Resolution Number 90-12-11-2RESOLUTION NO. 90-12-11-2
A RESOLUTION OF THE CITY OF COUNCIL OF THE CITY OF SAN
JUAN CAPISTRANO, CALIFORNIA, DECLARING WORK TO BE
COMPLETED AS TO PLANS AND SPECIFICATIONS FOR THE
CONSTRUCTION OF STREET IMPROVEMENTS - CAMINO
CAPISTRANO FROM 1100' SOUTH TO 1540' SOUTH OF AVENIDA
AEROPUERTO
WHEREAS, the City of San Juan Capistrano has entered into an agreement
with Barwick Datsun Agency for the installation of curb and gutter, sidewalk, pavement
and street lights on Camino Capistrano from 1100' south to 1540' south of Avenida
Aeropuerto; and,
WHEREAS, the installation of the improvements was performed by Whiting -
Turner Contracting Corporation; and,
WHEREAS, the Director of Engineering and Building has evaluated the final
quantities and cost figures and recommends approval.
NOW, THEREFORE, the City Council of the City of San Juan Capistrano, does
resolve as follows:
SECTION 1. That the work required to be performed by said contractor
has been completed.
SECTION 2. That the total cost of said work is in the amount of $109,306.
SECTION 2. That the work is hereby accepted and approved.
SECTION 3. The City Clerk is directed to forthwith forward a "Notice of
Completion" to the County Recorder of the County of Orange for recording.
PASSED, APPROVED, AND ADOPTED this 11th day
of December ,1990.
ATTEST:
i
w-
w
-
e
KENNETH E. FRIE S, MAYPR
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss
CITY OF SAN JUAN CAPISTRANO )
1, CHERYL JOHNSON, City Clerk of the City of San Juan Capistrano,
California, DO HEREBY CERTIFY that the foregoing is a true and correct copy of
Resolution No. 90-12-11-2 adopted by the City Council of the City of San Juan
Capistrano, California, at a regular meeting thereof held on the 11th day
Of Derpmh r , 1990, by the following vote:
AYES: Councilmen Jones, Buchheim, Vasquez
and Mayor Hausdor£er
NOES: None
ABSENT: Councilman Hausdorfer
(SEAL)
CHERYL JOf-iNSON, CITY CLERK
-2-