Resolution Number 04-01-06-02RESOLUTION NO. 04-01-06-02
A RESOLUTION OF THE CITY OF SAN JUAN CAPISTRANO,
CALIFORNIA, DECLARING WORK TO BE COMPLETED AS TO PLANS
AND SPECIFICATIONS FOR THE EMERGENCY GENERATOR
ELECTRICAL CONNECTIONS PROJECT (CIP NO. 760) (TAMANG
ELECTRIC)
WHEREAS, on the 18th day of July, 2003, the City of San Juan Capistrano
entered into a contract with Tamang Electric for the Emergency Generator Electrical
Connections Project; and,
WHEREAS, the Engineer of Record has evaluated the final quantities and cost
figures and recommends approval per its letter dated December 12, 2003; and,
NOW, THEREFORE, BE IT RESOLVED, by the City of San Juan Capistrano as
follows:
SECTION 11. That the work required to be performed by said Contractor has
been completed.
SECTION 2. That the total cost of said work is in the amount of $49,841.
SECTION 3. That the work is hereby accepted and approved.
SECTION 4. That the City Clerk is directed to forthwith forward a "Notice of
Completion" to the County Recorder of the County of Orange for recording.
ATTEST:
PASSED, APPROVED, AND ADOPTED this 6th day of January 2004.
JOE SOTO, MAYPR
)J -Z+ R, �/�
R. MONAHAN, CITY CLERK
1 01-06-2004
STATE OF CALIFORNIA
COUNTY OF ORANGE )ss.
CITY OF SAN JUAN CAPISTRANO
1, MARGARET R. MONAHAN, appointed City Clerk of the City of San Juan Capistrano, do
hereby certify that the foregoing Resolution No. 04-01-06-02 was duly adopted by the City
Council of the City of San Juan Capistrano at a regular meeting thereof, held the 6 th day of
January 2004, by the following vote:
AYES: COUNCIL MEMBERS: Gelff, Bathgate, Swerdlin, Hart and Mayor Soto
NOES: COUNCIL MEMBERS: None
ABSTAIN: COUNCI� M BE N ne
j I In 1�r 7
, City Clerk