Resolution Number 88-8-2-2RESOLUTION NO. 88-8-2-2
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN
JUAN CAPISTRANO, CALIFORNIA, DECLARING WORK TO BE
COMPLETED AS TO PLANS AND SPECIFICATIONS FOR THE
CONSTRUCTION OF MEREDITH CANYON AND ALTO
CAPISTRANO SLURRY SEAL PHASE I (DOUG MARTIN
CONTRACTING CO., INC.)
WHEREAS, on the 7th day of June, 1988, the City of San Juan Capistrano
entered into a contract with Doug Martin Contracting Co., Inc., for the Meredith Canyon
and Alto Capistrano Slurry Seal Phase 1; and,
WHEREAS, the Director of Public Works has evaluated the final quantities and
cost figures and recommends approval.
NOW, THEREFORE BE IT RESOLVED by the City Council of the City of San
Juan Capistrano, as follows:
SECTION 1. That the work required to be performed by said contractor
has been completed.
SECTION 2. That the total cost of said work is in the amount of
$19,110.12.
SECTION 3. That the work is hereby accepted and approved.
SECTION 4. The City Clerk is directed to forthwith forward a "Notice of
Completion" to the County Recorder of the County of Orange for recording.
PASSED, APPROVED, AND ADOPTED this
of August , 1988.
4GARY 5 ORFE , MAY
ATTEST:
CITY CLERK
2nd
day
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss
CITY OF SAN JUAN CAPISTRANO )
I, MARY ANN HANOVER, City Clerk of the City of San Juan Capistrano,
California, DO HEREBY CERTIFY that the foregoing is a true and correct copy of
Resolution No. 88-8-2-2 adopted by the City Council of the City of San Juan
Capistrano, California, at a regular meeting thereof held on the 2nd day
of August , 1988, by the following vote:
AYES: Councilmen Friess, Buchheim, Bland, and
Mayor Hausdorfer
NOES: None
ABSENT: Councilman Schwartze
(SEAL)
MARY ANN H OVER, UtTY CLERK
-2-