19-0627_SANCON ENGINEERING_Preliminary Notice CALIFORNIA PRELIMINARY NOTICE
THIS NOTICE IS GIVEN PURSUANT TO CALIFORNIA CIVIL CODE§§8034(a),8102,8200 ET SEQ.PRIVATE WORKS
•
AND CALIFORNIA CIVIL CODE§§8034(b),8102,9300 ET SEQ PUBLIC WORKS
THIS IS NOT A LIEN.THIS IS NOT A REFLECTION ON THE INTEGRITY OF ANY CONTRACTOR OR SUBCONTRACTOR
YOU ARE HEREBY NOTIFIED THAT...
CONSTRUCTION LENDER or Reputed Lender(if any) EBS UTILITIES ADJUSTING,INC
OR SURETY OR OTHER INTERESTED PARTY (name of person or firm furnishing labor,services,equipment or material)
1320 E.6TH STREET STE.100
(address of person or firm furnishing labor,services,equipment or material)
DUDEK CORONA,CA 92879-1700
27372 CALLE ARROYO has furnished or will furnish labor,services,equipment or material
SAN JUAN CAPISTRANO,CA 92675 of the following general description:
ADJUST STREET UTILITIES
(general description of the labor,services,equipment of material furnished
or to be furnished)
for the building,structure or other work of improvement located at:
OWNER or PUBLIC AGENCY ANNUAL SEWER REHABILITATION PROGRAM
or Reputed Owner (on public work) CIP 18701
(on private work) SAN JUAN CAPISTRANO
(address or description of job site sufficient for identification)
The name of the person or firm who contracted for the purchase of such
CITY OF SAN JUAN CAPISTRANO GRBCON
32400 PASEO ADELANTO 5114 ELTON STREET, BALDWIN PARK,CA 91706
SAN JUAN CAPISTRANO,CA 92675 This is an estimated amount,and is not a limitation of claimant's final amount
$ 50,000.00
This is an estimated amount,and is not a limitation of claimant's final amount
Notice to Property owner
DIRECT CONTRACTOR or EVEN THOUGH YOU HAVE PAID YOUR CONTRACTOR IN FULL,if the
Reputed Contractor,if any person or firm that has given you this notice is not paid in full for labor,
services,equipment,or material provided or to be provided to your
SANCON TECHNOLOGIES INC construction project,a lien may be placed on your property.Foreclosure
5841 ENGINEER DR of the lien may lead to loss of all or part of your property.You may wish
HUNTINGTON BEACH,CA 92649 to protect yourself against this by(1)requiring your contractor to provide
a signed release by the person or firm that has given you this notice
before making payment to your contractor,or(2)any other method that
is appropriate under the circumstances.
SUBCONTRACTOR This notice is required by law to be served by the undersigned as a
person or firm who contracted for statement of your legal rights.This notice is not intended to reflect upon
purchase of such labor,services,equipment or materials the financial condition of the contractor or the person employed by you
on the construction project.
If you record a notice of cessation of completion of your construction
GRBCON project,you must within 10 days after recording,send a copy of the notice
5114 ELTON STREET of completion to your contractor and the person or firm that has given you
BALDWIN PARK, CA 91706 this notice.The notice be sent by registered or certified mail.Failure to
send the notice will extend the deadline to record a claim of lien.You are
not required to send the notice if you are a residential homeowner of a
dwelling containing four or fewer.units.
D ed: 6/27/2019
Signal e:Jessica Licea a Title: Accounts Receivable
Telephone Number: (951)279-6869 ext.101
JOB# 195057
I, Jessica Licea , declare that I served copies of the above PRELIMINARY NOTICE(PRIVATE WORK/PUBLIC WORK)by First Class
Certified or Registered Mail service,postage prepaid,addressed to each of the parties at the addresses shown above on 06/27/2019.
I declare under penalty of peripry under the laws of the State of California that the foregoing is true and correct.
Executed at CORONA,California on 06/27/2019