B22-1297 - 25863-MP STONEHILL DR10/05/23
25863 - MP Stonehill Drive
Service Pedestal Installation
738518
Elecnor Belco Electric, Inc.
14320 Albers Way
Chino, CA 91710
1
9/29/2022Melissa Ibarra
Melissa Ibarra
909 993-5470
melissa.ibarra@elecnor.com
B22 1297
Additional Address Info:
PROCEDURE FOR INSTALLATION
1. PHONE DIG ALERT "811" AT LEAST TWO DAYS PRIOR TO TRENCHING FOR LOCATION OF UNDERGROUND UTILITIES.
2. Phone Service Coordinator at 949-361-8066 for the following:
- 3 Working days prior to trenching to arrange pre-meet with inspector and initiate trenching process.
- After excavation of trench, installation of conduit and service entrance equipment at meter location, CALL FOR INSPECTION. Do
not cover conduit without inspector's written approval to backfill.
- When trench is backfilled and compacted, CALL FOR INSPECTION.
- If service entrance equipment is installed after backfill, CALL FOR INSPECTION OF THE EQUIPMENT.
3. Meter cannot be set until inspector has approved installation, including service equipment, and receipt of city/county/state inspection
Metering: Self Contained. Test Bypass Facilities Reqd Meter Clips: 4
Utilities Maximum Contribution to Fault Current: 42000Phase: 1# of Wires: 3
Voltage: 120/240
Bend Info: 3" 90 DEG 36"R DB60Bend Type: TRANSFORMER
Riser Quad: Stop Trench: from PoleLadder Arms:
Standards Page: Handhole Lid Shall Read:
Structure #: D239066Station ID #: 1073-889
Temp Service Charge due on First Bill $ 0.00
Assessor's Parcel Number: Additional Information:
City/County inspection should be received prior to 2:00 p.m. on the same day as the disconnection of service to allow the SDG
&E crew enough time for reconnection of the service on the same day.
Number/Size of Main Switch: 1/200Service Panel Rating: 200
Conduit Size: 1-3"Conduit Installed By:
Customer Phone #: 310-530-7277Customer POC: Alex Nikolakopulos
Wanted Date: O/I
Job #:
ELECTRIC UNDERGROUND METER & SERVICE LOCATION
Customer Copy
Project Title: GANAHL LUMBER - TRAFFIC SIGNAL MP
Notification #: 300000391884
Project Address: 25863 STONEHILL DR MP
Customer Type: Commercial
Date Prepared: 10/03/2022
Project City: SAN JUAN CAPISTRANO
SDGE Contact: Service Coordinator Contact Info: SERVICE DESK,949-361-8066
Service Type: UG SERVICE NEW
TB: 972-A5
SERVICE ATTACHMENT POINT AND/OR METER LOCATION:
Customer to set new 200a meter ped at proposed location. Customer is responsible for trench, backfill, surface repair, Compaction,
Pull tape and 3" PVC conduit from ex. sta. 1073-889 to new meter ped. Face meter towards driven way and
permanently label with address " 25863-mp". Maintain a 3x3 clearance. CALL 949-361-8066 to schedule a pre trench meeting. JOB
SKETCH provided
X SDG&E Application Required-Call: 1-800-411-7343
Municipal Inspection required By: CITY OF SAN JUAN CAPISTRANO
Bend Installed By: SDG&E
Handhole Installed By:
Traffic Control Permit Required
Excavation/Encroachment Permits Required By: Customer
Joint Trench With: Electric Gas Telco CATV
Right of Way Required
Meter height -- 4'0'' min. (3'0" min. for multiple installation) -- 6'3" max. From finish grade to centerline of meter base. Meters are required to
be readily accessible 24 hours per day. Meters must be located in a safe area free of any potentially hazardous or dangerous condition.
Provide 3-ft. x 3-ft. clear and level working space in front of meter. Where meter room is proposed, contact the planner at the nearest SDG&E
office. Meter bases and meter service disconnects must be located at or immediately adjacent to each other and be identified with address
and unit number.
If SDG&E encounters hazardous or toxic material while performing construction of your project, SDG&E will halt work immediately and it will
be your responsibility to remove and or clean up all hazardous or toxic material prior to SDG&E continuing construction. SDG&E shall have no
liability or obligation whatsoever to cleanup, remove or remediate any hazardous or toxic materials discovered during the course of
construction unless it is through negligence of SDG&E.
Customer-owned facilities to receive gas service are subject to all applicable local and state of California inspection authority requirements.
Building address and/or houseline must be permanently identified prior to meter set. Per Rule 16.A.1.a. In compliance with Section 783 of
the Public Utilities Code, SDG&E will apply only those construction and design specifications, standards, terms, and conditions that are
applicable to a new extension of service project for the 18 months following the date the application for a new extension of service project is
approved. Keep this notice with your building permit.
Planned By: Albert LeDon Phone#: 6195789697
January 6, 2021
San Diego Gas & Electric
662 Camino De Los Mares
San Clemente CA 92673
Re: Address Request for Meter Pedestal
To those concerned:
Per Ganahl Lumber’s request, the following address has been approved for a meter pedestal in
the City of San Juan Capistrano. Please update your records accordingly. For further assistance,
please contact James Fournier, GIS Specialist, at (949) 443-6355.
Address as Listed:
25863-MP STONEHILL DR
Thank you for your cooperation.
Sincerely,
_|át _t
Lisa La
Senior Permit Technician
949-443-6349
lla@sanjuancapistrano.org