Resolution Number 66-4-25-324U
RESOLUTION NO. 66-4-25-3
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
SAN JUAN CAPISTRANO, CALIFORNIA, DECLARING ITS
INTENTION TO ORDER CERTAIN CHANGES AND MODIFI-
CATIONS IN THE WORK AND PROCEEDINGS FOR THE
CONSTRUCTION OF CERTAIN IMPROVEMENTS IN ASSESS-
MENT DISTRICT NO. 64-1 IN SAID CITY: DESCRIBING
SAID PROPOSED CHANGES AND MODIFICATIONS AND FIXING
A TIME AND PLACE FOR HEARING OBJECTIONS TO SAID
PROPOSED CHANGES AND MODIFICATIONS
WHEREAS, this City Council did on the 14th day of December, 1964, adopt its
Resolution of Intention No. 64-12_14-1 declaring its intention to order the con-
struction of certain improvements and acquisitions in Assessment District No. 64-1
in the City of San Juan Capistrano, California; and
WHEREAS, Engineering Science, Inc., has recommended and presented to this
Council a certain change order designated Contract Change Order No. 3 recommending
certain changes in the work be ordered and made in Assessment District No. 64-1
in the City of San Juan Capistrano.
NOW, THEREFORE, IT IS HEREBY RESOLVED BY THE CITY COUNCIL OF THE CITY OF
SAN JUAN CAPISTRANO, CALIFORNIA, AS FOLLOWS:
SECTION 1. That pursuant to a signed change order designated Contract
Change Order No. 3, said change order on file in the office of the City Clerk of
this City and by reason of the recommendations of the Engineer of Work, in the
public interest and convenience, it is the intention of the City Council of the
City of San Juan Capistrano, California, to order the following changes and modifi-
cations all as listed on said Contract Change Order No. 3 recommended by the
Engineer of Work.
1. Furnish only 104 lineal feet of 8 -inch diameter A.C. Pipe which shall
be installed by the local Orange County Water District forces.
Increase in contract price, which includes taxes, delivery, and all
related costs. $107.34
No change in contract time
This change is necessitated because a water line at approximate
station 111 + 90, line T-1, sheet 13, which was installed after the
plans were prepared and was not shown on the drawings. Portions of
this water line were subsequently removed during construction.
2. a. Within the parcel of land westerly of Line L-2.11, downstream
of 3 + 93.39, protect the existing horse trough, grout lined
storm channel, corral fence, horse shade structure, grouted
retaining wall and other improvements all as if they were shown
on the contract drawings.
b. Care and protect the horses as if the corral and horses existed
in their present location at the time of receipt of construction
bids.
Increase in contract price for item (a) $979.95
Increase in contract price for item (b) $640.00
Increase in contract time 1 day
241
This change is necessitated because all of the above improvements
were constructed after the receipt of construction bids and
consequently were not shown on the contract plans.
3. Construct a ten (10) foot wide hot oil mix roadway within Well Site
Road, between approximate stations 38+00, Line T-1 and 11+00, Line L-1.
The surface shall be a minimum of 2" thick, spreader depth, and equal
to that surface removed during construction. The resurfacing is esti-
mated to consist of approximately 15,000 square feet.
Increase in contract price shall be $0.12 per square foot. The
quantity constructed shall be as ordered by the Engineer and actual
payment shall be based upon measurements approved by the Engineer.
Estimated increase in contract price $1,800.00
Increase in contract time 3 days
This change is necessitated because this portion of Well Site Road
was covered with approximately one foot of dirt during the time when
the plans were being prepared and consequently was denoted on the
contract plans as being a dirt road within this reach. The balance
of the Well Site Road was shown as paved and is not included in this
change.
4. Construct the pipeline between 71+00 and 71+90, line No. T-1 of Class
3300 A.C. pipe in lieu of Class 1500 as shown on the contract plans.
Increase in contract price $1.70 per lineal foot for ninety (90) feet.
$ 153.00
No change in contract time.
This change is necessitated because the plans erroneously specified
the class of pipe within this reach identical with that specified on
each side.
SECTION 2. The total amount of increase in the Contract for the above
changes is estimated to be $3,680.29.
SECTION 3. That NOTICE IS HEREBY GIVEN that the 9th day of May, 1966, at
the hour of 7:30 o'clock p.m. in the Council Chambers located in the City Hall,
in the City of San Juan Capistrano, California, is the time and place when and
where any interested persons having any objections to the proposed changes and
modifications proposed to be made may appear before this City Council and show
cause why, such changes and modifications should not be made in accordance with
this Resolution. Objections must be in writing and filed with the City Clerk in
said City not later than the time set for hearing said objections.
SECTION 4. The City Clerk is hereby directed to certify to the adoption of
this Resolution and cause said Resolution to be published once not less than ten
(10) days prior to the date of said hearing, in the "COASTLINE DISPATCH", a news-
paper published and of general circulation in the City of San Juan Capistrano,
California
APPROVED and ADOPTED this 25th day of April
ATTEST:
City Clerk of the City of
San Juan Capistrano
San Juan Capistrano
2 4: 2
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss
CITY OF SAN JUAN CAPISTRANO )
I, ERNEST A. THOMPSON, City Clerk of the City of San Juan Capistrano, DO
HEREBY CERTIFY that the foregoing Resolution, being Resolution No. 66-4-25-3,
was duly passed, approved and adopted by said. City Council, approved and signed
by the Mayor, and attested by the City Clerk, all at a regular meeting of said
City Council held on the 25th day of April, 1966, and that the same was passed
and adopted by the following vote, to wit:
AYES: COUNCILMEN: BATHGATE, BUCHHEIM, FORSTER, OLIVARES and DURNFORD
NOES: COUNCILMEN: NONE
ABSENT: COUNCILMEN: NONE
DATED this 25th day of April 1966.
-<�--
CiW Clerk of the City of
San Juan Capistrano