20-1120_ECO RESOURCES, INC AND ARB, INC_Construction AgreementAGREEMENT FOR THE CONSTRUCTION OF THE
SAN JUAN BASIN DESALTER PROJECT
between
ECO RESOURCES, INC.
and
ARB, INC.
4XOW.1
410828 }
412574.1
Capistrano Valley Water District Page i Construction Agreement
San Juan Basin Desalter Project
UON84
AMA12
412574.1
TABLE OF CONTENTS
Page
ARTICLE1- GENERAL..........................................................................................................................2
ARTICLE 2 - CONTRACTOR'S SERVICES AND RESPONSIBILITIES......................................14
ARTICLE 3 - DESIGN -BUILDER'S SERVICES AND RESPONSIBILITIES................................27
ARTICLE 4 - HAZARDOUS MATERIALS AND DIFFERING SITE CONDITIONS ...................30
ARTICLE5 - CONTRACT TIMES.......................................................................................................32
ARTICLE 6 - GUARANTEED MAXIMUM PRICE...........................................................................35
ARTICLE 7 - PROCEDURE FOR PAYMENT....................................................................................36
ARTICLE8 - TERMINATION..............................................................................................................42
ARTICLE 9 - REPRESENTATIVES OF THE PARTIES...................................................................47
ARTICLE 10 - INSURANCE AND BONDS..........................................................................................47
ARTICLE11- INDEMNIFICATION....................................................................................................49
ARTICLE12 - CHANGES......................................................................................................................51
412574 1
TABLE OF CONTENTS
(continued)
Page
ARTICLE 13 - DISPUTE RESOLUTION.............................................................................................57
ARTICLE 14 - MISCELLANEOUS.......................................................................................................58
EXHIBIT A — SCOPE OF WORK ..........................................
EXHIBIT B — CONTRACTOR PERMITS .............................
....................................................1
...................................................1
EXHIBIT C — PROJECT SCHEDULE AND MILESTONES.............................................................1
EXHIBIT D — INSURANCE REQUIREMENTS..................................................................................1
EXHIBIT E — CONCEPTUAL DESIGN DRAWINGS.........................................................................1
EXHIBIT F TIME AND MATERIAL RATES, UNIT PRICES AND EQUIPMENT COSTS .......... I
EXHIBIT G SERVICE CONTRACT.....................................................................................................1
EXHIBIT H CONTRACTOR'S PROPOSAL.........................................................................................1
Capistrano Valley Water District
San Juan Basin Desalter Project
Uesas4
4vwaz
412574.1
Page ii
Construction Agreement
AGREEMENT FOR THE CONSTRUCTION OF THE
SAN JUAN BASIN DESALTER PROJECT
This Agreement (the "Agreement") is made as of this _ day of , 2002 (the
"Effective Date"), by and between ECO Resources, Inc. ("Design -Builder") and
("Contractor") which entities are sometimes individually referred to herein
as "Party" and collectively as the "Parties."
RECITALS
A. Design -Builder has entered into an agreement (the "Service Contract") with the
Capistrano Valley Water District ("Owner") entitled Service Contract for the Design,
Construction, Financing and Operation of the San Juan Basin Desalter Project (the
"Project"). A copy of the Service Contract, including all appendices thereto, is attached
hereto as Exhibit G.
B. Under the terms of the Service Contract, Design -Builder has agreed to design, construct,
operate and maintain the Project, and also to undertake certain obligations to guarantee
bonds being issued to finance the costs of the Project.
C. The Service Contract was entered into by Owner and Design -Builder pursuant to
California Government Code Sections 5956, et seq., which provisions allow local
governmental agencies to use private investment capital to develop, finance, design,
build, operate and maintain public infrastructure projects. The costs of the Project will be
financed from the proceeds of bonds issued and sold for that purpose. The bond holders
will be represented by a trustee who shall, in addition to the Owner, have authority and
oversight over the work of the Project and payments to Design -Builder (the "Trustee").
The Trustee shall be represented during the project by an independent engineer, retained
by Trustee for that purpose (the "Independent Engineer"). Under the terms of the Service
Contract, payments for the work of the Project will be made by the Trustee on behalf of
the Owner.
D. Design -Builder has retained Boyle Engineering, Inc. (the "Project Engineer") to prepare
the Project Design in accordance with Owner's requirements as set forth in the Service
Contract.
E. Contractor is entering into this Agreement on the basis of conceptual drawings attached
hereto as Exhibit E prepared by the Project Engineer and with knowledge of Owner's
requirements for the construction of the Project as set forth in the Service Contract.
Contractor understands that the Project Design has not been prepared as of the date of
Capistrano Valley Water District Page 1 Construction Agreement
San Juan Basin Desalter Project
4108281
412574.1
this Agreement and that the Project will be constructed on a "fast track" basis with
portions of the Project Design being completed as necessary to maintain the progress of
the work of the Project and Owner's schedule requirements as set forth in the Service
Contract. Contractor understands and agrees that time is strictly of the essence under the
terms of the Service Contract and that Design -Builder may be subject to substantial and
cumulative liquidated damages if Owner's schedule requirements are not met.
F. Design -Builder wishes to retain Contractor to furnish all work required to construct the
Project in accordance with the Project Design prepared by the Project Engineer and in
accordance with Owner's requirements as set forth in the Service Contract. In retaining
Contractor to construct the Project, Design -Builder is relying on Contractor's experience
constructing like projects of similar magnitude and complexity under equivalent time
constraints.
NOW THEREFORE, for good and valuable consideration, including the mutual
covenants and conditions contained herein, Design -Builder and Contractor agree as follows:
AGREEMENT
ARTICLE 1— GENERAL
1.1 Basic Purpose
Design -Builder has contracted with Owner to provide the services necessary for the design and
construction of the Project as set forth in the Service Contract. Design -Builder has retained
Contractor to furnish all construction services Design -Builder is required to perform under the
Service Contract. Design -Builder has separately retained the Project Engineer to furnish all
design services Design -Builder is required to perform under the Service Contract. It is the intent
of the Parties that, except as otherwise provided herein, Design -Builder and Contractor shall
have the same rights, responsibilities, and obligations to one another for the construction of the
Project as Owner and Design -Builder under the Service Contract. Design -Builder is retaining
Contractor for the purpose of furnishing all labor, services, equipment, materials, facilities,
supplies, tools, incidentals and temporary utilities necessary to construct the Project in strict
accordance with this Agreement and the documents and materials incorporated by reference
herein including, without limitation, the applicable provisions of the Service Contract and the
Project Design.
1.2 Definitions
Terms used in this Agreement shall have the meanings set forth in the Service Contract unless
otherwise provided below. Key terms defined in the Service Contract and used in this
Agreement are set forth below.
Capistrano Valley Water District Page 2 Construction Agreement
San Juan Basin Desalter Project
410828.1
00.8
412574.1
Agreement refers to this Agreement for the Construction of the San Juan Basin Desalter
Project between Eco Resources, Inc. and ARB, Inc. including the Contract Documents.
Applicable Laws means (1) any federal, state or local law, code, regulation, consent order
or agreement; (2) any formally adopted and generally applicable rule, requirement,
determination, standard, policy, implementation schedule or order of any Governmental Body
having appropriate jurisdiction; (3) any established interpretation of law or regulation utilized by
an appropriate Governmental Body if such interpretation is documented by such regulatory body
and generally applicable; and (4) any Governmental Approval, in each case having the force of
law and applicable from time to time to (a) the construction, equipping, possession, permitting
start-up, testing of water treatment systems relating to the Project; (b) the delivery, treatment,
storage or supply of water; (c) any other transaction or matter contemplated hereby (including,
without limitation, any of the foregoing which pertain to the construction of the Project,
including, but not limited to safety, fire, environmental protection, labor relations, building
codes, the payment of prevailing or minimum wages and non-discrimination). Applicable Law
shall be deemed to include the requirements contained in the final mitigated negative declaration
approved by the District in connection with the Project.
Booster Pumping Station means the Strawberry Booster Pumping Station, for boosting
the pressure of Finished Water conveyed from the Plant to the Water System, including all
related buildings, structures, pipes, valves and equipment, as more particularly described in
Appendix 1 of the Service Contract.
Booster Pumping Station Site means the parcels of real property described in Appendix 1
of the Service Contract on which the Booster Pumping Station is to be constructed by the
Contractor.
Brine means any sanitary wastewater and any brine, liquid or water -carried pollutant
resulting from the treatment of Raw Water that is not capable of, or is prohibited by Applicable
Law or the Service Contract from, being recycled at the Plant and requires disposal in
accordance with the Service Contract.
CERCLA means the Comprehensive Environmental Response, Compensation, and
Liability Act, 42 U.S.C. 9601 et seq., and applicable regulations promulgated thereunder, each as
amended from time to time.
Change in Law means any of the following acts, events or circumstances to the extent
that compliance therewith materially increases the cost of performing or materially increases the
scope of the party's obligations hereunder:
(a) the adoption, amendment, promulgation, issuance, modification, repeal or
written change in administrative or judicial interpretation of any Applicable Law on or
after the Effective Date of this Agreement, unless such Applicable Law was on or prior to
Capistrano Valley Water District Page 3 Construction Agreement
San Juan Basin Desalter Project
4108281
�I OR2R.2
412574.1
the Effective Date duly adopted, promulgated, issued or otherwise officially modified or
changed in interpretation, in each case in final form, to become effective without any
further action by any Governmental Body;
(b) the order or judgment of any Governmental Body issued on or after the
Effective Date (unless such order or judgment is issued to enforce compliance with
Applicable Law which was effective as of the Effective Date) to the extent such order or
judgment is not the result of willful or negligent action, error or omission or lack of
reasonable diligence of Contractor or of Design -Builder, whichever is asserting the
occurrence of a Change in Law; provided, however, that the contesting in good faith or
the failure in good faith to contest any such order or judgment shall not constitute or be
construed as such a willful or negligent action, error or omission or lack of reasonable
diligence;
(c) except with respect to any Governmental Approval required for the
construction of the Project as provided within (b) below pertaining to exclusions from
"Change in Law",—a delay in the review, issuance or renewal of, or the suspension,
termination or interruption of any Governmental Approvals relating to the Work, or the
imposition of a term, condition or requirement which is more stringent or burdensome
than the standards to be followed by Contractor under this Agreement in connection with
the issuance, renewal or failure of issuance or renewal of, any Governmental Approval to
the extent that such occurrence is not the result of willful or negligent action, error or
omission or a lack of reasonable diligence of the Contractor or of Design -Builder,
whichever is asserting the occurrence of a Change in Law; provided, however, that the
contesting in good faith or the failure in good faith to contest any such occurrence shall
not be construed as such a willful or negligent action or lack of reasonable diligence.
It is specifically understood, however, that none of the following shall constitute a "Change in
Law":
(a) a change in the nature or severity of the actions typically taken by a
Governmental Body to enforce compliance with Applicable Law which was effective as
of the Effective Date; or
(b) acts, events and circumstances with respect to which the Contractor has
assumed the permitting risk relating to the Project under this Agreement;
City refers to the City of San Juan Capistrano.
Concentrate Disposal Line means the transmission line for the conveyance from the Plant
to the South Orange County Wastewater Authority PC5 Ocean Outfall of Brine concentrate
resulting from the treatment of Raw Water at the Plant, including all related buildings, structures,
pipes, valves and equipment, as more particularly described in Appendix 1. The Concentrate
Disposal Line includes the Concentrate Disposal Line Site.
Capistrano Valley Water District Page 4 Construction Agreement
San Juan Basin Desalter Project
41 ON381
410828
412574.1
Concentrate Disposal Line Site means the real property or rights of way described in
Appendix 1 on or over which the Concentrate Disposal Line is to be constructed.
Conceptual Design Drawings refers to the drawings and plans attached to this Agreement
as Exhibit E.
Construction Governmental Approvals means those Governmental Approvals which are
necessary in order to commence and complete construction of the Project.
Construction Manager refers to a representative appointed by Design -Builder.
Construction Schedule refers to the schedule for performance of the Work and
Completion of the Project prepared by Contractor, and accepted by the Design -Builder pursuant
to the terms of this Agreement including, without limitation, the provisions appearing at Exhibit
C to this Agreement.
Cost Substantiation has the meaning specified in Section 16.5 of the Service Contract.
Contract Documents has the meaning specified in Section 1.3 of this Agreement.
Guaranteed Maximum Price has the meaning specified in Article 6 of this Agreement.
Contract Times refers to times for performance of the Work of the Project set forth at
Article 5 and Exhibit C to this Agreement.
Contractor refers to ARB, Inc.
Contractor Fault means any breach (including the untruth or breach of any Contractor
representation or warranty herein set forth), failure, non-performance or non-compliance by the
Contractor with respect to its obligations and responsibilities under this Agreement to the extent
not attributable to any Uncontrollable Circumstance or Design -Builder Fault, and which
materially and adversely affects Design -Builder's rights and obligations or ability to perform
under this Agreement or the Service Contract.
Day or Days refers to calendar days unless stated otherwise.
Deliverable Material has the meaning specified in Section 6.12 of the Service Contract.
Design Requirements means the design requirements for the Project set forth in the
Appendices to the Service Contract, as the same may be changed or modified in accordance
therewith.
District means the Capistrano Valley Water District.
Capistrano Valley Water District Page 5 Construction Agreement
San Juan Basin Desalter Project
U08284
Oo=
412574.1
District Engineer means either the City's Director of Public Works or other engineer
employed or designated by the District from time to time in writing by the District.
District Fault means any breach (including the untruth or breach of any District
representation or warranty set forth in the Service Contract), failure, non-performance or non-
compliance by the District under the Service Contract with respect to its obligations and
responsibilities under the Service Contract to the extent not attributable to any Uncontrollable
Circumstance or Design -Builder Fault, and which materially and adversely affects Design -
Builder's or Contractor's rights, obligations or ability or costs to perform under this Agreement.
Effective Date means the date first set forth above in the preamble to this Agreement.
Encumbrances means any Lien, lease, mortgage, security interest, charge, judgment,
judicial award, attachment or encumbrance of any kind with respect to the Project, other than
Permitted Encumbrances.
EPA means the United States Environmental Protection Agency and any successor
agency.
