22-1114_JAMBOREE HOUSING CORPORATION_Exhibit M-3EXHIBIT M-3
TO
AFFORDABLE HOUSING DISPOSITION AND DEVELOPMENT AGREEMENT
(City Hall — Paseo Adelanto Mixed Use Permanent Supportive Housing)
City Hall Project Schedule of Performance
[Attached Behind This Page]
EXHIBIT M-3
61147.80021\40183270.13
Paseo Adelanto City Hall Schedule
Item
DESIGN AND PLAN CHECK
Developer Submit to Plan Check
City 1st Round Plan Check Comments Received
Developer Submit to Plan Check 2nd Review
City Provide 2nd Round Plan Check Comments Received
Developer Submit to Plan Check 3rd review
City Provide 3rd Round Plan Check Comments
Final Submittal
Grading Permit Ready to Issue
Building Permit Ready to Issue
CLOSING
City Move Out Deadline
Target Closing Date
Outside Closing Date
CONSTRUCTION
Commence Bidding
Final SOV
Final GC Contract City Hall
Start of Construction/Notice to Proceed
Developer Provides CPM Construction Schedule
Mobilize and Start Construction/Demolition
Rough Grading Commencement
Underground Utilities
Foundations
Framing
Mechanical, Electrical, Plumbing (MEPs) Sign Offs
Interior Finishes
Site Work
Final Inspections
Energize/Meter Set
Certificate of Occupancy
Construction Completion
Post -Construction Completion
Solar Set
Code Required Commissioning
Owner Commissioning (FF&E, etc.)
Certificate of Completion
EXHIBIT M-3
Outside Date
8/29/2022
Within 20 days after receipt of 1st Submittal
Within 21 days after receipt of 1st Comments
Within 15 days after receipt of 2nd Submittal
Within 21 days after receipt of 2nd Comments
Within 15 days after receipt of 3rd Submittal
Within 21 days after receipt of 3rd Comments
Within 5 days after final submittal, in no event later than 12/10/22
Within 5 days after final submittal, in no event later than 12/10/22
Outside Date
12/1/2022
12/12/2022
12/23/2022
Outside Date
Within 15 days after Developer 2nd Plan Check Submittal
Within 60 days after Commencement of Bidding
Within 5 days after Final SOV
60 days after Close of Escrow
Within 30 days after Close of Escrow
Within 60 days of Notice to Proceed
Within 9 weeks of Start of Demolition
Within 9 weeks of Start of Rough Grading
Within 6 weeks of Start of Underground Utilities
Within 10 weeks of Start of Foundations
Within 8 weeks of Start of Framing
Within 22 weeks of Start of MEPs
Within 10 weeks of Start of Interior Finishes
Within 6 weeks of Start of Site Work
Within 6 weeks of Start of Final Inspections
Within 8 weeks of Energy/Meter Set
24 months after Closing Date
Within 10 weeks after Construction Completion
Within 3 weeks of Certificate of Occupancy
Within 4 weeks of Certificate of Occupancy
Within 2 weeks of Commissioning
Within 1 week of Certificate of Completion
EXHIBIT M-4
TO
AFFORDABLE HOUSING DISPOSITION AND DEVELOPMENT AGREEMENT
(City Hall — Paseo Adelanto Mixed Use Permanent Supportive Housing)
City Hall Project Budget
[Attached Behind This Page]
EXHIBIT M-4
61147.80021 \40183270.13