Resolution Number 02-03-05-01RESOLUTION NO. 02-03-05-01
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN JUAN
CAPISTRANO, CALIFORNIA, DECLARING WORK TO BE COMPLETED
AS TO PLANS AND SPECIFICATIONS FOR EL CAMINO REAL/SPRING
STREET STORM DRAIN PROJECT (MATTHEW & STEWART CO. INC.)
WHEREAS, on the 7th day of August, 2001, the City of San Juan Capistrano entered
into a contract with Matthew & Stewart Co. Inc., 2841 Gardena Avenue, Signal Hill, CA
90806 for construction of EI Camino Real/Spring Street Storm Drain Project; and,
WHEREAS, the Director of Engineering and Building has evaluated the final
quantities and const figures and recommends approval.
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of San Juan
Capistrano, does resolve as follows:
SECTION 1. That the work required to be performed by said Contractor has
been completed.
SECTION 2. That the total cost of said work is $84,711.24.
SECTION 3. That the work is hereby accepted and approved.
SECTION 4. That the City Clerk is directed to forward forthwith a Notice of
Completion to the County Recorder of the County of Orange
for recording.
PASSED, APPROVED AND ADOPTED this 5`h day of March 2002.
DIANE BATHGAT 'MAYOR
ATTEST:
WA—bftARET R. MONAHAN, CITY CLERK
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss.
CITY OF SAN JUAN CAPISTRANO )
I, MARGARET R. MONAHAN, appointed City Clerk of the City of San Juan Capistrano, do
hereby certify that the foregoing Resolution No. 02-03-05-01 was duly adopted by the City
Council of the City of San Juan Capistrano at a regular meeting thereof, held the 5th day of
March 2002, by the following vote:
AYES: COUNCIL MEMBERS: Hart, Campbell, Swerdlin, Gelff and Mayor Bathgate
NOES: COUNCIL MEMBERS: None
ABSENT: COUNCIL MEMBERS: None
R. MONAHAN, City Clerk