Exit Test Procedures and Standards means the test procedures and standards for the
performance test of the Project to be conducted by Design -Builder prior to termination or
expiration of the Service Contract as set forth in Appendix 18 to the Service Contract.
Final Completion means completion of the requirements of Section 7.16(A)(1), (A)(3),
(A)(4) as applicable, (A)(7), as applicable, (A)(8)as applicable, (A)(9), and 7.16 (B)(2) of the
Service Agreement; completion of the Final Punch List work;, and Completion all any and all
other construction -related responsibilities described in this Agreement.
Final Punch List has the meaning specified in subsection 7.15(A), as applicable, of the
Service Contract.
Finished Water means Raw Water which has been treated at the Plant in accordance with
the Service Contract and delivered to the Finished Water Transmission Line.
Finished Water Transmission Line means the transmission line for the conveyance of
Finished Water to the Water System, including all related buildings, structures, pipes, valves and
equipment, as more particularly described in Appendix 1 of the Service Contract. The Finished
Water Transmission Line includes the Finished Water Transmission Line Site.
Finished Water Transmission Line Site means the real property or rights of way described
in Appendix 1 of the Service Contract on or over which the Finished Water Transmission Line is
to be constructed.
Capistrano Valley Water District Page 6 Construction Agreement
San Juan Basin Desalter Project
Good Engineering and Construction Practice means those methods, techniques,
standards and practices which, at the time they are to be employed and in light of the
circumstances known or reasonably believed to exist at such time, are generally recognized and
accepted as good design, engineering, equipping, installation, construction and commissioning
practices for the design, construction and improvement of capital assets in the municipal water
treatment industry as followed in the southern California region of the United States.
Governmental Approvals means all orders of approval, permits, licenses, authorizations,
consents, certifications, inspections, tests, exemptions, rulings, entitlements and approvals issued
by a Governmental Body of whatever kind and however described which are required under
Applicable Law to be obtained or maintained by any person with respect to the Contract
Services.
Governmental Body means any federal, state, regional or local legislative, executive,
judicial or other governmental board, agency, authority, commission, administration, court or
other body, or any official thereof having jurisdiction.
Hazardous Material means any waste, substance, object or material deemed hazardous
under Applicable Law including, without limitation, "hazardous substance" as defined under
CERCLA and "hazardous waste" as defined under RCRA.
Independent Engineer means a nationally -recognized qualified consulting engineer or
firm of consulting engineers representing the Trustee and having experience with respect to
obtaining of governmental approvals for, design, construction, testing, operation, maintenance,
repair, replacement and management of water treatment facilities and in monitoring construction
progress and reviewing related payment applications.
Legal Proceeding means every action, suit, litigation, arbitration, administrative
proceeding, and other legal or equitable proceeding having a material bearing upon this Service
Contract or the performances of the parties hereunder, and all appeals therefrom.
Lien means any and every lien against the Project or against any monies due or to become
due from the District to Design -Builder under the Service Contract or to Contractor under this
Agreement, for or on account of the Work, including mechanics' liens and stop notices.
Loss -and -Expense means any and all actual loss, liability, forfeiture, obligation, damage,
fine, penalty, judgment, deposit, cost, expense, charge, Tax, or expense, including all Fees and
Costs, except as explicitly excluded or limited under any provision of the Service Contract.
Metropolitan Agreement means the 1998 San Juan Basin Desalter Project Agreement
between the Metropolitan Water District of Southern California, the Municipal Water District of
Capistrano Valley Water District Page 7 Construction Agreement
San Juan Basin Desalter Project
410828 1
410828.1
412574.1
Orange County and the San Juan Basin Authority, dated December 4, 1998, as amended,
modified, clarified and implemented from time to time.
Metropolitan means the Metropolitan Water District of Southern California.
Non -Conforming Work means defective material, workmanship and/or improper
installation or construction performed by Contractor which fails to conform with the
requirements of this Agreement.
Notice to Proceed means a notice issued by Design -Builder to Contractor to commence
the Work.
Owner shall mean the Capistrano Valley Water District or its assignee or successor -in -
interest as described in the Service Contract.
Plant means the San Juan Capistrano Desalter Plant, consisting generally of the treatment
works for production of Finished Water from Raw Water. The Plant includes the Plant Site, the
Project Structures and Project Equipment involved in water treatment and production, as further
described in Appendix 1 of the Service Contract, The Plant will be located proximate to 32400
Paseo Adelanto, San Juan Capistrano, California.
Plant Site means the parcel of real property described in Appendix 1 of the Service
Contract on which the Plant is to be constructed.
Pre -Existing Environmental Condition means, and is limited to, (1) the presence
anywhere in, on or under the Project on the Effective Date of this Agreement, if not disclosed to
Contractor as of said Effective Date, of underground storage tanks (for the storage of chemicals
or petroleum products), and (2) the presence anywhere in, on or under the Project, whether or not
disclosed to Contractor as of the Effective Date, of Hazardous Materials.
Project means the Sites and the Project Improvements.
Project Design refers to the Conceptual Design Drawings and to the drawings, plans,
specifications and other documents and materials prepared and to be prepared as the Project
progresses by the Project Engineer describing the requirements for construction of the Project in
accordance with the provisions of the Service Contract including, without limitation, all
approved submittals, executed change orders and responses to requests for information.
Project Engineer refers to Boyle Engineering, Inc.
Project Equipment means all manufactured equipment, property or assets, whether or not
constituting personal property or fixtures, constituting part of the Project Improvements
Capistrano Valley Water District Page 8 Construction Agreement
San Juan Basin Desalter Project
4109181
4in42R z
412574.1
including tanks, pumps, membrane systems, and water processing and treatment equipment;
instrumentation and control systems; remote monitoring and communications systems; filtration,
disinfection, corrosion control and water treatment systems; and chemical mixing, metering,
storage, handling and feed systems. Appendix 1 generally lists the types of equipment that are
expected to be installed in the Project and to constitute "Project Equipment".
Project Improvements means the Plant, the Wells, the Raw Water Transmission Line, the
Booster Pumping Station, the Finished Water Transmission Line, the Concentrate Disposal Line,
and any Capital Modifications made thereto from time to time. After Acceptance, the Booster
Pumping Station shall become part of the Water System, and shall not be considered part of the
Project Improvements.
Project Schedule refers to the times by which the various stages of both the design and
construction of the Project must be performed pursuant to the Service Contract so as to satisfy
Design -Builder's obligations to Owner.
Project Sites shall have the same meaning as the Sites.
Project Structures means all structures, buildings, concrete basins and metal tanks, piping
and other buried infrastructure, other than Project Equipment, constituting part of the Project
Improvements.
Property Lease means the Property Lease to be entered into by the District and the Issuer
providing for the lease of the Sites from the District to the Issuer, as the same may be amended
from time to time in accordance therewith.
Provisional Acceptance Date has the meaning specified in Section 7.8 of the Service
Contract.
Raw Water means any water pumped from the Wells and conveyed to the Plant for
treatment hereunder.
Raw Water Transmission Line means the transmission lines for the conveyance of Raw
Water to the Plant, including all related buildings, structures, pipes, valves and equipment, as
more particularly described in Appendix 1. The Raw Water Transmission Line includes the Raw
Water Transmission Line Site.
Raw Water Transmission Line Site means the real property or rights of way described in
Appendix 1 on or over which the Raw Water Transmission Line is to be constructed.
RCRA means the Resource Conservation and Recovery Act, 42 U.S.C.A. §6901 et seq.,
and applicable regulations promulgated thereunder, each as amended from time to time.
Capistrano Valley Water District Page 9 Construction Agreement
San Juan Basin Desalter Project
41083&1
AI US 2
412574.1
Scheduled Acceptance Date has the meaning specified in Section 7.12 of the Service
Contract.
Schedule of Values has the meaning specified in Exhibit C to this Agreement and shall be
used by Design -Builder, in conjunction with Contractor's Construction Schedule, as the basis for
making all payments to Contractor under this Agreement.
Service Contract refers to the Service Contract for the Design, Construction, Financing
and Operation of the San Juan Basin Desalter Project between the Capistrano Valley Water
District and ECO Resources, Inc. dated September 3 2002, including all Appendices thereto and
documents incorporated by reference therein.
Sites means the Plant Site, the Wellfield, the Booster Pumping Station Site, the Raw
Water Transmission Line Site, the Finished Water Transmission Line Site and the Concentrate
Disposal Line Site.
Specified Site Conditions means, and is limited to: (1) the presence at the Project of
subsurface structures, materials or conditions having historical, archaeological, religious or
similar significance; (2) the presence at the Project of functioning subsurface structures used by
Utility providers on, underneath, near or adjacent to the Project if not disclosed to Contractor as
of the Effective Date; (3) the presence at the Project of any habitat of an endangered or protected
species as provided in Applicable Law.
Subcontractor means every person (other than employees of Contractor) employed or
engaged by Contractor (including all subcontractors and suppliers of every tier) to perform or
furnish any portion of the Work, whether for the furnishing of labor, materials, equipment,
supplies, services or otherwise.
Substantial Completion has the meaning specified in Section 7.4.2 of this Agreement.
Tax means any tax, fee, levy, duty, impost, charge, surcharge, assessment or withholding,
or any payment -in -lieu thereof, and any related interest, penalty or addition to tax.
Uncontrollable Circumstance means any act, event or condition that is beyond the
reasonable control of the party relying thereon as justification for not performing an obligation or
complying with any condition required of such party under this Agreement, and that materially
interferes with or materially increases the costs of performing its obligations hereunder (other
than payment obligations) to the extent that such act, event or condition is not the result of the
willful or negligent act, error or omission, failure to exercise reasonable diligence, or breach of
this Service Contract on the part of such party.
(1) Inclusions. Subject to the foregoing, Uncontrollable Circumstances shall include,
and shall not be limited to, the following:
Capistrano Valley Water District Page 10 Construction Agreement
San Juan Basin Desalter Project
(a) a Change in Law, except as provided in (1) and (m) of item 2 below;
(b) the existence of a Pre -Existing Environmental Condition;
(c) the existence of a Specified Site Condition;
(d) the treatment of Raw Water having parameters which are outside the range
established by the Design Raw Water Quality Parameters;
(e) contamination of the Project from groundwater, soil or airborne Hazardous
Material migrating from sources outside of the Project and not caused by Contractor
Fault;
(f) naturally occurring events (except weather conditions normal for the Service
Area, including 20 days of severe weather as defined in Section 5.5.2 hereof) such as
landslides, underground movement, earthquakes, fires, tornadoes, hurricanes, floods,
lightning, epidemics and other acts of God;
(g) explosion, sabotage or similar occurrence, acts of a declared or undeclared public
enemy, extortion, war, blockade or insurrection, riot or civil disturbance;
(h) labor disputes, except labor disputes involving employees of the Contractor, its
Affiliates, or Subcontractors which affect the performance of the Contract Services;
(i) the failure of any Subcontractor (other than the Contractor) to furnish services,
materials, chemicals or equipment on the dates agreed to, but only if such failure is the
result of an event which would constitute an Uncontrollable Circumstance if it affected
the Contractor directly, and the Contractor is not able after exercising all reasonable
efforts to timely obtain substitutes;
0) the failure of any appropriate Governmental Body or private utility having
operational jurisdiction in the area in which the Project is located to provide and maintain
Utilities to the Project which are required for the performance of this Agreement, except
as provided in paragraph (h) of item (2) below;
(k) the absence of ownership rights by the District or the City in the Sites,
notwithstanding the representation of the District with respect thereto in subsection
2.1(H) of the Service Contract;
(1) except as provided in (k) of item 2 below, the existence of any right, restriction,
servitude, license, easement, right of way, limitation, qualification, exception, adverse
claim, Encumbrance or Lien on the Sites which either is unrecorded or not listed as an
exception on the Preliminary Title Reports as provided in the Service Contract and which
materially and adversely affects the performance of the Work;
(m) the preemption, confiscation, diversion, destruction or other interference in
possession or performance of materials or services by a Governmental Body in
connection with a public emergency or any condemnation or other taking by eminent
domain of any material portion of the Project;
(n) a violation of Applicable Law by a person other than the affected party or its
Subcontractors;
(o) any Legal Proceeding described in subsection 4.5(A)(9) of the Service Contract,
or any order or decree issued by a court of competent jurisdiction or other Governmental
Capistrano Valley Water District Page 11 Construction Agreement
San Juan Basin Desalter Project
410818.1
412574.1
Body which delays or prevents the construction or operation of the Project, where such
order or decree is not caused by Contractor Fault;
(p) District Fault or District -requested Change Orders not due to Contractor Fault;
and
(2) Exclusions. It is specifically understood that, without limitation, none of the
following acts, events or circumstances shall constitute Uncontrollable Circumstances:
(a) any act, event or circumstance that would not have occurred if the affected party
had complied with its obligations hereunder;
(b) changes in interest rates, inflation rates, wage rates, insurance premiums,
commodity prices, currency values, exchange rates or other general economic conditions;
(c) changes in the financial condition of the Contractor affecting its ability to perform
their respective obligations;
(d) the consequences of error, neglect or omissions by Contractor or its
Subcontractors in the performance of the Work;
(e) union or labor work rules, requirements or demands which have the effect of
increasing the number of employees employed at the Project or otherwise increasing the
cost to the Contractor of performing the Contract Services;
(f) any and all surface, subsurface and other conditions affecting the Sites, which
may increase cost of performing or cause delay in the performance of the Work,
including particularly any subsurface geotechnical conditions, except those constituting
Pre -Existing Environmental Conditions and Specified Site Conditions;
(g) mechanical failure of equipment to the extent not resulting from a condition that
is listed in the "Inclusions" Section of this definition;
(h) power outages not caused by third -party Utilities or other Uncontrollable
Circumstances;
(i) weather conditions normal for the location of the Project,
(k) failure of the Contractor to secure any patent or other intellectual property right
which is or may be necessary for the performance of the Contract Services;
(1) any Change in Law regarding the quality of Finished Water (including the
issuance of any Governmental Approval, the enactment of any statute, or the
promulgation of any regulation) the terms and conditions of which do not impose more
stringent or burdensome requirements on the Contractor than are imposed by the
standards to be followed by Contractor under this Agreement,
Wellfield means the real property described in Appendix 1 to the Service Contract within
which the Wells are to be located and constructed.
