Resolution Number 84-11-6-3RESOLUTION NO. 84-11-6-3
115
TENTATIVE PARCEL MAP 84-851
(CAPISTRANO INDUSTRIAL CENTER)
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF SAN JUAN CAPISTRANO, CALIFORNIA, APPROVING
TENTATIVE PARCEL MAP 84-851 (CAPISTRANO
INDUSTRIAL CENTER)
WHEREAS, the applicant, Capistrano Industrial Center,
3906 Calle Ariana, San Clemente, California, has submitted
Tentative Parcel Map 84-851, proposing to subdivide approximately
8.98 acres of land into four industrial lots, located on Lots 2
through 10 of Tract 10564; and,
WHEREAS, the City's Environmental Review Board has
determined that the proposed project will not have a significant
effect on the environment, has accordingly issued a Negative
Declaration for the project, and has otherwise carried out all
requirements of the California Environmental Quality Act; and,
WHEREAS, the City Planning Commission has forwarded the
parcel map to the City Council recommending approval; and,
WHEREAS, a public hearing has been duly advertised and
held to review and receive public testimony on the application;
and,
WHEREAS, the City Council of the City of San Juan
Capistrano finds and determines as follows:
1. The proposed project, as conditioned, and its
design and improvements are consistent with the
4.0 Industrial Park designation on the General
Plan Map and are otherwise consistent with all
other Elements of the General Plan.
2. The proposed project, as conditioned, conforms to
all applicable requirements of Title 9 of the
City's Municipal Code (Land Use) and is consistent
with the approved concept plans for Parcels 3 and
4 (Architectural Control 84-9).
3. The project site is physically suitable for the
type and density of the proposed development.
4. The design and improvements of the proposed
project will not cause substantial environmental
damage; nor will said design or improvements
avoidably injure wildlife or their habitat.
5. The design or improvements of the proposed project
will not cause serious public health problems.
6. The design or improvements of the proposed project
will not conflict with easements acquired by the
public at large for access through or use of
property within the proposed project.
-1-
-11-'6
7. The design or improvements of the proposed project
will not interfere with the maintenance or
preservation of an historical site.
NOW, THEREFORE, BE IT RESOLVED, that the City Council
of the City of San Juan Capistrano does hereby approve Tentative
Parcel Map 84-851, subject to the following conditions:
Landscaping Installation - Landscaping shall be
installed as follows:
(a) Erosion control landscaping for all
manufactured slopes shall be installed
immediately after the certification of rough
grading by the City.
(b) Street trees and all other non -erosion -
control landscaping shall be installed in
accordance with the landscape plan approved
by the Planning Commission. No final
building inspection shall be conducted for
any industrial unit within a given parcel
until all landscaping has been installed for
that parcel and approved by the Department of
Community Planning and Development.
2. Signal Participation - The applicant shall
participate in the future signalization of Avenida
Aeropuerto and Camino Capistrano. Said
participation shall be the pro -rata share as
determined by the City Engineer.
3. Private Streets - The following private street
shall be designed and constructed in accordance
with Section 9-4.103 of the Municipal Code:
(a) The developer shall provide for a dedication
of a 24 foot wide public service access
easement. This access easement shall be
provided over a portion of Lots 2 and 3.
This easement shall be provided as a means of
public circulation between Calle Aviador and
Calle Perfecto.
4. CC&Rs - Conditions, Covenants and Restrictions
shall be submitted which provide for continued
landscape maintenance of all landscaping within
the public right-of-way and required 10 -foot
landscape buffer area for Tentative Parcel Map
84-851. Said CC&Rs shall require each individual
parcel owner to maintain the landscaping on the
subject lot and adjacent public right-of-way.
Said CC&Rs shall be approved as to form and
content by the Director of Public Works and City
Attorney, and reviewed and approved by the City
Council prior to recordation of a final tract map.
-2-
11'7
5. Water - Water transmission and distribution
aci ities shall be designed, constructed, and
dedicated in accordance with Section 9-4.109 of
the Municipal Code and the requirements of the
Capistrano Valley Water District. Such
distribution facilities and appurtenances shall be
approved by the County Fire Marshal.
Slopes - All manufactured slopes shall be designed
and constructed in accordance with Sections
9-3.505 and 9-4.112 of the Municipal Code. All
such slopes shall be 2:1 ratio or flatter.
7. Other Improvements - Driveways, pedestrian ways,
bikeways, equestrian trails, utility
undergrounding, street lights, traffic signals,
drainage facilities, and sanitary sewers shall be
located and constructed in accordance with Article
9-4.1 (Design Standards and Requirements) of the
Municipal Code and adopted City policy.
8. Geotechnical Study - A geotechnical feasibility
study shall be completed to determine the seismic
safety and soils stability of all proposed grading
and development within the project. The report
shall be reviewed and approved by the City
Engineer prior to approval of a final map.
9. Fees - All required fees shall be paid prior to
approval of a final map.
PASSED, APPROVED AND ADOPTED this 6th day of
November , 1984 , by the following vote, to wit:
AYES: Councilmen Friess, Bland, Buchheim,
Schwartze, and Mayor Hausdorfer
NOES: None
ABSENT: None
Y L AU DORFER, MAYO
ATTEST:
-3-
-118
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss.
CITY OF SAN JUAN CAPISTRANO )
I, MARY ANN HANOVER, City Clerk of the City of San Juan
Capistrano, California, DO HEREBY CERTIFY that the foregoing is a
true and correct copy of Resolution No. 84-11-6-3 , adopted by
the City Council of the City of San Juan Capistrano, California,
at a regular meeting thereof held on the 6th day of
November F 1984 .
(SEAL)----F7%�`
MARY ANN NOVE , CITY CLERK
STATE OF CALIFORNIA
COUNTY OF ORANGE ) ss. AFFIDAVIT OF POSTING
CITY OF SAN JUAN CAPISTRANO )
MARY ANN HANOVER, being first duly sworn, deposes
and says:
That she is the duly appointed and qualified City Clerk
of the City of San Juan Capistrano;
That in compliance with State laws of the State
California and in further compliance with City Resolution
No. 83-12-20-3 and on the 8th day of November ,
she caused to be posted:
RESOLUTION NO. 84-11-6-3
being: TENTATIVE PARCEL MAP 84-851
(CAPISTRANO INDUSTRIAL CENTER)
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF SAN JUAN CAPISTRANO, CALIFORNIA, APPROVING
TENTATIVE PARCEL MAP 84-851 (CAPISTRANO
INDUSTRIAL CENTER)
of
1984 ,
in three (3) public places in the City of San Juan Capistrano,
to wit: City Hall; Old Fire Station Recreation Complex; Orange
County Public Library.
CHECK LIST
ORD. NO_...._.--- RPS. NO.._......_
Mayor has signed
._ Ir Clerk has signed
City Seal stamped
......... All blanks typed in
"Absent.. .... �----- ..._.---......
"Noes.. ... -.... $.---- ............._..----------------
.......---- Typed in Official Record Book
....._------ Posted to Classified Cards -
............. Copies sent[o.�JvsT.. j..-�j_Gv_-�,. j
.....!�' Legal Publication ordered to be published
-- (date) ----- .. - .---..._......_....---_........
No. Affidavits .. --------- .....--------- -.....---- --
No. Printed copies required ..--------- '7__.......
Remarks
Fi
-4-
CLERK
MARY
ANN
YANOVER, CITY
San
Juan
Capistrano,
California
-4-