Resolution Number 88-1-5-1391
RESOLUTION NO. 88-1-5-1
COMPLETION OF ASPHALT CONCRETE OVERLAY -
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN
JUAN CAPISTRANO, CALIFORNIA, DECLARING WORK TO BE
COMPLETED AS TO PLANS AND SPECIFICATIONS FOR THE
CONSTRUCTION OF ASPHALT CONCRETE OVERLAY - GANADO
ROAD, GALANO WAY AND ORO PLACE (SULLY -MILLER
CONSTRUCTION COMPANY)
WHEREAS, on the 15th day of September 1987, the City of San Juan
Capistrano entered into a contract with Sully -Miller Construction Company for the
Asphalt Concrete Overlay - Ganado Road, Galano Way and Oro Place; and,
WHEREAS, the Director of Public Works has evaluated the final quantities and
cost figures and recommends approval.
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of San
Juan Capistrano, as follows:
SECTION 1. That the work required to be performed by said Contractor
has been completed.
SECTION 2. That the total cost of said work is in the amount of
$38,384.25.
SECTION 3. That the work is hereby accepted and approved.
SECTION 4. The City Clerk is directed to forthwith forward a "Notice of
Completion" to the County Recorder of the County of Orange for recording.
PASSED, APPROVED, AND ADOPTED this 5th day
of January '1988.
z 0/0 /7 ��f�d'�
ANTHONY BLAND, MAYOR
ATTEST:
-1-
392
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss
CITY OF SAN JUAN CAPISTRANO )
I, MARY ANN HANOVER, City Clerk of the City of San Juan Capistrano,
California, DO HEREBY CERTIFY that the foregoing is a true and correct copy of
Resolution No. SR -1-S-1 adopted by the City Council of the City of San Juan
CAPISTRANO, California, at a regular meeting thereof held on the 5th day
of January , 1988, by the following vote:
AYES: Councilmen Schwartze, Friess, Buchheim,
Hausdorfer, and Mayor Bland
NOES: None
ABSENT: None
(SEAL) 22
MARY AN ANOVER, CITY CLERK
-2-