Wells means the wells to be constructed by the Contractor hereunder for the production of
Raw Water, including any related structures and equipment.
Work has the meaning specified in Section 2.1 of this Agreement.
Capistrano Valley Water District Page 12 Construction Agreement
San Juan Basin Desalter Project
4408284
41(15.8.2
412574.1
1.3 Contract Documents
The Contract Documents include the following:
1.3.1 Change Orders executed or issued pursuant to the terms of this Agreement;
1.3.2 This Agreement and Exhibits hereto and attachments incorporated by reference herein
including, without limitation, the following:
1 the Service Contract;
.2 Appendix 1 to the Service Contract (Project Description);
.3 Appendix 5 to the Service Contract (Design Requirements);
.4 Attachment 1 to Appendix 5 to the Service Contract (Well Construction
Specifications);
5 Appendix 6 to the Service Contract (Design/Build Work Review Procedures);
.6 Appendix 8 to the Service Contract (Acceptance Test Procedures and Standards);
7 Appendix 9 to the Service Contract (Governmental Approvals);
8 Appendix 11, Part 2 of the Service Contract (Required Construction Insurance)
8 Appendix 14 to the Service Contract (Safety and Security Plan);
9 Appendix 17 to the Service Contract (Acknowledged Subcontractors);
10 Appendix 18 to the Service Contract (Exit Test and Transition Plan); and
11 Appendix 21 to the Service Contract (Milestone Payment Schedules), except that
the Milestones listed in said Appendix 21 are incorporated herein for purposes of
Contractor's Construction Schedule and not as the basis or schedule for any
payments by Design -Builder to Contractor under this Agreement.
1.3.3 The Project Design, including all plans, drawings and specifications prepared by the
Project Engineer.
Capistrano Valley Water District
San Juan Basin Desalter Project
uesU.4
1I (IR2R.2
412574.1
Page 13
Construction Agreement
1.4 Interpretation and Intent
1.4.1 Interpretation. The Contract Documents are intended to be complementary and
interpreted in harmony so as to avoid conflict, with words and phrases interpreted
consistent with construction and design industry standards. In the event of any
inconsistency, conflict, or ambiguity between or among the Contract Documents, the
Contract Documents shall take precedence in the order in which they are listed in Section
1.3 hereof with the document described in paragraph 1.3.1 above having the highest
priority.
1.5 Mutual Obligations and Acknowledgments
1.5.1 Design -Builder and Contractor commit at all times to cooperate fully with each other, and
proceed on the basis of trust and good faith, to permit each party to realize the benefits
afforded under the Contract Documents. Design -Builder and Contractor shall perform
their respective responsibilities, obligations and services in a timely manner to facilitate
the other's timely and efficient performance and so as not to delay or interfere with the
other's performance of its obligations under the Contract Documents.
ARTICLE 2 — CONTRACTOR'S SERVICES AND RESPONSIBILITIES
2.1 Scope of Services
In exchange for payment of the Guaranteed Maximum Price in accordance with and subject to
the terms and conditions of this Agreement, Contractor shall furnish all of the labor, services,
equipment, materials and supplies necessary to construct the Project as described in Exhibit A —
Scope of Services, which are referred to collectively in this Agreement as the "Work".
2.2 Delivery of Bonds, Insurance Information, Preliminary Subcontractor List and
Construction Schedule
2.2.1 Within seven (7) days after this Agreement is last executed by the Parties, Contractor
shall furnish to Design -Builder all bonds and proof of insurance documents required by
this Agreement.
2.2.2 Within fourteen (14) days after this Agreement is last executed by the Parties, Contractor
shall furnish its preliminary Construction Schedule to Design -Builder.
2.2.3 Within thirty (30) days after this Agreement is last executed by the Parties, Contractor
shall furnish the list of subcontractors which will perform Work on the Project. To the
extent that subcontractors are added or substituted, Contractor shall give Design -Builder
notice of such addition or substitution as soon as practicable. Design -Builder shall have
Capistrano Valley Water District
San Juan Basin Desalter Project
Page 14
Construction Agreement
the right to approve all of Contractor's subcontractors, which approval shall not be
unreasonably withheld.
2.3 Construction Standards
It is the intent of the Parties that Contractor shall employ Good Engineering and Construction
Practice and that all Work performed by Contractor shall conform to all applicable standards
provided in the Service Contract for the performance of the Work, that the Work shall
specifically include and conform to the provisions appearing at Section 6.5 of the Service
Contract, and that the standards for performance of the Work shall include, without limitation,
the following:
2.3.1 Standards of Workmanship and Materials. Any reference in the Service Contract or this
Agreement to materials, equipment, systems or supplies (whether such references are in
lists, notes, specifications, schedules, or otherwise) shall be construed to require
Contractor to furnish the same in accordance with the grades and standards therefor
indicated in the Service Contract. Where the Service Contract and this Agreement do not
specify any explicit quality or standard for construction materials or workmanship,
Contractor shall use only workmanship and new materials of a quality consistent with
that of construction workmanship and materials specified elsewhere in the Design
Requirements, and the Design Requirements are to be interpreted accordingly.
2.3.2 Technical Standards and Codes. References in this Agreement to all professional and
technical standards, codes and specifications are to the most recently published
professional and technical standards, codes and specifications of the institute,
organization, association, authority or society specified, all as in effect as of the effective
date of the Service Contract. Unless otherwise specified to the contrary, (1) all such
professional and technical standards, codes and specifications - shall apply as if
incorporated in the Design Requirements and (2) if any material revision occurs, to the
Contractor's knowledge, after the effective date of the Service Contract, and prior to
completion of the Work, Contractor shall notify Design -Builder. If so directed by
Design -Builder, Contractor shall perform the Work in accordance with the revised
professional and technical standard, code, or specification as long as Contractor is
compensated, subject to Cost Substantiation, for any additional cost or expense
attributable to any such revision.
Capistrano Valley Water District Page 15 Construction Agreement
San Juan Basin Desalter Project
U08-184
410828 .2
412574.1
2.4 Review of Site and Contract Documents
2.4.1 Contractor represents and warrants that it has examined the Project Sites so as to
reasonably ascertain the nature of the Work and the various conditions affecting the
Work as provided in Section 4.1 of the Service Contract.
2.4.2 Contractor represents and warrants that it has carefully examined the Contract
Documents. Contractor shall have a continuing obligation to promptly, but in no event
more than fifteen (15) days after discovery, provide written notice to Design -Builder of
any errors, inconsistencies or omissions in the Contract Documents, or between the
Contract Documents and Applicable Laws of which Contractor has actual knowledge.
Contractor shall be responsible for the costs of any additional Work and for any damages
resulting from such errors, inconsistencies and omissions that would not have been
required but for Contractor's failure to promptly provide the notice required by this
Section. Contractor's failure to provide the notice required by this Section shall
constitute a waiver of Contractor's right to seek an adjustment in the Guaranteed
Maximum Price or Time based on such errors, inconsistencies or omissions.
2.5 Commencement of Contract Times; Notice to Proceed
The Contract Times shall begin to run upon issuance of the Notice to Proceed by Design -Builder
to Contractor.
2.6 Pre -Construction Conference
2.6.1 Within fourteen (14) days after execution of this Agreement, Design -Builder, Project
Engineer, Contractor and other necessary persons and parties will meet to discuss and
review issues affecting the administration, scheduling and performance of the Work,
including:
1 Owner's requirements and compliance with the requirements of the Service
Contract;
.2 Permit status;
3 Contractor's preliminary Construction Schedule and materials and equipment to
be procured by Contractor having a long lead time for ordering;
4 The Project Design and constructability issues;
Capistrano Valley Water District
San Juan Basin Desalter Project
4108181
aortia
412574.1
Page 16
Construction Agreement
5 Implementation of necessary procedures, including but not limited to those
relating to schedule updates, submittals, and payment, to facilitate the ability of
the parties to perform their obligations under this Agreement;
.6 Designation of Contractor's and Design -Builder's key representatives;
7 The role and authority of the Construction Manager and Project Engineer;
8 Staffing issues;
.9 Project Safety issues;
.10 Form and process for submittal, review and approval of Contractor's requests for
payment;
11 Project reporting requirements;
.12 Project meeting requirements and schedule.
2.6.2 Contractor shall attend all pre -construction conferences with Owner required under the
Service Contract.
2.7 Assistance With Project Design
2.7.1 Contractor shall meet and confer and attend meetings with the Project Engineer and
Design -Builder's representatives to assist the Design -Builder in the preparation of the
Project Design. Such assistance shall include:
.1 Reviewing the Project Design for constructability;
.2 Reviewing the Project Design for consistency with the requirements of the
Service Contract; and
3 Reviewing Project Engineer's schedule for the preparation of the various elements
of the Project Design so that such elements are available to Contractor when
needed to avoid delays, interruptions or other impacts to the progress and
prosecution of the Work.
2.7.2 Notwithstanding any assistance provided by Contractor in the preparation of the Project
Design, and except as provided elsewhere in this Agreement, Contractor shall not be
liable for errors, omissions or inaccuracies in the Project Design.
Capistrano Valley Water District
San Juan Basin Desalter Project
4109391
41(1828.2
412574.1
Page 17
Construction Agreement
2.8 Supervision and Superintendence of the Work; Personnel
2.8.1 Contractor shall supervise, inspect, and direct the Work competently and efficiently,
devoting such attention thereto and applying such skills and expertise as may be
necessary to perform the Work in accordance with the Contract Documents and
Applicable Laws. The Contractor shall be solely responsible for the means, methods,
techniques, sequences, and procedures of construction and all safety precautions and
programs incidental thereto. The Contractor shall be knowledgeable of the
manufacturer's requirements and recommendations relating to the installation of
equipment on the Project. The Contractor shall be responsible to see that the completed
Work complies accurately with the Contract Documents.
2.8.2 The Contractor shall designate in writing and keep on the Project at all times during the
performance of the Work a technically qualified superintendent who is an employee of
the Contractor and who shall not be replaced without written notice to the Design -
Builder. The superintendent will be the Contractor's representative at the Site and shall
have authority to act on behalf of the Contractor. All communications given to the
superintendent shall be as binding as if given to the Contractor.
2.8.3 The Contractor's superintendent shall be present at the Project at all times while work is
in progress and shall be available by phone for emergencies 24 hours per day, 7 days per
week. Contractor shall provide its superintendent's emergency contact information prior
to the commencement of Work.
2.8.4 Contractor shall be aware of and comply with the applicable provisions of Section 6.13 of
the Service Contract regarding Personnel and with respect to the construction of the
Project, Design -Builder's rights as to Contractor under said section shall be the same as
Owner's rights as to Design -Builder.
2.9 Pre -Construction Services
2.9.1 Contractor shall assist Design -Builder regarding the selection of building systems,
materials, and equipment, as well as Project cost, schedule, and construction feasibility
studies with respect to the Work. Such studies shall address, among other things, labor
availability, construction costs, and procurement strategies related to the Work set forth
in the Contract Documents. However, the final decision regarding the selection of the
foregoing items is vested with Design -Builder. Design -Builder acknowledges that
Contractor is not licensed nor qualified to design the Work nor make recommendations
concerning the suitability or compatibility of building systems, materials and equipment.
Design -Builder shall, to the fullest extent permitted by law, indemnify, defend and hold
harmless Contractor, anyone employed directly or indirectly by Contractor, Contractor's
officers, directors, employees and agents, from and against any and all claims, losses,
Capistrano Valley Water District Page 18 Construction Agreement
San Juan Basin Desalter Project
U08284
411!328.2
412574.1
damages, liability and expenses, including attorney fees and expenses, arising out of, in
whole or in part, the design of the Project or any part thereof.
2.9.2 Contractor shall, if requested by Design -Builder, and to the extent it deems it is qualified
to do so, make recommendations to Design -Builder regarding the preparation and
issuance of the Project Design for a portion of the Work to permit construction to proceed
on that portion of the Work prior to completion of the Project Design for the entire
Project.
2.9.3 At the Pre -Construction Conference, Contractor shall advise Design -Builder regarding a
schedule for the procurement of items included in the Work, which have long -lead times.
2.10 Construction Schedule
Contractor shall prepare, maintain and update the Construction Schedule in accordance with the
provisions of Exhibit C. Contractor acknowledges that its scheduling obligations are of the
essence of this Agreement.
2.11 Submittals and Substitutions
2.11.1 Contractor understands that the Contract Documents, including the Project Design, will
be issued in phases. Within seven (7) days of Contractor's receipt of each element of the
Project Design, Contractor shall submit for Design -Builder's review and approval
submittals, including shop drawings, product data and samples. Any variances with the
Project Design shall be specifically identified in Contractor's submittals. Design -
Builder's review and approval of submittals and shop drawings shall not relieve
Contractor of its responsibilities to perform the Work in accordance with the standards
set forth herein and the Project Design unless Design -Builder or Engineer expressly and
specifically approves in writing any such variance in its response to Contractor's
submittals. Contractor shall make any necessary revisions to the submittals requested by
Design -Builder.
2.11.2 All submittals and shop drawings shall comply with the requirements of the Service
Contract. Contractor understands and agrees that its submittals and shop drawings may
be subject to review by Owner and the Independent Engineer.
2.11.2 Contractor shall not make any substitutions in the Work or procedures or methods
specified by Design -Builder for performing the Work unless it first receives written
approval for such substitution from Design -Builder or the Project Engineer.
Capistrano Valley Water District Page 19 Construction Agreement
San Juan Basin Desalter Project
2.12 Subcontractors
2.12.1 Contractor shall comply with the requirements of Section 16.7 of the Service Contract
regarding the use of Subcontractors. Contractor's obligations to Design -Builder with
regard to Subcontractors shall be the same as Design -Builder's obligations to Owner
under the provisions of the Service Contract including, without limitation, Section 16.7
thereof.
2.12.2 Subcontractors shall be qualified to perform the Work for which they are engaged by
Contractor and shall possess all business and professional licenses required by Applicable
Laws. Design -Builder shall have the right to approve Contractor's subcontractors, which
approval shall not be unreasonably withheld.
2.12.3 Contractor shall ensure that all applicable provisions of this Agreement and the Service
Contract, including, but not limited to Section 16.7 thereof, are expressly incorporated by
reference into Contractor's subcontracts of all tiers.
