Resolution Number 89-1-3-2385
RESOLUTION NO. 89-1-3-2
COMPLETION OF OSO PARK IMPROVEMENTS
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN
JUAN CAPISTRANO, CALIFORNIA, DECLARING WORK TO BE
COMPLETED AS TO PLANS AND SPECIFICATIONS FOR THE
CONSTRUCTION OF OSO PARK IMPROVEMENTS (CARLSON
LANDSCAPING COMPANY
WHEREAS, on the 16th day of February, 1988, the City of San Juan Capistrano
entered into a contract with Carlson Landscaping Company for the construction of Oso
Park Improvements; and,
WHEREAS, the Director of Public Works has evaluated the final quantities and
cost figures and recommends approval.
NOW, THEREFORE BE IT RESOLVED by the City Council of the City of San
Juan Capistrano, as follows:
SECTION 1. That the work required to be performed by said contractor
has been completed.
SECTION 2. That the total cost of said work is in the amount of
$25,930.60.
SECTION 3. That the work is hereby accepted and approved.
SECTION 4. The City Clerk is directed to forthwith forward a "Notice of
Completion" to the County Recorder of the County of Orange for recording.
PASSED, APPROVED, AND ADOPTED this 3rd day
of January , 1989.
ATTEST:
CITY CLE
G RY HAUSDORFER,MAY R
-1-
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss
CITY OF SAN JUAN CAPISTRANO )
I, MARY ANN HANOVER, City Clerk of the City of San Juan Capistrano,
California, DO HEREBY CERTIFY that the foregoing is a true and correct copy of _
Resolution No. 89-1-3-2 adopted by the City Council of the City of San Juan
Capistrano, California, at a regular meeting thereof held on the 3rd day
Of January , 1989, by the following vote:
AYES: Councilman Schwartze, Friess, Bland and
Mayor Hausdorfer
NOES: None
ABSENT: Councilman Buchheim
(SEAL)
MARY ANN A OVER, CITY CLERK