B24-0171 - 26966 CALLE ESPERANZAFINAL
07/26/24
Additional Address Info:
PROCEDURE FOR INSTALLATION
1. PHONE DIG ALERT "811" AT LEAST TWO DAYS PRIOR TO TRENCHING FOR LOCATION OF UNDERGROUND UTILITIES.
2. Phone Operations Assistant at 949-361-8061 for the following:
- 3 Working days prior to trenching to arrange pre-meet with inspector and initiate trenching process.
- After excavation of trench, installation of conduit and service entrance equipment at meter location, CALL FOR INSPECTION. Do
not cover conduit without inspector's written approval to backfill.
- When trench is backfilled and compacted, CALL FOR INSPECTION.
- If service entrance equipment is installed after backfill, CALL FOR INSPECTION OF THE EQUIPMENT.
3. Meter cannot be set until inspector has approved installation, including service equipment, and receipt of city/county/state inspection
Metering: Self-Contained Meter Clips: 4
Utilities Maximum Contribution to Fault Current: 10000Phase: 1# of Wires: 3
Voltage: 120/240
Bend Info: 3" 90 DEG 36"R DB60Bend Type: TRANSFORMER
Riser Quad: Stop Trench: from PoleLadder Arms:
Standards Page: Handhole Lid Shall Read:
Structure #: D4795956979Station ID #: 795-278
Temp Service Charge due on First Bill $ 0.00
Assessor's Parcel Number: Additional Information:
To minimize the electrical outage, you are advised to schedule a morning disconnect with an afternoon reconnect. There is no charge
for this service. Before you change out your meter consider (1) SDG&E needs advance notice to schedule a crew and (2) SDG&E will not
reconnect the service without municipal approval on the new panel. Please contact the City of San Juan Capistrano regarding permits
and inspections. City/County inspection should be received prior to 2:00 p.m. on the same day as the disconnection of service to
allow the SDG&E crew enough time for reconnection of the service on the same day.
Number/Size of Main Switch: 1/200Service Panel Rating: 200
Conduit Size: 3"Conduit Installed By: CUSTOMER
Customer Phone #: 713-446-8984Customer POC: anthony quinton
Wanted Date: ON INSPECTION
Job #: 530000352645
ELECTRIC UNDERGROUND METER & SERVICE LOCATION
Customer Copy
Project Title: SOT OC 26966 CALLE ESPERANZA DR US
Notification #: 300000704099
Project Address: 26966 CALLE ESPERANZA
Customer Type: Residential(1-2 Units)
Date Prepared: 04/01/2024
Project City: SAN JUAN CAPISTRANO
SDGE Contact: Operations Assistant Contact Info: SERVICE DESK,949-361-8061
Service Type: UG SERVICE REWIRE/RELOCATION
TB: 0972-D4
SERVICE ATTACHMENT POINT AND/OR METER LOCATION:
Locate the new 200 amp meter panel on the West wall, in existing location as indicated on sketch. Customer is to provide all
excavation, trench, 3" conduit, backfill, compaction, 3/4" pulling and measuring tape in conduit and surface repair from transformer
D4795956979 to new meter panel. Take conduit to within distance as instructed by SDG&E inspector. Prior to digging, please contact
the Trench Desk at 949-361-8061 schedule a pre-meet with your trench inspector. Customer is to provide and maintain a 3 foot by 3
foot clear and level workspace in front of the new electric meter panel. See SDG&E Service and Standards Guide pages for
specifications.
SDG&E Application Required-Call: 1-800-411-7343
Municipal Inspection required By: CITY OF SAN JUAN CAPISTRANO
Bend Installed By: SDG&E
Handhole Installed By:
Traffic Control Permit Required
Excavation/Encroachment Permits Required By:
Joint Trench With:
Right of Way Required
Meter height -- 4'0'' min. (3'0" min. for multiple installation) -- 6'3" max. From finish grade to centerline of meter base. Meters are required to
be readily accessible 24 hours per day. Meters must be located in a safe area free of any potentially hazardous or dangerous condition.
Provide 3-ft. x 3-ft. clear and level working space in front of meter. Where meter room is proposed, contact the planner at the nearest SDG&E
office. Meter bases and meter service disconnects must be located at or immediately adjacent to each other and be identified with address
and unit number.
If SDG&E encounters hazardous or toxic material while performing construction of your project, SDG&E will halt work immediately and it will
be your responsibility to remove and or clean up all hazardous or toxic material prior to SDG&E continuing construction. SDG&E shall have no
liability or obligation whatsoever to cleanup, remove or remediate any hazardous or toxic materials discovered during the course of
construction unless it is through negligence of SDG&E.
Customer-owned facilities to receive gas service are subject to all applicable local and state of California inspection authority requirements.
Building address and/or houseline must be permanently identified prior to meter set. Barrier posts may be required based on field conditions
at any time prior to meter set as determined by the SDG&E Representative. Per Rule 16.A.1.a. In compliance with Section 783 of the Public
Utilities Code, SDG&E will apply only those construction and design specifications, standards, terms, and conditions that are applicable to a
new extension of service project for the 18 months following the date the application for a new extension of service project is approved. Keep
this notice with your building permit.
All installations performed under this order must meet SDG&E standards unless a written deviation has been approved.
Planned By: Melissa Riggs Phone#: 6196765787