2.12.4 Contractor assumes responsibility to Design -Builder for the proper performance of the
Work of Subcontractors and suppliers and any acts and omissions in connection with
such performance to the same extent as Contractor is responsible for the acts and
omissions of its own employees. Contractor shall coordinate the activities of all
Subcontractors and suppliers. Nothing in this Agreement is intended or deemed to relieve
Contractor from responsibility for the work performed by its Subcontractors, or create
any legal or contractual relationship between Owner or Design -Builder and any
Subcontractor, including, but not limited to any third -party beneficiary rights.
2.13 Work of Others
2.13.1 If Design -Builder or Owner performs other work on the Project or at the Site with
separate contractors under Design -Builder's control, Contractor agrees to reasonably
cooperate with those separate contractors and coordinate its work with these separate
contractors so that the Project can be completed in an orderly and coordinated manner
without unreasonable disruption.
2.13.2 If any part of the Work depends upon other work performed by Design -Builder, or
Design -Builder's or Owner's separate contractors, Contractor shall, prior to proceeding
with that part of the Work, inspect such other work and promptly notify Design -Builder
of any discovered discrepancies or defects that would render it unacceptable for the
proper performance of the Work. Contractor shall not proceed with such part of the
Work without further direction from Design -Builder. Design -Builder shall promptly
correct or cause to be corrected any such discrepancy or defect in the other work. Except
to the extent such discrepancies or defects in such other work are latent, Contractor shall
Capistrano Valley Water District Page 20 Construction Agreement
San Juan Basin Desalter Project
U08:184
410,128 2
412574.1
be liable for appropriate losses or damages incurred due to any discrepancies or defects in
such other work not reported to Design -Builder by Contractor.
2.14 Use of Premises, Site Cleanup, and Protection of the Work
2.14.1 Contractor's use of the Project Sites shall be in accordance with the provisions of the
Service Contract. Contractor shall assist Design -Builder in the preparation of a
Community Outreach Program as provided at Appendix 15 of the Service Contract.
2.14.2 Prior to the commencement of the Work, the Contractor shall conduct a pre -construction
audit of the condition of the Project Sites and identify any pre-existing damage to areas
adjacent to the Project Sites that may be impacted by the Work. Contractor shall create a
photographic record of said Sites and provide Design -Builder with a written report of its
pre -construction audit.
2.14.3 The Contractor shall confine construction equipment, the storage of materials and
equipment, and the operations of the workers to the Project Sites, and areas identified in
the Contract Documents. Contractor shall assume responsibility for all damage to such
land or area, or the Owner or occupant thereof, or any land or areas contiguous thereto,
resulting from the performance of the Work.
2.14.4 The Contractor shall comply with all noise restrictions applicable to its Work.
2.14.3 Contractor shall be responsible, at its sole cost and expense, for obtaining the use of any
additional lands required by Contractor as staging or storage areas.
2.14.4 Contractor shall keep the Sites, adjacent streets and other areas utilized by Contractor
reasonably free from debris, trash and construction wastes to permit Contractor to
perform its construction services efficiently, safely and without interfering with the use of
adjacent land areas. Contractor shall not allow any nuisance to occur or continue at the
Sites and shall respond promptly to all complaints or concerns relating to Contractor's
Work. Upon Substantial Completion of the Work, or a portion of the Work, Contractor
shall remove all debris, trash, construction wastes, materials, equipment, machinery and
tools arising from the Work or applicable portions thereof to permit Design -Builder
and/or Owner to occupy the Project or a portion of the Project for its intended use.
Except where permanently modified to accommodate the Work, and except where
otherwise provided in the Project Design or the Service Contract, Contractor shall restore
the Sites to their prior condition upon completion of the Work.
2.14.5 Contractor shall protect the Work throughout the period of construction and shall bear all
risk of loss concerning the Work until Substantial Completion.
Capistrano Valley Water District Page 21 Construction Agreement
San Juan Basin Desalter Project
U08284
4izsN1252
�a. i
2.15 Inspection; Notice of Covering of Work; Correction of Defective Work
Design -Builder and Contractor understand and expect that the Project will be subject to
considerable scrutiny, oversight, review and/or inspection by numerous entities including, but
not limited to, the District, the City, the Trustee and other Governmental Bodies acting by or
through their authorized representatives as provided in the Service Contract. Contractor shall
anticipate the foregoing level of scrutiny in its performance and scheduling of the Work.
2.15.1 Contractor shall employ and pay for the services of independent inspection agencies or
laboratories to perform all construction inspections, tests or approvals required by
Applicable Laws, the standards set forth at Section 2.3 of this Agreement, the Contract
Documents and the Service Contract including, without limitation, Sections 6.9(B) and
7.2(6) of the Service Contract. Soil tests required by this paragraph shall not be deemed
to include soil testing for contaminates and/or hazardous substances. Contractor shall
provide Design -Builder with notice of said inspections in compliance with Section 6.9(B)
of the Service Contract.
2.15.2 At all reasonable times, Contractor shall provide sufficient facilities for inspection of the
Work by Design -Builder, City, Owner and/or the Independent Engineer at the Project
Sites and at all locations where portions of the Work are in progress or various stages of
completion. The Work will be available, at all times, for appropriate and required
inspections. Design -Builder shall monitor the progress of the Work and shall, except to
the extent that it is the responsibility of the Contractor, conduct appropriate inspections in
a timely manner so as not to interfere with or impede the progress of the Work.
2.15.3 Contractor shall be responsible for obtaining manufacturer inspection of the reverse
osmosis system and the iron/manganese filters and such other Project equipment and
materials as are required by the Contract Documents and Applicable Laws. Such
inspections of installation and testing shall be for the purpose of obtaining certifications
that such equipment has been properly installed and tested in accordance with the
manufacturers' recommendations and requirements.
2.15.4 In the event that inspections or tests reveal that any portion of the Work does not comply
with the Contract Documents or Applicable Laws, Contractor shall promptly correct said
non-compliance and shall bear the cost of corrective measures deemed necessary by the
Design Builder, the Project Engineer, the Owner and/or the Independent Engineer, as
well as the cost of subsequent re -inspection or re -testing. Notwithstanding any
inspections or test, Contractor shall have a continuing obligation during this Agreement
to correct any Work that does not comply with the Contract Documents. Contractor's
obligations and Design -Builder's rights regarding correction of the Work shall be as set
forth at Section 6.10 of the Service Contract. Contractor's obligations to Design -Builder
shall be the same as Design -Builder's obligations to Owner under said Section and
Capistrano Valley Water District Page 22 Construction Agreement
San Juan Basin Desalter Project
4108181
410828 ?
412574.1
Design -Builder's rights with respect to Contractor shall be the same as Owner's rights
with respect to Design -Builder under said Section.
2.15.5 The obligations, rights and remedies of Design -Builder and Contractor regarding the
covering and uncovering of Work shall be as set forth at Section 6.9(E) of the Service
Contract. Contractor's obligations to Design -Builder shall be the same as Design -
Builder's obligations to Owner under said Section and Design -Builder's rights with
respect to Contractor shall be the same as Owner's rights with respect to Design -Builder
under said Section.
2.15.6 Notwithstanding any testing requirements set forth herein, Contractor shall have no
responsibility for the performance of any Acceptance Testing or for the performance of
the design of the Project as required under the Service Contract, except as provided in
Exhibit A.
2.16 Patents and Copyrights
2.16.1 Contractor shall pay all license fees and royalties due for items or processes applicable to
the Work, which are subject to copyrights or patent rights and which are selected by
Contractor. However, where such items or processes are required by the Contract
Documents, Design -Builder shall be responsible for payment of all license fees and
royalties due for such items.
Contractor shall pay all license fees and royalties and assume all costs incident to the use
in the performance of the Work or the incorporation in the Work of any invention,
design, process, product, or device selected and/or specified by Contractor and which is
the subject of patent rights or copyrights held by others. If a particular invention, design,
process, product, or device is specified and/or selected by the Design -Builder for use in
the performance of the Work and if its use is subject to patent rights or copyrights calling
for the payment of any license fee or royalty to others,. With the exception of any
invention, design, process, product or device selected by the Contractor for the Work,
Design -Builder shall pay all license fees and royalties and assume all costs incident to the
use in the performance and/or incorporation into the Work. Contractor shall defend,
indemnify and hold Design -Builder harmless from and against all claims and liabilities
arising out of any infringement of patent rights or copyrights incident to the use in the
performance of the Work or resulting from the incorporation in the Work of any
invention, design, process, product, or device not specified in the Contract Documents.
Design -Builder shall defend, indemnify and hold Contractor harmless from and against
all claims and liabilities arising out of infringement of patent rights or copyrights incident
to the use in the performance of the Work or resulting from incorporation in the Work of
any invention, design, process or product, or device specified in the Contract Documents.
Capistrano Valley Water District
San Juan Basin Desalter Project
410829 1
i rnsxa."
412574.1
Page 23
Construction Agreement
2.17 Applicable Laws; Licenses
2.17.1 Contractor shall perform the Work in accordance with all Applicable Laws and shall
maintain in effect at all times during this Agreement all professional and business
licenses required by law for Contractor to perform the Work hereunder.
2.17.2 Contractor shall be entitled to an adjustment of the Guaranteed Maximum Price and
Contract Time made necessary by a change in Applicable laws if and to the same extent
as Design -Builder is entitled to such adjustment under the terms of the Service Contract.
2.18 Government Approvals and Permits
2.18.1 Contractor shall be responsible for obtaining, at no cost or expense to Design -Builder, the
permits and approvals described in Exhibit B.
2.18.2 Contractor shall provide reasonable assistance to Design -Builder and the Project Engineer
in obtaining those Project -related permits, approvals and licenses, if any, that are the
responsibility of persons other than the Contractor.
2.18.3 Contractor shall comply with the terms and conditions of all permits governing or
affecting the performance of the Work.
2.19 Project Safety
2.19.1 Contractor recognizes the importance of performing the Work in a safe manner so as to
prevent damage, injury or loss to (i) all individuals at the Site, whether working or
visiting, (ii) the Work, including materials and equipment incorporated into the Work or
stored on -Site or off -Site, (iii) the work of others on the Project, and (iv) all other
property at the Site or adjacent thereto. Contractor assumes responsibility for
implementing and monitoring all safety precautions and programs related to the
performance of the Work. Contractor shall, prior to commencing construction, designate
a Safety Representative with the necessary qualifications and experience to supervise the
implementation and monitoring of all safety precautions and programs related to the
Work. Unless otherwise required by the Contract Documents, Contractor's Safety
Representative shall be an individual stationed at the Site who may have other
responsibilities on the Project in addition to safety. The Safety Representative shall make
routine daily inspections of the Work and shall hold weekly safety meetings with
Contractor's personnel, Subcontractors and others as applicable.
2.19.2 Contractor and Contractor's Subcontractors shall comply with all Applicable Laws
relating to safety set forth in the Contract Documents, including Appendix 14 to the
Service Contract, as necessary for the performance of the Work. Contractor will
Capistrano Valley Water District Page 24 Construction Agreement
San Juan Basin Desalter Project
4109391
412574.1
immediately report in writing any safety-related injury, loss, damage or accident arising
from the Work to Design -Builder's Representative and, to the extent mandated by
Applicable Laws, to all government or quasi -government authorities having jurisdiction
over safety-related matters involving the Project or the Work.
2.19.3 Contractor's responsibility for safety under this Section 2.20 is not intended in any way
to relieve Subcontractors or Sub -Subcontractors of their own contractual and legal
obligations and responsibility for (i) complying with all Applicable Laws, including those
related to health and safety matters, and (ii) taking all necessary measures to implement
and monitor all safety precautions and programs to guard against injury, losses, dames or
accidents resulting from their performance of the Work.
2.20 Contractor's Warranty; Correction of Defective Work
2.20.1 Contractor warrants that the Work, including all materials and equipment furnished as
part of the Work, shall be new, shall comply with all applicable provisions of the
Contract Documents and shall be free of defects in materials and workmanship for a
period of one (1) year following Final Completion or issuance of a Notice of Completion
by Design -Builder, whichever is later (the "Warranty Period").
.1 The one year period referenced in Section 2.20.1 applies only to Contractor's
continuing obligation to correct nonconforming Work and is not intended to
constitute a period of limitations for any other rights or remedies Design -Builder
may have regarding Contractor's obligations under the Contract Documents.
2.20.2 Contractor's warranty obligation excludes defects caused by abuse, alterations, or failure
to maintain the Work by persons other than Contractor, subsequent to the completion of
the Work, or anyone for whose acts Contractor is not responsible.
2.20.3 Nothing in this warranty is intended to limit any manufacturer's warranty that provides
greater warranty rights than provided herein. Contractor will provide and assign to
Design -Builder all manufacturers' warranties as a condition of Design -Builder's
obligation to make any final payment otherwise due Contractor under this Agreement.
2.20.4 Contractor shall, within seven (7) days of receipt of written notice from Design -Builder
during the Warranty Period that the Work is not in conformance with the Contract
Documents, take meaningful steps to commence correction of such Non -Conforming
Work, including the correction, removal or replacement of the Non -Conforming Work
and any damage caused to other parts of the Work or the Project affected by the Non -
Conforming Work. If Contractor fails to commence the necessary steps within such seven
(7) day period, Design -Builder, in addition to any other remedies provided under the
Contract Documents, may provide Contractor with written notice that Design -Builder
Capistrano Valley Water District Page 25 Construction Agreement
San Juan Basin Desalter Project
4108391
4ins'R,
412574.1
will commence correction of such Non -Conforming Work with its own forces. If Design -
Builder does perform such corrective Work, Contractor shall be responsible for all
reasonable costs incurred by Design -Builder in performing such correction. If the non-
conforming Work prevents the project from producing Finished Water, Contractor shall
respond to any notice as provided above within twenty-four (24) hours and Design -
Builder's rights if Contractor fails to so respond shall be as set forth above.
1 Contractor's failure to perform its warranty obligations under this Section 2.20
shall constitute a breach of its warranty obligations and shall entitle Design -
Builder to seek recourse from Contractor's performance bond surety or, at
Design -Builder's discretion, to itself cause such correction work to be performed.
2 Contractor shall be liable to Design -Builder for all Loss -and -Expense and
damages of any kind, including cost of correction work, incurred by Design -
Builder as a result of Contractor's breach of its warranty obligations hereunder.
