Resolution Number 06-01-03-01RESOLUTION NO. 06-01-03-01
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN JUAN
CAPISTRANO, CALIFORNIA, DECLARING WORK TO BE COMPLETED
AS TO PLANS AND SPECIFICATIONS FOR THE MAJOR SEWER
REPAIRS (SOUTHWEST PIPELINE AND TRENCHLESS CORP. (CIP
No. 728)
WHEREAS, on the 19th day of April, 2005, the City of San Juan Capistrano
entered into a contract with Southwest Pipeline and Trenchless Corp. 539 W. 1401h
Street, Gardena, CA 90248 for construction of Major Sewer Repairs Capital
Improvement Project; and
WHEREAS, the Director of Engineering and Building has evaluated the final
quantities and cost figures and recommends approval.
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of San
Juan Capistrano, does resolve as follows:
SECTION 1. That the work required to be performed by said Contractor has
been completed.
' SECTION 2. That the total cost of said work is $403,235.80.
SECTION 3. That the work is hereby accepted and approved.
SECTION 4. That the City Clerk is directed to forward forthwith a Notice of
Completion to the County Recorder of the County of Orange for
Recording.
PASSED, APPROVED, AND ADOPTED this 3`d day of January 2006.
ATTEST:
R. MONAHAN, CITY CLERK
Page 1 of 1 01-03-2006
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss.
CITY OF SAN JUAN CAPISTRANO )
I, MARGARET R. MONAHAN, appointed City Clerk of the City of San Juan Capistrano, do hereby
certify that the foregoing Resolution No. 06-01-03-01 was duly adopted by the City Council of the
City of San Juan Capistrano at a Regular meeting thereof, held the 3m day of January 2006, by
the following vote:
AYES: COUNCIL MEMBERS: Hart, Bathgate, Soto, Allevato and Mayor Swerdlin
NOES: COUNCIL E ER: None
ABSENT:, COUNCI M R:�None
R. MONAHAN, City Clerk