Loading...
Resolution Number 88-9-6-2RESOLUTION NO. 88-9-6-2 245 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN JUAN CAPISTRANO, CALIFORNIA, DECLARING WORK TO BE COMPLETED AS TO PLANS AND SPECIFICATIONS FOR THE CONSTRUCTION OF THE CAMINO CAPISTRANO ASPHALT CONCRETE OVERLAY, I-5 RAMPS AT SAN JUAN CREEK ROAD TO 1,700 FEET SOUTH (CAR WASH) (BLAIR PAVING, INC.) WHEREAS, on the 21st day of June, 1988, the City of San Juan Capistrano entered into a contract with Blair Paving, Inc., for the Camino Capistrano Asphalt Concrete Overlay, I-5 Ramps at San Juan Creek Road to 1,700 Feet South (Car Wash); and, WHEREAS, the Director of Public Works has evaluated the final quantities and cost figures and recommends approval. NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of San Juan Capistrano, as follows: SECTION 1. That the work required to be performed by said Contractor has been completed. SECTION 2. That the total cost of said work is in the amount of $64,162.09. SECTION 3. That the work is hereby accepted and approved. SECTION 4. The City Clerk is directed to forthwith forward a "Notice of Completion" to the County Recorder of the County of Orange for recording. PASSED, APPROVED, AND ADOPTED this 6th day of September , 1988. GARY . HAUSDO E ,MAYO ATTEST: CITY CL7K -1- 246 STATE OF CALIFORNIA ) COUNTY OF ORANGE ) ss CITY OF SAN JUAN CAPISTRANO ) I, MARY ANN HANOVER, City Clerk of the City of San Juan Capistrano, California, DO HEREBY CERTIFY that the foregoing is a true and correct copy of Resolution No. 88-9-6-2 adopted by the City Council of the City of San Juan Capistrano, California, at a regular meeting thereof held on the 6th day of September , 1988, by the following vote: AYES: Councilmen Friess, Buchheim, Bland, and Mayor Hausdorfer NOES: None ABSENT: Councilman Schwartze (SEAL) MARY AN,�VKANOVER, CITY CLERK -2-