2.20.5 Contractor's obligation to perform and complete the Work in accordance with the
Contract Documents shall be absolute. None of the following will constitute (a) an
acceptance of Work that is not in accordance with the Contract Documents, (b) a release
of Contractor's obligation to perform and complete the Work in accordance with the
Contract Documents, or (c) a waiver of any of Design -Builder's rights and remedies
under the Contract Documents or at law:
1 Observation and inspection of the Work;
.2 The making of any payment to Contractor hereunder;
.3 The issuance of a notice of completion by Owner;
.4 Use or occupancy of the Work or any part thereof except as provided in Section
2.20.2 of this Agreement;
5 Any acceptance, including Final Acceptance by Design -Builder or Owner; and
6 Any review and approval of a shop drawing or sample submittal.
2.21 Excess Spoils
Provided excess spoils are not contaminated nor contain hazardous substances which would
require removal to a Class I, Class II or Class III disposal site, any excess spoils generated during
excavation or grading of the Work shall be the responsibility of the Contractor. To the extent
Capistrano Valley Water District
San Juan Basin Desalter Project
4OM4
416828.2
412574.1
Page 26
Construction Agreement
spoils do contain such contamination, and must be removed to a disposal site as indicated above,
the removal thereof shall be the responsibility of Design -Builder.
2.22 Reports, Books and Records, Record Drawings
2.22.1 Contractor shall keep and maintain at the Project Sites available for inspection by
Design -Builder and Owner a complete set of Contract Documents and shall have a
continuing obligation to update the Contract Documents, including the as -built plans, to
reflect the as -built condition of the Work and the Project, including all approved changes.
Upon completion of the Project, said Contract Documents shall be the basis for Design -
Builder's submission of final as -built Contract Documents.
2.22.2 Contractor shall assist in the preparation of construction -related reports required to be
given by Design -Builder to Owner under Sections 6.8 and 6.9(D) of the Service Contract.
Design -Builder intends that Contractor's monthly Construction Schedule update,
including Narrative Report, shall serve as the basis for the reports required by Section 6.8
of the Service Contract.
2.22.3 Contractor shall comply with Section 6.14 of the Service Contract with regard to the
keeping of Construction Books and Records. Design -Builder's rights as to Contractor
under said section shall be the same as Owner's rights as to Design -Builder.
2.22.4 Contractor agrees that it will comply with Owner's requirements regarding the
submission of reports in digital form. Digital copies shall consist of computer readable
data submitted in Autocad, Microsoft Word, Microsoft Access, and Microsoft Excel or
in any other similar standard interchange format which the Owner may reasonably
request to facilitate the administration and enforcement of this Service Contract.
2.23 Meetings
Contractor shall attend all meetings required under Section 6.9(F) of the Service Contract.
ARTICLE 3 — DESIGN -BUILDER'S SERVICES AND RESPONSIBILITIES
3.1 Timely Reviews and Approvals
3.1.1. Design -Builder shall provide timely reviews and approvals of submittals consistent with
the turnaround times mutually agreed to and set forth in the Construction Schedule.
3.1.2 Design -Builder shall exercise its best efforts to ensure that the level of scrutiny which
Contractor's Work is expected to receive does not disrupt or delay Contractors
performance of the Work. Design -Builder's efforts shall include providing Contractor
Capistrano Valley Water District
San Juan Basin Desalter Project
U08284
41!1828.2
412574.1
Page 27
Construction Agreement
with notices upon receipt from Owner and providing as much advance notification as
possible subject to the requirements of the Service Contract and the Contract Documents.
3.2 Design -Builder's Representative
3.2.1 Design -Builder's Representative shall be responsible for providing Design -Builder -
supplied information and approvals in a timely manner to permit Contractor to fulfill its
obligations under the Contract Documents.
3.2.2 Design -Builder may designate Construction Manager as Design -Builder's representative.
In that event, Construction Manager shall act as a Design -Builder's agent for purposes of
administering this Agreement except that under no circumstances shall Construction
Manager have authority to approve or authorize changes in the Work, the Guaranteed
Maximum Price or the Contract Times without Design -Builder's express written
approval.
3.3 Furnishing of Services and Information
3.3.1 Unless expressly stated to the contrary in the Contract Documents, and to the extent
Design -Builder has received such items from Owner, Design -Builder shall provide for
Contractor's information the items listed below. Design -Builder does not warrant the
accuracy or completeness of such items provided, however, that Contractor is entitled to
rely on these items to the same extent Design -Builder is entitled to rely upon such items
in the Service Contract.
1 Surveys describing the property, boundaries, topography and reference points for
use during construction, including existing service and utility lines;
.2 Geotechnical studies describing subsurface conditions, and other surveys
describing other latent or concealed physical conditions at the Site;
.3 Temporary and permanent easements, zoning and other requirements and
encumbrances affecting land use, or necessary to permit the proper construction
of the Project and enable Contractor to perform the Work.
.4 A legal description of the Project Sites;
5 As -built and record drawings, if any, of any existing structures at the Project
Sites;
Capistrano Valley Water District
San Juan Basin Desalter Project
4= s�
412574.1
Page 28
Construction Agreement
.6 Environmental studies, reports and impact statements describing the
environmental conditions, including Hazardous Conditions, in existence at the
Site;
.7 Owner's Project Criteria;
.8 All permits, approvals, and licenses set forth in the Owner's Permit List attached
as an exhibit to the Service Contract; and
9 Test and inspection reports.
3.3.2 If Contractor requests Design -Builder to obtain any of the documents described
immediately above from Owner, Design -Builder shall, in good faith use all reasonable
efforts to do so. To the extent that Design -Builder would have a claim against Owner,
based upon: (1) a failure to provide the above -entitled documents; (2) a failure to
cooperate in procuring any of the above-described documents if reasonably necessary for
the performance of the Work; and/or (3) the inaccuracy of said documents, then, in such
event, Contractor shall have a claim against Design -Builder. Except as provided in this
Section, Contractor shall no claim against Design -Builder, Project Engineer or Owner
arising from the foregoing circumstances.
3.3.3 Design -Builder shall provide Contractor with a fully signed copy of the Service Contract,
including all exhibits, attachments, and other Contract Documents enumerated and
incorporated therein.
3.3.4 Upon Contractor's reasonable written request, Design -Builder shall provide Contractor
with reasonable assurances regarding Design -Builder's ability to meet its payment
obligations to Contractor under this Agreement.
3.3.5 Design -Builder shall provide Contractor with the Project Design as provided and subject
to the provisions of this Agreement.
3.3.6 Design -Builder shall obtain those permits, approvals and licenses that are not required to
be provided by Owner pursuant to the Service Contract or by Contractor pursuant to this
Agreement and which are required and/or reasonably necessary for the prosecution of the
Work.
3.4 Notification of Errors
Design -Builder or the Project Engineer shall promptly notify Contractor of any errors,
inconsistencies, or omissions in the Work of which they have actual knowledge. However,
Design -Builder's or Project Engineer's failure to discover errors, inconsistencies or omissions in
Capistrano Valley Water District Page 29 Construction Agreement
San Juan Basin Desalter Project
414
�ngzs.:
412574.1
the Work shall not relieve Contractor of responsibility for such errors, inconsistencies, or
omissions or Contractor's obligation to correct such Work.
3.5 Attendance at Design Meetings
Design -Builder shall afford Contractor and its Subcontractors the opportunity to attend all
necessary design meetings with Owner, Designer and/or Design Consultants.
3.6 Review and Approval of Submittals
Design -Builder or its representative shall review and approve submittals in writing, including
shop drawings, product data and samples, submitted by Contractor, which review shall be only
for the purpose of confirming general conformance with the Project Design. Design -Builder's
and/or Engineer's review and approval shall not relieve Contractor of its responsibilities to
perform the Work in accordance with the Project Design unless Design -Builder or Project
Engineer expressly and specifically approves in writing any such variance in its response to
Contractor's submittals. If revisions are necessary to a submittal prior to Design -Builder's
approval, Design -Builder shall inform Contractor of any such necessary revisions. Subject to
the right of Owner and the Independent Engineer's rights to review such submittals under the
terms of the Service Contractor, Design -Builder shall exercise its best efforts to complete such
reviews within ten (10) days of submittal.
3.7 Design -Builder's Separate Contractors
Design -Builder is responsible for all work performed on the Project or at the Site by separate
contractors under Design -Builder's control. Design -Builder shall contractually require its
separate contractors to cooperate with, and coordinate their activities so as not to interfere with
Contractor's ability to timely complete the Work consistent with the Contract Documents.
3.8 Project Progress Meetings
Design Builder, Project Engineer and Contractor shall meet twice a month during the Project to
discuss the progress of the Work.
ARTICLE 4 — HAZARDOUS MATERIALS AND DIFFERING SITE CONDITIONS
4.1 Hazardous Materials
4.1.1 Unless otherwise expressly provided in the Contract Documents to be part of the Work,
Contractor is not responsible for any Hazardous Materials encountered at the Project
Sites. Upon encountering any Hazardous Materials, Contractor will stop Work
immediately in the affected area and duly notify Design -Builder and, if required by
Capistrano Valley Water District Page 30 Construction Agreement
San Juan Basin Desalter Project
UOW84
JI0=-'
412574.1
Applicable Laws, all government or quasi -government entities with jurisdiction over the
Project. In addition, Contractor shall comply with the provisions of Section 14.2 of the
Service Contract regarding Uncontrollable Circumstances.
4.1.2 Contractor shall be obligated to resume Work at the affected area of the Project only after
Design -Builder provides Contractor with a written certification from Design -Builder's or
Owner's expert that (i) the Hazardous Materials have been removed or rendered
harmless, and (ii) all necessary approvals have been obtained from all government and
quasi -government entities having jurisdiction over the Project or Site. To the extent the
Hazardous Condition is the responsibility of Owner, Design -Builder agrees to include
Contractor in discussions with Owner to resolve the matter. If Design -Builder and
Contractor are unable to resolve the matter with Owner, the matter will be resolved in
accordance with the Dispute Resolution provisions of this Agreement.
4.1.3 Contractor will be entitled, in accordance with the Contract Documents, to an adjustment
in its Guaranteed Maximum Price and/or Contract Time(s) to the extent Contractor's cost
and/or time of performance have been adversely impacted by the presence of Hazardous
Materials as provided by Section 14.2 of the Service Contract. Design -Builder's and
Contractor's rights and obligations to one another under said Section shall be the same as
the rights and obligations of Owner and Design -Builder.
4.1.4 As provided in the Service Contract, Design -Builder has caused Owner to indemnify,
defend and hold harmless Design -Builder, anyone employed directly or indirectly by
Design -Builder, and their officers, directors, employees and agents, from and against any
and all claims, losses, damages, liabilities, and expenses including attorneys' fees and
expenses, arising out of or resulting from the presence, removal or remediation of
Hazardous Materials at the Site.
4.1.5 Notwithstanding the preceding provisions of this Section 4.1, Contractor is responsible
for Hazardous Materials introduced to the Site by itself, Contractor's Subcontractors, and
Contractor's Sub -Subcontractors. Contractor shall indemnify, defend and hold harmless
Owner, Design -Builder and their officers, directors, employees and agents from and
against all claims, losses, damages, liabilities, and expenses, including attorneys fees and
expenses, arising out of or resulting from those Hazardous Materials introduced to the
Site by Contractor, Contractor's Subcontractors and Contractor's Sub -Subcontractors.
4.2 Differing Site Conditions; Uncontrollable Circumstances
Contractor understands and acknowledges that Design -Builder is not entitled to additional
compensation or extensions of time from Owner resulting from the discovery of differing surface
or subsurface conditions at the Project Sites which increase Contractor's cost of performing or
cause delay in Contractor's performance of the Work, except to the extent such conditions
Capistrano Valley Water District Page 31 Construction Agreement
San Juan Basin Desalter Project
41988 1
AIDS
412574.1
constitute Uncontrollable Circumstances, Pre -Existing Environmental Conditions or Specified
Site Conditions as defined herein and in the Service Contract.
Contractor shall not be entitled to a change in the Guaranteed Maximum Price or Contract
Time(s) due to a differing Site condition except to the extent that Design -Builder is entitled to an
adjustment in its compensation or time for performance under the Service Contract.
Design -Builder's and Contractor's rights and obligations to one another with respect to
Uncontrollable Circumstances shall be the same as the rights and obligations of Owner and
Design -Builder to one another under the Service Contract and the provisions of the Service
Contract as so modified are incorporated herein as though fully set forth whether or not expressly
set forth below or elsewhere in this Agreement.
4.2.1 Before commencing the Work or any portion thereof, Contractor shall make its own
investigation, including investigatory explorations, excavations and inquiries with area
utility providers, and the appropriate regional notification center, as provided in
California Government Code Sections 4216, et seq.
4.2.3 Contractor shall notify Design -Builder of any Uncontrollable Circumstance by facsimile
or telephone promptly upon learning of such Uncontrollable Circumstance and shall
proceed as provided at Section 14.2 of the Service Contract.
4.2.4 Contractor's failure to give the notice required under this Section, or to maintain all
documentation required to establish the existence of an Uncontrollable Circumstance or
to substantiate its costs and expenses in the manner required under the Service Contract,
shall constitute a waiver of any right Contractor may have otherwise had to seek or obtain
an adjustment in the Guaranteed Maximum Price or the Contract Time(s).
4.2.5 Except as provided in this Agreement and in the Service Contract, Contractor shall
continue to perform the Work and shall take all steps possible to mitigate any delays and
disruptions notwithstanding the occurrence or discovery of an Uncontrollable
Circumstance.
ARTICLE 5 — CONTRACT TIMES
5.1 Date of Commencement
The Work shall commence not more than five (5) days after Contractor's receipt of the Contract
Documents and Design -Builder's Notice to Proceed ("Date of Commencement") unless the
parties mutually agree otherwise in writing.
Capistrano Valley Water District Page 32 Construction Agreement
San Juan Basin Desalter Project
mesas4
3leszsW
412574.1
5.2 Contract Times
5.2.1 Substantial Completion of the Work, as provided at Section 7.4.2 of this Agreement shall
be achieved no later than August 1, 2004 ("Substantial Completion Date"). Contractor's
obligation under this section of the Contract shall be limited to Scope of Work and shall
not include any duties or obligations of the Design -Builder under the terms of the Service
Contract.
