTION
1. Fire flows of 1250 9 -P.m. to 5000 g.p.m. will be
required depending on the type of construction
used.
2. Hydrant spacing shall be 300 feet to 600 feet de-
pending on the type of construction.
3. Additional fire protection measures should be con-
sidered in the design and construction of the pro-
posed development. Such measures may include
smoke detectors or automatic fire sprinkler sys-
tems in all buildings.
O. HEALTH CARE SERVICES
No mitigation proposed.
P. TELEPHONE SERVICE
No mitigation proposed.
Q. RECREATION
1. The elimination of on -street parking in order to
accommodate bicycle lanes on Doheny Park Road and
Camino Capistrano adjacent to the site should be
considered.
159
2. The use of lockers and racks to be utilized for
bicycle parking should also be considered.
III. REMAINING IMPACTS AFTER MITIGATION
1. An increase in traffic volumes on local and re-
gional roadways.
2. An increase in noise to the adjacent users.
3. Increased emissions of air pollutants affecting
local and regional air quality.
4. Incremental loss of regional and local open space.
5. Consumption of non-renewable resources (building
materials) and energy.
IV. FINDINGS
A. That the mitigation measures and conditions of ap-
proval required and incorporated into the project
will avoid or substantially lessen the significant
environmental effects identified in the areas of land
use, circulation, noise, air quality, archaeology,
aesthetics, water service, sewer service, storm water
drainage, fire and police protection, as well as
other utilities and services.
B. That the following mitigation measures which have not
been included as part of this project will be comple-
ted prior to the completion of the proposed project:
1. Planned improvements to Camino Capistrano north of
the project; and
2. The extension of Stonehill Drive.
C. That certain mitigation measures or alternatives
identified in the Final EIR are not feasible for
implementation at t}is time due to overriding social,
economic, or other considerations with the exception
Of Alterntive 4 which in effect is a modification of
the current development proposal based on the mitiga-
tion recommended in the EIR.
160
I. The No Project Alternative
The No Project Alternative assumes no discretion-
ary action at this time. This would mean that the
City's and County's plans for development of the
site would remain unimplemented. As a result of
this alternative, none of the impacts identified
in this EIR would occur at this time. All the
"unavoidable" adverse impacts cited (consumption
of non-renewable resources -- building materials
-- and energy, increased emissions of air pollu-
tants, affecting local and regional air quality,
incremental loss of regional and local open space,
an increase in traffic volumes on local and re-
gional roadways, etc.) would be avoided. Mitiga-
tion measures presented throughout this EIR (e.g.,
flood control recommendations, noise barrier
requirements, intersection signalizations, etc.)
and improvements proposed as part of the Proposed
Development Plan (e.g., landscaping, internal
roadways, etc.), would not be necessary.
Failure to approve a Development Plan for the
project site and transfer of the 12.4 acres of to
site to the City of San Juan Capistrano, implies
that the property would remain vacant and undevel-
oped for an undetermined period of time. Failure
to implement the project will result in the con-
tinued demand for retail commercial and restaurant
uses in the area. This project will help satisfy
a portion of the demand for these retail commer-
cial and restaurant uses in the area.
2. Alternative Two - Previous Proposals
The project site could be developed under one of
the previous development proposals for the subject
property.
Under the development proposal processed through
the City in 1978, there were a variety of land
uses proposed, including: light industrial, of-
fices, restaurants, and financial institutions.
The total square footage proposed under this de-
velopment scenario was 311,328 square feet. This
is 1438 greater than the current project prooposal
based on square footage.
16.1
In 1983, Davis Developments proposed the Capis-
trano Commerce Center, which was located on the
northern ten acres of the project site, entirely
within the City of San Juan Capistrano. This
development proposal consisted of approximately
219,000 square feet of light industrial, commer-
cial, and mini -storage rentals. This is approxi-
mately 2,000 square feet more on 12.4 acres less
than the current project proposal.
Implementation of either the 1978 or the 1983 de-
velopment scenarios would result in impacts re-
lated to land use considerations, increased traf-
fic volumes and air pollution (although not as
signficant as the current proposal), potentially
greater noise volume, and incompatibilities with
land use goals of the City. Furthermore, indus-
trial development would likely be a generator of
noise, both as point source and highway noise,
primarily resulting from truck travel and the
loading/unloading of freight. Industrial develop-
ment would also not be as financially positive to
either the City or the project proponent as the
proposed project. And a general commercial use of
the site would be economically marginal due to
competing market forces in the immediate area and
region.
