Resolution Number 94-11-15-1328
RESOLUTIONNO.
COMPLETION OF GOLDEN REDGE-MRM DRAIN
(KUNO'S CRAWLER AND BACKHOEI
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN JUAN
CAPISTRANO, CALIFORNIA, DECLARING WORK TO BE
COMPLETED AS TO PLANS AND SPECIFICATIONS FOR THE
GOLDENRIDGE STORM DRAIN, AT GOLDENRIDGE LANE AND
SOMERSET DRIVE TO 400 FEET EAST (KUNO'S CRAWLER AND
BACKHOE)
WHEREAS, on the 5th day of April, 1994, the City of San Juan Capistrano entered
into a contract with Kuno's Crawler and Backhoe, 3163 Inclinado, San Clemente, 92672, for
construction of the Goldenridge Storm Drain; and,
WHEREAS, the Director of Engineering and Building has evaluated the final
quantities and cost figures and recommends approval.
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of San
Juan Capistrano as follows:
' SECTION L That the work required to be performed by said Contractor has been
completed.
SECTION 2. That the total cost of said work is in the amount of $44,093.04.
SECTION 3. That the work is hereby accepted and approved.
SECTION 4. That the City Clerk is directed to forthwith forward a "Notice of
Completion" to the County Recorder of the County of Orange for recording.
PASSED, APPROVED, AND ADOPTED this 15th day of
Noveraber 1994.
OLLE C ELL, MAYOR
ATTEST:
2:J� � �
' CITY CLERW 61
329
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss
CITY OF SAN JUAN CAPISTRANO )
I, CHERYL JOHNSON, City Clerk of the City of San Juan Capistrano, California,
DO HEREBY CERTIFY that the foregoing is a true and correct copy of Resolution No.
94-11-15-1 adopted by the City Council of the City of San Juan Capistrano, California,
at a regular meeting thereof held on the 15th day of November 1994, by the
following vote:
AYES: Council Members Jones, Ilausdorfer, Nash and
Mayor Campbell
NOES: None
ABSTAIN: None
ABSENT: Council Member Vasquez
(SEAL)
CHERYL JO S , CITY CLERK
-2-