5.2.2 Final Completion of the Work shall be achieved as provided herein on or before October
15, 2004.
5.2.3 All of the dates set forth in this Article 5 (the "Contract Time(s)") shall be subject to
adjustment in accordance with this Agreement.
5.3 Time is of the Essence
Contractor understands and acknowledges that the Project must achieve Acceptance no later than
December 4, 2004, and that Design -Builder may be subject to substantial liquidated and other
damages under the Service Contract if the foregoing deadlines are not met. Accordingly,
Contractor's timely performance of this Agreement is critical and Design -Builder and Contractor
mutually agree that time is strictly of the essence with respect to the dates and times set forth in
the Contract Documents that relate to the Work, including this Article 5, and the Project
Schedule. However, if any delay results from late submission of project design, plans or
specifications and/or late submission of design modifications by Design -Builder, at Design -
Builder's sole option, Contractor shall be entitled to either 1) a corresponding extension of time
for each day such plans, designs, specifications or modifications are delayed, or 2) its reasonable
acceleration costs to maintain the Construction Schedule, or 3) both.
5.4 Liquidated Damages
5.4.1 Contractor recognizes that Design -Builder will suffer financial loss if the Work is not
completed within the times specified in paragraph 3.1 above, plus any extensions thereof
allowed in accordance with this Agreement. The Parties also recognize the delays,
expenses and difficulties involved in proving the actual loss suffered by Design -Builder if
the Work is not completed on time. Accordingly, instead of requiring any such proof,
Design -Builder and Contractor agree that as liquidated damages for delay (but not as a
penalty) Contractor shall pay Design -Builder the following amounts: 1) if Substantial
Completion is delayed from 1 to 30 days --$2,000.00 per day; 2) if Substantial
Completion is delayed from 31-60 days -- $3,000 per day; 3) if Substantial Completion is
delayed for 61 days or thereafter -- $,4,000 per day. Such liquidated damages shall be
paid for each calendar day that expires after the time for Substantial Completion of the
Project until the foregoing events have been achieved, which amounts shall be
Capistrano Valley Water District
San Juan Basin Desalter Project
410828.1
412574.1
Page 33
Construction Agreement
cumulative. Subject to the other provisions of this Agreement, Contractor shall not be
responsible for, and Design -Builder will provide or cause to be furnished all finished
plans, specifications, designs and/or modifications. Late delivery of such plans,
specifications, designs, and modifications shall suspend assessment of Liquidated
Damages by the number of days equal to the late delivery.
5.4.2 The liquidated damages provided in Section 5.4.1 shall be in lieu of all liability for any
and all extra costs, losses, expenses, claims, penalties and any other damages, whether
special or consequential and of whatsoever nature incurred by Design -Builder which are
occasioned by any delay in achieving Substantial Completion or Acceptance of the Work.
5.4.3 The limitation set forth in Section 5.4.2 shall not apply in the event that Contractor,
except as specifically and expressly permitted in this Agreement, terminates or abandons
the Work before completion, in which event Design -Builder shall be entitled to assert all
remedies and recover all damages permitted by law even if Contractor's abandonment of
the Project or termination of this Agreement is based on a claim for an adjustment in the
Guaranteed Maximum Price or Contract Time(s) which it is ultimately determined to be
meritorious by a Court or other tribunal.
5.5 Delays to the Work
5.5.1 If Contractor is delayed in the performance of the Work on the Construction Schedule's
critical path due to an "Uncontrollable Circumstance" as that term is defined in the
Service Contract, and said delay is not due to any fault of Contractor or those for whom
Contractor is responsible, including, but not limited to its subcontractors and suppliers,
the Contract Time(s) for performance shall be reasonably extended by Change Order but
only to the extent Design -Builder's time for performance is extended as provided at
Section 14.2 of the Service Contract. Delays which do not impact the critical path of the
Work shall not be eligible for any time extension.
5.5.2 If Contractor is delayed in the performance of the work on the Construction Schedule's
critical path due as a result of the acts or omissions of Design -Builder or those for whom
Design -Builder is responsible, and said delay is not due to any fault of the Contractor or
those for whom the Contractor is responsible, Contractor's relief shall for said delay shall
be as provided in Section 12.5.4 of this Agreement.
5.5.3 Contractor's construction schedule shall anticipate twenty (20) days per year of delay due
to severe weather conditions.
Capistrano Valley Water District Page 34 Construction Agreement
San Juan Basin Desalter Project
41es1H 1
410828.1
412574.1
ARTICLE 6 — GUARANTEED MAXIMUM PRICE
6.1 Guaranteed Maximum Price
6.1.1 Design -Builder shall pay Contractor in accordance with Article 7 hereof the Guaranteed
Maximum Price of Sixteen Million, Five Hundred Thousand Dollars ($16,500,000)
("Guaranteed Maximum Price"), subject to adjustments made in accordance with the
Contract Documents. Unless otherwise provided in the Contract Documents, the
Guaranteed Maximum Price includes all the costs of labor, supervision, tools, equipment,
supplies, materials services, allowances overhead, profits, fees and other costs and
expenses related to the construction of the Project. The Guaranteed Maximum Price is
based upon to the scope of Work described in the Contract Documents, including, but not
limited to Exhibit A and the attachments and appendices referenced therein, the
conceptual drawings attached hereto as Exhibit E and the Contractor's Proposal attached
as Exhibit H to this Agreement.
6.1.2 Contractor confirms and agrees that its responsibility hereunder is to construct the Project
in accordance with the drawings and specifications. It is recognized that the Guaranteed
Maximum Price has been determined based upon incomplete design, and the Contractor
has exercised reasonable care and judgment to determine the intent of the design and has
calculated the Guaranteed Maximum Price on the basis of the quality of construction,
equipment, materials, and finishes that can be reasonably inferred from the design
documents or other information provided to the Contractor relating to this Project. The
Contractor shall utilize Exhibit A and the attachments and appendices referenced therein,
the conceptual drawings attached hereto as Exhibit E and the Contractor's Proposal
attached as Exhibit H to determine whether or not the scope of the Project has been
changed and in determining entitlement to an adjustment to the Guaranteed Maximum
Price. A determination regarding requests for adjustment (increase or decrease) to the
Guaranteed Maximum Price shall be made in writing within thirty (30) days of a written
request for an adjustment. As a condition of Design -Builders review of a request for
adjustment of the Guaranteed Maximum Price, Contractor shall be required to submit to
Design -Builder all the information described in Section 12.5.3 hereof.
6.1.3 Contractor shall not be entitled to an adjustment in the Guaranteed Maximum Price
hereunder for the costs of any Design -Builder generated changes up to 1% of the
Guaranteed Maximum Price (hereinafter referred to as the "1% Allowance")
6.1.4 The Guaranteed Maximum price shall include all sales, use, consumer and other taxes
mandated by Applicable Laws. The Guaranteed Maximum Price shall constitute
payment in full for the performance of the Work and all of Contractor's obligations under
this Agreement. Notwithstanding the above, Design -Builder is not responsible for
Capistrano Valley Water District Page 35 Construction Agreement
San Juan Basin Desalter Project
410838 1
.11(1828.2
412574.1
Contractor's bidding or estimating mistakes, price or wage increases, changes in Union
work rules or miscalculation of market conditions.
6.1.5 With respect to any adjustment to the Guaranteed Maximum Price, Contractor's fee shall
consist of a 10% home office overhead component and a 5 % profit component.
6.1.6 As a means of promoting a partnership approach and to reward innovation in the value
engineering, constructability review, procurement and execution of the Project and to
provide incentive for Contractor and Design -Builder to complete the Work at a cost
below the Guaranteed Maximum Price, Design -Builder and Contractor agree to share, on
an equal 50%-50% basis, any savings in the cost of the Work against the Final
Guaranteed Maximum Price. For purposes of this Agreement, the Final Guaranteed
Maximum Price shall equal the sum of the Guaranteed Maximum Price and any
adjustments to the Guaranteed Maximum Price agreed to between the Design -Builder and
Contractor, but not including the 1% Allowance for Design -Builder generated changes
and all taxes payable by the Contractor hereunder.
6.1.6 Contractor shall not be permitted to an extension of the Contract Time(s) as a result of
any variance between the Conceptual Design Drawings and either the Contract
Documents or the Project Design except to the extent that the Owner, without imposing
liquidated damages, extends Design -Builder's time for performance of the Service
Contract. If an extension of time is not granted by the Owner, the Guaranteed Maximum
Price shall be adjusted by appropriate additions or adjustments. Contractor shall supply
Design -Builder with all documentation necessary to substantiate the amount of the
addition to the price. Subject to 6.1.3, the Guaranteed Maximum Price will be increased
in accordance with Section 12.5.4 of this Agreement.
ARTICLE 7 — PROCEDURE FOR PAYMENT
7.1 Schedule of Values
Payments to Contractor under this Agreement shall be based on progress of the Work reflected
by the Project Schedule and Schedule of Values required under Exhibit C to this Agreement.
7.2 Progress Payments
7.2.1 Amount of Progress Payments. Subject to the provisions of Section 7.2 and this
Agreement, Design -Builder shall make monthly Progress Payments to Contractor equal
to the sum of the following:
1 Cost of the Work in permanent place as of the end of the immediately preceding
month. Cost of the Work shall refer to the portion of the Guaranteed Maximum
Capistrano Valley Water District
San Juan Basin Desalter Project
4108381
410828 2
412574.1
Page 36
Construction Agreement
Price applicable to Work performed by Contractor as of the end of the
immediately preceding month as shown in the approved Construction Schedule
update and Schedule of Values submitted with Contractor's Application for
Progress Payment...;
.2 Plus cost of materials not yet permanently incorporated in the Work, except as
provided in Section 7.2.4 of this Agreement;
.3 Less amounts previously paid;
.4 Less 10% to be withheld by Design -Builder as retention; Retention shall be
reduced to 5% upon Contractor's achievement of Substantial Completion. The
balance of Contractor's retention shall be paid upon Final Completion.
5 Less such other amounts Design -Builder is entitled to withhold under the terms of
this Agreement.
7.2.2 Progress Payment Applications. Beginning with the first month after the Date of
Commencement, and each month thereafter during this Agreement, Contractor shall
submit on the twentieth (20th) day of each month for Design -Builder's review and
approval Contractor's Progress Payment Application.
7.2.3 Form of Progress Payment Application. Progress Payment Applications shall be in a
form acceptable to Design -Builder and shall include, as a minimum, the following:
1 All information and certifications required under Section 5.5(C) and 5.5(D) of the
Service Contract.
.2 Contractor's Construction Schedule update, including Schedule of Values and
supporting information required by Exhibit C.
.3 Amounts for which payment is being requested on behalf of Subcontractors.
.4 Conditional Waivers and Releases Upon Progress Payments executed by
Contractor and all Subcontractors for whom payment is being requested.
.5 The Application shall identify the Guaranteed Maximum Price, the amounts of all
approved Change Orders, total amount paid by Design -Builder to date, total
amount withheld to date by Design -Builder as retention, amount of current
Application for Payment, and amount to be withheld as retention from Current
Application for Payment.
Capistrano Valley Water District
San Juan Basin Desalter Project
4108291
4I flq:R 2
412574.1
Page 37
Construction Agreement
.6 Amounts for which payment is request pursuant to Section 7.2.4.
.7 The value of materials and equipment stored on site which have not been
incorporated into the Work, and less a deductive adjustment for materials and
equipment installed which were not previously incorporated in the Work, but for
which payment was allowed pursuant to this section.
8 Design -Builder may, at its discretion, request the submission of certified payroll
information and certifications as a condition precedent to its obligation to make
any Progress Payment.
7.2.4 Materials Not Yet Incorporated in the Work. The Application for Payment may request
payment for the value of equipment and materials not yet incorporated into the Project,
provided that (i) Design -Builder is satisfied that the equipment and materials are suitably
stored at either the Site or another acceptable location, (ii) the equipment and materials
are protected by suitable insurance, and (iii) upon payment, Design -Builder will receive
the equipment and materials free and clear of all liens and encumbrances. Design -
Builder may, in its sole discretion, allow payment for such materials.
7.2.5 Contractor's Representation. The Application for Payment shall constitute Contractor's
representation that the Work has been performed consistent with the Contract
Documents, has progressed to the point indicated in the Application for Payment, and
that title to all Work which is the subject of the Application for Payment, as well as risk
of loss, will pass to Design -Builder free and clear of all claims, liens, encumbrances, and
security interests upon the incorporation of the Work into the Project, or upon
Contractor's receipt of payment, whichever occurs earlier.
7.2.6 Approval of Application for Payment. Approval of any part of a Progress Payment
Application may be withheld, and all or part of a previous Progress Payment Application
may be nullified and withheld from a current payment, on account of any of the
following:
.1 Defective work not remedied.
2 Third party claims against Design -Builder arising from Contractor's breach of its
obligations under this Agreement or Applicable Laws.
3 Mechanic's liens, stop notices or other claims filed against the Project.
4 A reasonable doubt that the Work can be completed within the Contract Times
and a failure by Contractor to undertake corrective measures.
Capistrano Valley Water District Page 38 Construction Agreement
San Juan Basin Desalter Project
4iesa84
.1I /IR2R.2
412574.1
5 Failure of Design Builder to submit any of the materials required to be submitted
with Progress Payment Applications.
.6 Liquidated Damages as provided by this Agreement.
7.2.7 Payment of Pro gess Pa ment. Subject to the withholding provisions of Section 7.2.6
and other applicable provisions of this Agreement, Design -Builder will pay undisputed
and properly submitted Progress Payment Applications no later than thirty (30) days after
receipt thereof.
7.2.8 Joint Checks. Design -Builder shall have the right, at its discretion, to make any
payments to Contractor under this Agreement which include amounts due from
Contractor to Subcontractors by joint check.
7.2.9 No Waiver/Acce tance. Progress payments made by Design -Builder shall not constitute
acceptance of defective work or a waiver of any of Design -Builder's rights under this
Agreement with regard to any work for which such payment was made.
7.3 Deposit of Securities in Lieu of Retention
7.3.1 Pursuant to Section 22300 of the California Public Contract Code, Contractor may
substitute securities for any money withheld by the Design -Builder to insure performance
under the Contract. At the request and expense of the Contractor, securities equivalent to
the amount withheld shall be deposited with the Design -Builder or with a state or
federally chartered bank in California as the escrow agent, who shall return such
securities to the Contractor upon satisfactory completion of the Contract.
