Resolution Number 80-8-6-714'7
RESOLUTION NO. 80-8-6-7
COMPLETION OF CAMINO CAPISTRANO AHFP 940 AND 984
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF SAN JUAN CAPISTRANO, CALIFORNIA, DECLARING
WORK TO BE COMPLETED AS TO PLANS AND
SPECIFICATIONS FOR THE CONSTRUCTION OF CAMINO
CAPISTRANO AHFP 940 AND 984, SCHEDULE "A"
WHEREAS, on the 5th day of July, 1979, the City of San
Juan Capistrano entered into a contract with Sully -Miller Contracting
Company for the construction of Camino Capistrano AHFP 940 and
984; and,
WHEREAS, the Director of Public Works has evaluated the
final quantities and cost figures and recommends approval.
NOW, THEREFORE, the City Council of the City of San Juan
Capistrano does resolve as follows:
SECTION 1. That the work required to be performed by
said contractor has been completed.
SECTION 2. That the total cost of said work is in the
amount of $378,349.45.
SECTION 3. That the work is hereby accepted and
approved.
SECTION 4. It is further ordered that a "Notice of
Completion" be recorded, on behalf of the City, in the office of
the County Recorder of the County of Orange within ten (10) days
of the date of this Resolution.
PASSED, APPROVED AND ADOPTED this 6th day of
August 1 1980, by the following vote, to wit:
AYES:
NOES:
ABSENT:
ATTEST:
Councilmen Friess, Schwartze, Thorpe,
Buchheim and Mayor Hausdorfer
None
No
CITY- CLFy C
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss.
CITY OF SAN JUAN CAPISTRANO )
I, MARY ANN HANOVER, City Clerk of the City of San Juan
Capistrano, California, DO HEREBY CERTIFY that the foregoing is a
true and correct copy of Resolution No. 80-8-6-7 , adopted by
the City Council of the City of San Juan Capistrano, California,
at a regular meeting thereof held on the 6th day of
August , 1980 .
,rte 01 IM
OVER, CITY CLERK
-1_
1.4 8 ,
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss.
CITY OF SAN JUAN CAPISTRANO )
and says:
AFFIDAVIT OF POSTING
MARY ANN HANOVER, being first duly sworn, deposes
That she is the duly appointed and qualified City
Clerk of the City of San Juan Capistrano;
That in compliance with State laws of the State of
California and in further comEpliance with City Resolution
No. 79-2-21-7 and on the 8th day of August 1980
she caused to be posted:
RESOLUTION NO. 80-8-6-7
being: COMPLETION OF CAMINO CAPISTRANO AHFP 940 AND 984
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF SAN JUAN CAPISTRANO, CALIFORNIA, DECLARING
WORK TO BE COMPLETED AS TO PLANS AND
SPECIFICATIONS FOR THE CONSTRUCTION OF CAMINO
CAPISTRANO AHFP 940 AND 984, SCHEDULE "A"
in three (3) public places in the City of San Juan Capistrano,
to wit:
The Administration Building;
The San Juan Hot Springs Dance Hall;
The Orange County Public Library.
CHECK LIST yp _ g-(_ - 7
ORD. NO_...__._ RES. NO.----
...... (�' Mayor has signed
....... Clerk has signed
City Seal stamped
...........
All blanks typed in
..Absent"----._.�-------- ---------
..-----..............
.Noes"......_..-�:_-......--`--'-- ..............
_........ Typed in Official Record Book
-------- Posted to Classifie Cards /
............. Copies sent to... .GS
........ -.... Legal Publication ordered to be published
(date) - ...------- ------- -----
No. Affidavits ....... ----- _
.....-.-
_..
No. Printed copies required _.... -....._..
Remarks........ .--------------------------- ...--- ..-- ---- --- ..----- ._,....
-2-
MARY ANNOVER, City Clerk