3. Alternative Three - Medium Density Residential
The project site could also be developed as a
medium density residential community with an
average of five dwelling units per acre, yielding
a total of 112 units for the entire project site.
Implementation of a residential project of this
nature, while being more compatible to the mobile
home park adjacent to the north of the site, might
represent an incompatibility with the existing
shopping center adjacent to the south.
Implementation of this development scenario would
require the same approvals as the current project
proposal, including Zone Change, General Plan
Amendment, and approval by the Coastal Commission
for the development of the 12.4 acre County par-
cel. This alternative would not require a Redevel-
opment Area Plan as required by the current pro-
posal.
162
It is likely that the residential alternative
would not result in the impacts to traffic, air
quality, and noise as the current development pro-
posal. However, any residential uses would be
impacted by the commercial development to the
south, as well as railroad and freeway noise.
4. Alternative Four - Modified Site Design
In effect, this alternative has been developed by
incorporating recommended mitigation measures, re-
sulting from the environmental concerns presented
in Section IV of the EIR. This alternative re-
sults in some modification to the proposed devel-
opment plan.
This alternative does not attempt to prioritize
the significance of each environmental impact or
whether there are any overriding considerations
which would balance the project's benefits against
unavoidable impacts.
One of the difficulties in presenting an alterna-
tive of this nature is that mitigation of one im-
pact may result in the creation of another impact.
For example, by providing an additional access on-
to the project site to be used exclusively by de-
livery trucks, fewer parking spaces would be pr-
ovided.
The discussion of this alternative is approached
from the perspective of a preliminary development
plan which mitigates each environmental topic
(which is applicable at this level of planning) to
a major extent with the exception of the "No Proj-
ect" alternative. Architectural considerations
are not included.
Land Use
The following comments are in response to various
City and County policies, goals, and objectives.
Additional landscaping and berming on the islands
along Doheny Park Road is encouraged to create a
visual screen of the proposed development. In ad-
dition, where the development plan varies from one
tree per 12 to 16 spaces, this alternative would
increase the number of trees, providing one tree
per eight spaces. In addition to providing more
163
of a visual buffer this would also provide summer
shading and windbreaks.
To encourage pedestrian access, a special paving
treatment would be utilized at major pedestrian
crossings.
The 75,000 square foot large retail outlet would
be moved closer to the southern boundary to create
a more clustered appearance with the smaller re-
tail and restaurant uses and would also give the
impression of varied setbacks.
Circulation
The main access to the Price Club is aligned oppo-
site Camino Capistrano at Doheny Park Road or at
some point southerly of where this access is loca-
ted at the Proposed Development Plan; this access
is signalized in this alternative. An exclusive
delivery truck access is provided along the south-
ern boundary, south of the clustered retail and
restaurant uses.
Noise
Perimeter walls are incorporated into the site de-
sign along the southern and western boundaries to
lessen noise impacts and for safety reasons along
the western boundary adjacent to the AT&SF rail
line.
Aesthetics
As noted previously, additional landscaping is in-
cluded in this alternative.
By incorporation of the mitigation recommended in
the EIR the Proposed Development Plan would be
modified to resemble the description of this al-
ternative.
V. STATEMENT OF OVERRIDING CONSIDERATIONS
The City of San Juan Capistrano proposes to approve the
project while recognizing that it will have certain un-
avoidable adverse impacts as identified in the EIR.
L64
Therefore, the City Council# having
ered the information contained in
ord, makes the following statement
erations which have been balanced
able adverse impacts in reaching
project.
reviewed and consid-
the EIR and the rec-
of overriding consid-
against the unavoid-
a decision on this
The following statements are considerations which war-
rant approval of the project and therefore override the
above environmental impacts:
1. Project implementation of the proposed development
plan would result in development of site which is
consistent with both City and County land use
plans.
2. Completion of the project will provide an addi-
tional 217,110 square feet of retail commercial
and restaurant uses in the project area.
3. Implementation of the proposed project with the
recommended mitigation for storm water drainage
would eliminate the flood hazard potential on the
site, as well as some of the adjacent areas.
4. The environmental impacts associated with this
project that are not fully mitigated are regional
in nature, and the project's cumulative contribu-
tion to those impacts is considered minimal and
acceptable from a regional perspective.
5. In view of all factors, the project with the rec-
ommended mitigation measures represents the best
reasonable balance and mix of uses for the project
area.
98.20