7.3.2 Alternatively, the Contractor may request and the Design -Builder shall make payment of
retentions earned directly to the escrow agent at the expense of the Contractor. At the
expense of the Contractor, the Contractor may direct the investment of the payments into
securities and the Contractor shall receive the interest earned on the investments upon the
same terms provided for in this section for securities deposited by the Contractor. Upon
satisfactory completion of the Contract, the Contractor shall receive from the escrow
agent all securities, interest, and payments received by the escrow agent from the Design -
Builder, pursuant to the terms of this section. The Contractor shall pay to each
subcontractor, not later than 20 days of receipt of the payment, the respective amount of
interest earned, net of costs attributed to retention withheld from each subcontractor, on
the amount of retention withheld to insure the performance of the Contractor.
7.3.3 Securities eligible for investment under Section 7.3 shall be limited to those listed in
Section 16430 of the Government Code and to bank or savings and loan certificates of
Capistrano Valley Water District Page 39 Construction Agreement
San Juan Basin Desalter Project
Uesaa4
AIM -Mw
412574,1
deposit, interest bearing demand deposit accounts, standby letters of credit, or any other
security mutually agreed to by the Contractor and the Design -Builder.
7.4 Substantial Completion
7.4.1 Contractor shall provide Design -Builder with at least thirty (30) days advance written
notice of when Contractor reasonably believes that Substantial Completion as provided in
Section 7.3(B) of the Service Agreement will be achieved.
7.4.2 "Substantial Completion" shall mean the completion of all Work necessary to achieve the
following: 1) all Work has been completed so that both of the water treatment process
trains are fully operational, the wells and pipelines are operational and the Project is
ready for Acceptance Testing; 2) a temporary or preliminary certificate of occupancy has
been issued for the Project; and 3) the Contractor has delivered to the Design -Builder
written certifications of all equipment supplied by Contractor that certify that said
equipment has been installed and tested in accordance with the manufacturer's
recommendations and requirements.
7.4.3 Contractor shall notify Design -Builder when Contractor reasonably believes that
Substantial Completion has been achieved. Within three (3) days of Design -Builder's
receipt of Contractor's notice, Contractor, Design -Builder, Project Engineer, Independent
Engineer and District Engineer will jointly inspect such Work to verify that it is
substantially complete in accordance with requirements of the Contract Documents.
Design -Builder shall promptly thereafter provide Contractor with written notice of all
Work required to achieve Substantial Completion and Contractor shall promptly perform
such Work. The parties shall diligently repeat the above process until Substantial
Completion has been achieved.
7.5 Provisional Acceptance and Acceptance Under Service Contract
7.5.1 Design -Builder shall promptly notify Contractor when Substantial Completion and
Provisional Acceptance or Acceptance has occurred
7.5.2 On or before the Substantial Completion Date, Contractor shall prepare a proposed final
punch list and claims statement in accordance with the provisions of Section 7.15 of the
Service Contract. After any required changes to and approval of the proposed final
punch list, Contractor shall perform all final punch list items and submit all materials
required to be submitted by Contractor under Section 7.16 of the Service Contract.
Capistrano Valley Water District Page 40 Construction Agreement
San Juan Basin Desalter Project
4108281
410828.1
412574.1
7.6 Partial Use
Design -Builder, at its option, may use a portion of the Work which has been determined to be
substantially complete provided that (i) a Certificate of Substantial Completion has been issued
for the portion of Work addressing the items set forth in Section 7.5.1 above, (ii) Contractor and
Design -Builder have obtained the consent of their sureties and insurers, and to the extent
applicable, the appropriate government authorities having jurisdiction over the Project, and (iii)
Design -Builder and Contractor agree that Design -Builder's use or occupancy will not interfere
with Contractor's completion of the remaining Work. Design -Builder's occupation and use of
the Project with Contractor in order to monitor and observe the performance of Acceptance Tests
shall not relieve Contractor's responsibility for the Project until Final Completion has occurred.
7.7 Final Completion and Final Payment
7.7.1 Contractor shall submit its Final Application for Payment to Design -Builder in
accordance with Section 7.7.2 below when Final Completion has been achieved Design -
Builder shall make the final payment, including Contractor's final retention payment,
based on Contractor's properly submitted and accurate Final Application for Payment
within thirty (30) days after receipt of Contractor's Final Application for Payment,
provided also that Contractor has satisfied the requirements for final payment set forth in
Section 7.7.2 below.
7.7.2 At the time of submission of its Final Application for Payment, and as a condition of such
final payment, Contractor shall also submit the following information:
.1 Affidavits in a form acceptable to Design -Builder executed by Contractor and its
Subcontractors that there are no claims, obligations or liens outstanding or
unsatisfied for labor, services, material, equipment, taxes or other items
performed, furnished or incurred for or in connection with the Work which will in
any way affect Design -Builder's or Owner's interests;
2 Conditional waivers and releases upon final payment conforming with the
requirements of California Civil Code Section 3262 executed by Contractor and
its Subcontractors.
.3 Consent of Contractor's surety, if any, to final payment.
.4 All training required to be provided by Contractor.
.5 All operating manuals, warranties, certificates of inspection, as -built drawings and
specifications and other deliverables or documents required by the Contract
Documents; and
Capistrano Valley Water District Page 41 Construction Agreement
San Juan Basin Desalter Project
4aesas4
3I�
412574.1
.6 Certificates of insurance confirming that required coverages will remain in effect
consistent with the requirements of the Contract Documents;
.7 Subject to Design -Builder's approval, Contractor's written certification that it has
completed all Work required to be performed under this Agreement, including but
not limited to all punch list work; and
.8 Submission of Contractor's final claims statement, if any, pursuant to Section
7.16(B)(2) of the Service Contract.
7.7.3 Design -Builder shall be entitled to withhold from Contractor's final payment reasonably
disputed amounts set forth at Section 7.2.6 of this Agreement.
7.8 Advance Payments
Design -Builder has the right, at its sole option, to advance any payment due Contractor under
this Agreement.
7.9 Interest/Late Charges
Undisputed payments due and unpaid under this Agreement shall bear interest in accordance
with Applicable Laws governing the making of such payments.
7.10 Payment Not Acceptance
No payment to Contractor under this Agreement shall be evidence of, or construed to be,
acceptance of defective, faulty, improper or non -conforming work.
7.11 Contractor's Payment Obligations
Contractor will pay Subcontractors, in accordance with its contractual obligations to such parties,
all the amounts Contractor has received from Design -Builder on account of their work.
Contractor will impose similar requirements on Subcontractors to pay those parties with whom
they have contracted. Contractor will indemnify and defend Owner and Design -Builder against
any claims for payment and mechanic's liens as set forth in Section 11.3 hereof.
ARTICLE 8 — TERMINATION
8.1 Design -Builder's Right To Suspend Work
8.1.1 Design -Builder may, without cause and for its convenience, order Contractor in writing
to stop and suspend the Work. Such suspension shall not exceed thirty (30) consecutive
days or aggregate more than forty-five (45) days during the duration of the Project.
Capistrano Valley Water District Page 42 Construction Agreement
San Juan Basin Desalter Project
4108281
412574.1
8.1.2 In the event of a suspension under Section 8.1.1, Contractor shall be entitled to
compensation in the amount of the direct incurred by Contractor as a result of such
suspension and shall be required to provide Cost Substantiation for such expenses as
provided by Section 16.6 of the Service Contract.
8.1.3 If the Work is required to be accelerated in order to avoid delays to the Contract Times as
a result of such suspension, Contractor shall be entitled to compensation for the
reasonable costs of such acceleration which shall be paid pursuant to a written Change
Order issued pursuant to Article 12 of this Agreement.
8.2 Design -Builder's Right to Terminate for Convenience
Contractor recognizes that Owner has the right to terminate the Service Contract under Sections
4.11, 13.5, 13.6, 13.7, 13.8 and other provisions of the Service Contract for the Owner's
convenience. Design -Builder may terminate this Agreement for its convenience, whether or not
Owner exercises its right to terminate the Service Contract for its convenience, upon ten (10)
days' written notice to Contractor.
8.2.1 If Design -Builder terminates this Agreement for its convenience as a result of Owner's
exercise of its right to terminate the Service Contract for its convenience, Contractor shall
receive compensation equal to the amount that would otherwise be due Contractor under
the terms of this Agreement for Work performed up to the effective date of such
termination plus amounts Contractor has paid or incurred to Subcontractors, including a
reasonable sum for demobilization costs. In the event of such a termination, Contractor's
right to such compensation shall be subject to Cost Substantiation as provided in Section
16.6 of the Service Contract.
8.2.2 If Design -Builder terminates this Agreement for its convenience but Owner has not
exercised its right to terminate the Service Contract for its convenience, Contractor shall
receive compensation equal to the amount that would otherwise be due Contractor under
the terms of this Agreement for Work performed up to the effective date of such
termination plus amounts Contractor has paid or incurred to Subcontractors, including a
reasonable sum for demobilization costs.
8.2.3 Contractor shall not be entitled to receive any compensation in the event Design -Builder
terminates this Agreement for its convenience except as expressly provided herein.
Contractor's compensation in the event of such a termination shall be exclusively limited
to that provided in Sections 8.2.1 or 8.2.2 of this Agreement. Design -Builder shall have
no obligation to reimburse Contractor for anticipated or lost profits or revenue,
consequential damages or any other economic loss or damages of any kind resulting from
the termination.
Capistrano Valley Water District Page 43 Construction Agreement
San Juan Basin Desalter Project
8.3 Design -Builder's Right to Terminate for Default
8.3.1 Design -Builder shall have the right to terminate this Agreement for default if, in Design -
Builder's reasonable judgment, Contractor persistently fails to:
1 Provide a sufficient number of skilled workers to perform the Work in accordance
with the Contract Documents;
.2 Properly manage the Work;
.3 Timely provide Design -Builder with Construction Schedule updates;
.4 Supply the materials required by the Contract Documents;
.5 Comply with Applicable Laws;
.6 Timely pay, without cause, its Subcontractors;
.7 Prosecute the Work with promptness and diligence to ensure that the Work is
completed by the Contract Time(s), as such times may be adjusted;
8 Perform material obligations under the Contract Documents, and if
9 Contractor causes the occurrence of an Event of Default by Contractor as defined
in the Service Contract at Section 13.2(B)(1) through (5).
8.3.2 Upon the occurrence of an event set forth in Section 8.3.1 above, Design -Builder may
provide written notice to Contractor that it intends to terminate the Agreement for Default
unless the problem cited is cured, or commenced to be cured, within seven (7) days of
Contractor's receipt of such notice. If Contractor fails to cure, or reasonably and
materially commence to cure, such problem, then Design -Builder may give a second
written notice to Contractor of its intent to terminate within three (3) day period. If
Contractor, within such three (3) day period, fails to cure, or reasonably commence to
cure, such problem, then Design -Builder may declare the Agreement terminated for
default by providing written notice to Contractor of such declaration. Such a termination
shall be effective as of the end of said three-day period. If Design -Builder reasonably
determines that any of the events set forth in Section 8.3.1 above have occurred and are
not susceptible to cure by Contractor, Design -Builder may terminate this Agreement for
default without providing Contractor an opportunity to cure by providing seven (7) days
written notice of such termination to Contractor.
Capistrano Valley Water District
San Juan Basin Desalter Project
U08284
airi4:A,
412574.1
Page 44
Construction Agreement
8.3.3 Upon declaring the Agreement terminated pursuant to Section 8.3.2 above, Design -
Builder may enter upon the premises and take possession for the purpose of completing
the Work, of all materials, equipment, scaffolds, tools, appliances and other items
thereon, which have been purchased or provided for the performance of the Work, all of
which Contractor hereby transfers, assigns and sets over to Design -Builder for such
purpose, and to employ any person or persons to complete the Work and provide all of
the required labor, services, materials, equipment and other items. In the event of such
termination, Contractor shall not be entitled to receive any further payments under the
Contract Documents until the Work shall be finally completed in accordance with the
Contract Documents. At such time, if the unpaid balance of the Guaranteed Maximum
Price exceeds the cost and expense incurred by Design -Builder in completing the Work,
such excess shall be paid by Design -Builder to Contractor. If Design Builder's cost and
expense of completing the Work exceeds the unpaid balance of the Guaranteed
Maximum Price, then Contractor shall be obligated to pay the difference to Design -
Builder. Such costs and expense shall include not only the cost of completing the Work,
but also losses, damages, costs and expenses, including attorneys fees and expenses,
incurred by Design -Builder in connection with the re -procurement of Work and the
defense of claims arising from Contractor's default.
8.3.4 The remedies provided at Section 8.3.3 shall in no way limit any and all other rights and
remedies Design -Builder may have at law.
8.4 Contractor's Obligations Upon Termination
Contractor's obligations upon any termination of this Agreement by Design -Builder shall be as
set forth at Section 13.11(A) through (G).
8.5 Contractor's Right to Terminate
8.5.1 Contractor shall not have the right to terminate this Agreement for any reason except as
expressly provided in this Section 8.5.1:
1 Design -Builder fails to pay undisputed amounts due to Contractor under this
Agreement.
.2 The insolvency of the Design -Builder as determined by the Bankruptcy Code.
.3 The filing by the Design -Builder of a petition of voluntary bankruptcy or
reorganization under the Bankruptcy Code or consenting to the filing of any
bankruptcy or reorganization petition against the Design -Builder.
Capistrano Valley Water District
San Juan Basin Desalter Project
Page 45
Construction Agreement
4. The issuance of an order of a court of competent jurisdiction appointing a
receiver, liquidator, custodian or trustee of the Design -Builder.
8.5.2 Upon occurrence of an event set forth in Section 8.5.1 above, Contractor shall provide
written notice to Design -Builder if it intends to terminate the Agreement unless the
problem cited is cured, or commenced to be cured, within seven (7) days of Design -
Builder's receipt of such notice. If Design -Builder fails to cure, or reasonably commence
to cure, such problem, then Contractor may give a second written notice to Design -
Builder declaring the Agreement terminated for default by providing written notice to
Design -Builder of such declaration. In such case, Contractor shall be entitled to recover
all damages and relief as allowed by this Agreement and by law.
