22-1114_ORTIZ ENTERPRISES, INC._Retention Release Letter
November 14, 2022
Ortiz Enterprises, Inc.
6 Cushing, Suite 200
Irvine, CA 92618-4221
Re: San Juan Capistrano – Quiet Zone Improvement at Rancho Capistrano Crossing
Project
To Whom it May Concern:
On October 3, 2022, the City of San Juan Capistrano accepted work as completed for the
construction of the Quiet Zone Improvements at Rancho Capistrano Crossing Project.
A copy of the recorded Notice of Completion is enclosed for your records.
The retention will be payable upon 35 days from recording of the Notice of Completion.
The Notice was recorded on October 24, 2022; therefore, the final payment in the amount
of $6,290.78 may be released on November 28, 2022. If you have any questions, please
do not hesitate to contact Paul Meshkin, Senior Civil Engineer at (949) 443-6350.
Sincerely,
Christy Jakl, CMC
Assistant City Clerk
cc: Tom Toman, Public Works Director
George Alvarez, Traffic Engineer
Ken Al-Iman, Chief Financial Officer
Jeanien Marsh, Senior Accounting Specialist