Resolution Number 70-9-28-2338
RESOLUTION NO. 70-9-28-2
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF SAN JUAN CAPISTRANO ACCEPTING WORK: OSO
INTERCEPTOR SEWER.
WHEREAS, Lowry Engineering -Science, Engineers for the Oso
Interceptor Sewer project, has represented to Council that the con-
tractor has satisfactorily completed said project in accordance with
the plans and specifications therefor; and
WHEREAS, said Engineer has also represented that any and
all delays in completion beyond the time set forth in the contract
were caused by interference with poles and telegraph lines along
the alignment of the sewer within the A.T. & S.F. Railway right of
way.
1970.
NOW, THEREFORE, BE IT RESOLVED that:
1. The Contractor be and is hereby granted an extension
of time for the completion of work on the Oso Inter-
ceptor Sewer to and including September 25th, 1970.
2. The work on the Oso Interceptor Sewer project be and
is hereby accepted as complete as of September 25th,
1970.
3. Lowry Engineering -Science be and is hereby authorized
to file a Notice of Completion for said project.
4. The Finance Director be and is hereby authorized to
pay the Contractor the amounts due in accordance with
the final quantities as shown on letter from Lowry
Engineering -Science dated September 28th, 1970.
PASSED, APPROVED and ADOPTED this 28th day of September,
AYES: COUNCILMEN: THORPE, BATHGATE, CHERMAK,
GAMMELL, and FORSTER
NOES: COUNCILMEN: NONE
ABSENT: COUNCILMEN: NONE
Mayor of the City of
San Juan Capistrano
339
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss.
CITY OF SAN JUAN CAPISTRANO )
I, ERNEST A. THOMPSON, City Clerk of the City of San Juan
Capistrano, California, hereby certify the foregoing Resolution No.
70-9-28-2 was duly adopted by the City Council of said City at a
regular meeting thereof held on the 28th day of September, 1970,
and passed by a unanimous vote of said Council.
IN WITNESS WHEREOF, I have hereunto set my hand and seal.
lerk
City Clerk