8.6 Events of Default Without Right to Cure
Notwithstanding the provisions of 8.3.2, each of the following shall constitute an event of default
by the Contractor upon which the Design -Builder, by notice to the Contractor, may terminate this
Agreement without providing any opportunity to cure:
8.6.1 The insolvency of the Contractor as determined by the Bankruptcy Code;
8.6.2 The filing by the Contractor of a petition of voluntary bankruptcy or reorganization under
the Bankruptcy Code or consenting to the filing of any bankruptcy or reorganization
petition against the Contractor;
8.6.3 The issuance of an order of a court of competent jurisdiction appointing a receiver,
liquidator, custodian or trustee of the Contractor;
8.6.4 The termination or expiration of Contractor's performance and payment bonding required
hereunder; or
8.6.5 Any bankruptcy filing by Contractor's bonding company.
Capistrano Valley Water District Page 46 Construction Agreement
San Juan Basin Desalter Project
408M.4
41012.1
412574.1
ARTICLE 9 — REPRESENTATIVES OF THE PARTIES
9.1 Design -Builder's Representatives
9.1.1 Design -Builder designates the individual listed below as its Representative ("Design -
Builder's Representative"):
Chris Costello
Construction Manager
ECO Capistrano Valley, Inc.
32234 Paseo Adelanto
Suite D
San Juan Capistrano, California 92675
Tel: (949) 218-7714
Fax: (949) 218-7716
9.2 Contractor's Representatives
9.2.1 Contractor designates the individual listed below as its Representative ("Contractor's
Senior Representative"):
Tim Healy
Vice President
ARB, Inc.
26000 Commer Centre Drive
Lake Forest, Ca. 92630
949-454-7144
949- 454-7190
ARTICLE 10 — INSURANCE AND BONDS
10.1 Contractor's Insurance Requirements
Contractor, at its sole cost and expense, shall obtain the policies of insurance required by
Exhibit D before commencing the Work and shall maintain such insurance in effect all times
during this Agreement.
Capistrano Valley Water District
San Juan Basin Desalter Project
UOU84
41=61
412574.1
Page 47
Construction Agreement
10.1.1 Contractor shall be responsible for ensuring that all Subcontractors performing Project
Work obtain and maintain all insurance required by Applicable Laws in connection with
their presence and performance of Work for the Project.
10.1.2 Contractor and its Subcontractors and Sub -Subcontractors warrant that the insurance
coverage set forth in Exhibit D shall not exclude coverage due to participation in
design/build projects or similar exclusions that could compromise coverage because of
the design -build delivery of the Project.
10.1.3 Prior to commencing any Work, Contractor shall provide Design -Builder with certificates
evidencing that (i) all insurance obligations required by the Contract Documents are in
full force and in effect and will remain in effect for the duration required by the Contract
Documents and (ii) no insurance coverage will be canceled, renewal refused, or
materially changed unless at least thirty (30) days prior written notice is given to Design -
Builder.
10.2 Performance and Payment Bonds
10.2.1 Prior to the commencing the Work, Contractor shall furnish a performance bond
conditioned on Contractor's faithful performance of all of its obligations under this
Agreement which shall remain in effect until the end of the Warranty Period. The
performance bond shall be in a form acceptable to Design -Builder as provided in the
Contract Documents.
10.2.2 Prior to commencing the Work, Contractor shall furnish a payment bond in a form
acceptable to Design -Builder as provided in the Contract Documents that complies with
the requirements of California Civil Code Sections 3096 and 3248.
10.2.3 The performance bond and payment bond shall each be in the amount of the Guaranteed
Maximum Price.
10.2.4 The performance bond and payment bond shall remain in effect for one year after the
date of Acceptance.
10.4.2 The performance bond and payment bond shall be issued by admitted surety insurers
having an AM Best rating of "A" or better. All Bonds signed by an agent must be
accompanied by a certified copy of such agent's authority to act.
10.4.3 If the surety on any bond furnished by the Contractor is declared bankrupt or becomes
insolvent or its right to do business is terminated in any state, the Contractor shall within
seven (7) days thereafter substitute another bond and surety, which must be acceptable to
Capistrano Valley Water District Page 48 Construction Agreement
San Juan Basin Desalter Project
4108381
4 ffS28 2
412574.1
the Design -Builder. Absent such a timely substitution, Design Builder may terminate this
Agreement for Cause.
ARTICLE 11— INDEMNIFICATION
11.1 Patent and Copyright Infringement
11.1.1 Contractor shall defend any action or proceeding brought against Owner or Design -
Builder based on any claim that the Work, or any part thereof, or the operation or use of
the Work or any part thereof, constitutes infringement of any United States patent or
copyright, now or hereafter issued. Design -Builder shall give prompt written notice to
Contractor of any such action or proceeding and will reasonably provide authority,
information and assistance in the defense of same. Contractor shall defend, indemnify
and hold harmless Owner, Design -Builder and Project Engineer from and against any and
all claims, demands, liabilities, damages and costs, including but not limited to attorneys
fees and expenses awarded against Owner, Design -Builder or Project Engineer in any
such action or proceeding. Contractor agrees to keep Design -Builder informed of all
developments in the defense of such actions.
11.1.2 If Design -Builder is enjoined from the operation or use of the Work, or any part thereof,
as the result of any patent or copyright suit, claim, or proceeding, Contractor shall at its
sole expense take reasonable steps to procure the right to operate or use the Work. If
Contractor cannot so procure such right within a reasonable time, Contractor shall
promptly, at Contractor's option and at Contractor's expense, (i) modify the Work so as
to avoid infringement of any patents, or copyrights, or (ii) replace said Work with Work
that does not infringe or violate any such patent or copyright.
11.1.3 Sections 11.1.1 and 11. 1.2 above shall not be applicable to any suit, claim or proceeding
based on infringement or violation of a patent or copyright (i) relating to a particular
process or product of a particular manufacturer specified by Owner, Design -Builder or
Project Engineer or (ii) arising from modifications to the Work by Owner or Design -
Builder after acceptance of the Work. If the suit, claim or proceeding is based upon
events set forth in the preceding sentence, Design -Builder shall defend, indemnify and
hold harmless Contractor to the same extent Contractor is obligated to defend, indemnify
and hold harmless Design -Builder in Section 11.1.1 above.
11.1.4 The provisions of Section 11.1 shall have no application where the alleged infringement
of any United States patent or copyright is due, in whole or part, to the design of the
Project or where the alleged infringement was mandated by the Contract Documents. In
such event, Design -Builder, to the fullest extent permitted by law, shall indemnify, hold
harmless and defend Contractor and its officers, directors, employees and agents and
Contractor's Subcontractors, from and against claims, losses, damages, liabilities,
Capistrano Valley Water District Page 49 Construction Agreement
San Juan Basin Desalter Project
4108281
41(1328.2
412574.1
including attorney fees and expenses, for the infringement or alleged infringement of any
United States patent or copyright, now or hereinafter issued.
11.2 Tax Claim Indemnification
11.2.1 If, in accordance with Design -Builder's direction, an exemption for all or part of the
Work is claimed for taxes, Design -Builder shall indemnify, defend and hold harmless
Contractor from and against any liability, penalty, interest, fine, tax assessment, attorney
fees or other expenses or costs incurred by Contractor as a result of any action taken by
Contractor in accordance with Design -Builder's directive.
11.3 Payment Claim Indemnification
Providing that Design -Builder is not in breach of its contractual obligation to make payments to
Contractor for the Work, Contractor shall defend, indemnify and hold harmless Owner and
Design -Builder from any claims brought against Owner, Design -Builder, or against the Project
as a result of the failure of Contractor, or those for whose acts it is responsible, to pay for any
services, materials, labor, equipment, taxes or other items or obligations furnished or incurred
for, or in connection with the Work. Within three (3) days of receiving written notice from
Design -Builder that such a claim has been filed, Contractor shall commence to take reasonable
steps necessary to discharge said claim or lien. If Contractor fails to do so, Design -Builder will
have the right to discharge the claim or lien and hold Contractor liable for costs and expenses
incurred, including attorneys' fees.
11.4 Contractor's General Indemnification
The Contractor shall indemnify, defend and hold harmless the Design -Builder, the District, and
their directors, officers, officials, employees, representatives, agents and representatives (each, a
"Design -Builder Indemnitee") and the Trustee and its officers, employees, representatives,
agents and representatives ("Trustee Indemnitee"), from and against (and pay the full amount of)
any and all Loss -and -Expense incurred by a Design -Builder Indemnitee or a Trustee Indemnitee
to third parties arising from or in connection with (or alleged to arise from on in connection
with): (1) any failure by the Contractor to promptly and perform its obligations under this
Service Contract; or (2) the negligence or willful misconduct of the Contractor or any of its
officers, directors, employees, agents, representatives or Subcontractors in connection this
Service Contract. The Contractor shall also indemnify Design -Builder as and to the extent
provided elsewhere in this Agreement. The Contractor's indemnity obligations hereunder shall
not be limited by any coverage exclusions or other provisions in any insurance policy maintained
by the Contractor which is intended to respond to such events. The Contractor shall not,
however, be required to reimburse or indemnify any Design -Builder Indemnitee or Trustee
Indemnitee for any Loss -and -Expense to the extent caused by the negligence or willful
misconduct of any Design -Builder Indemnitee or Trustee Indemnitee or to the extent attributable
Capistrano Valley Water District Page 50 Construction Agreement
San Juan Basin Desalter Project
to any Uncontrollable Circumstance. A Design -Builder Indemnitee or Trustee Indemnitee shall
promptly notify the Contractor of the assertion of any claim against it for which it is entitled to
be indemnified hereunder, and the Contractor shall have the right to assume the defense of the
claim in any Legal Proceeding and to approve any settlement of the claim. These
indemnification provisions are for the protection of the Design -Builder Indemnitee and the
Trustee Indemnitee only and shall not establish, of themselves, any liability to third parties. The
provisions of this Section shall survive termination of this Service Contract.
11.5 Design -Builder's General Indemnification
Design -Builder shall indemnify, defend and hold harmless the Contractor, and its directors,
officers, officials, employees, representatives, agents and representatives (each, a "Contractor
Indemnitee"), from and against (and pay the full amount of) any and all Loss -and -Expense
incurred by a Contractor Indemnitee to third parties arising from or in connection with (or
alleged to arise from on in connection with): (1) any failure by the Design -Builder to perform its
obligations under this Agreement; or (2) the negligence or willful misconduct of the Design -
Builder or any of its officers, directors, employees, agents, representatives or subcontractors in
connection this Agreement. With the exception of any claims, damages or injuries caused or
contributed to by Contractor's negligence or willful misconduct, the Design -Builder shall also
indemnify the Contractor as to any claims arising from damage caused or alleged to have been
caused by noise and/or vibration resulting from Pile Driving activities. The Design -Builder's
indemnity obligations hereunder shall not be limited by any coverage exclusions or other
provisions in any insurance policy maintained by Design -Builder which is intended to respond to
such events. The Design -Builder shall not, however, be required to reimburse or indemnify any
Contractor Indemnitee for any Loss -and -Expense to the extent caused by the negligence or
willful misconduct of any Contractor Indemnitee or to the extent attributable to any
Uncontrollable Circumstance. A Contractor Indemnitee shall promptly notify the Design -
Builder of the assertion of any claim against it for which it is entitled to be indemnified
hereunder, and the Design -Builder shall have the right to assume the defense of the claim in any
Legal Proceeding and to approve any settlement of the claim. These indemnification provisions
are for the protection of the Contractor Indemnitee only and shall not establish, of themselves,
any liability to third parties. The provisions of this Section shall survive termination of this
Agreement.
ARTICLE 12 — CHANGES
12.1 Design -Builder's Right to Order Changes
Design -Builder shall have the right, without breaching this Agreement, to order changes in the
Work including, without limitation, additions, modifications and deletions thereto.
Capistrano Valley Water District Page 51 Construction Agreement
San Juan Basin Desalter Project
4109291
4 7A 7
412574.1
12.1.1 General Notice Requirement. Except as specifically and expressly provided elsewhere in
the Contract Documents, Contractor shall provide written notice to Design -Builder of any
occurrence, event or circumstance, including any act or omission by Design -Builder and
any inaccuracy, ambiguity or error in the Contract Documents, for which Contractor
reasonably believes it is entitled to an adjustment in the Guaranteed Maximum Price
and/or Contract Time(s). Said notice must be provided no later than ten (10) days after
Contractor's discovery of the occurrence, event or circumstance and the failure to provide
such notice shall constitute a waiver of Contractor's right to any relief.
12.1.2 General Record Keeping Requirement. Except as specifically and expressly provided
elsewhere in the Contract Documents, Contractor shall keep and maintain accurate
records of all labor, services, equipment or materials furnished for which Contractor
reasonably believes it will be entitled to an adjustment in the Guaranteed Maximum Price
and/or Contract Time(s). Such records shall be in the form required by Owner from
Design -Builder and shall include, at a minimum, daily records of actual quantities of
labor, service, equipment or materials furnished by Contractor as submitted on a daily
basis for verification by Design -Builder or its representative, original receipts, invoices,
delivery tickets, weigh tickets, photographs and daily extra work reports, and records of
payments made by Contractor.
12.1.3 Construction Schedule. Any request by Contractor for a Change Order shall include an
analysis of its impact on the Construction Schedule, including the Schedule of Values.
Following the issuance of any Change Order, Contractor shall submit a proposed update
to the Construction Schedule incorporating the work of the Changer Order therein in the
manner required for preparation of the Construction Schedule provided at Exhibit C.
Contractor shall make any revisions reasonably required by Design -Builder to the
proposed update to the Construction Schedule.
12.1.3 Effect of Failure to Give Notice or to Keep Records. Except as specifically and expressly
provided elsewhere in the Contract Documents, Contractor's failure to provide the notice
required under Section 12.1.1 or to keep records required under Section 12.1.2 shall
constitute a waiver of any right Contractor may have otherwise had to obtain an
adjustment in the Guaranteed Maximum Price or Contract Time(s)
12.2 Change Orders
12.2.1 The Guaranteed Maximum Price and Contract Time(s) may not be changed except by
written Change Order issued pursuant to this Article 12. A Change Order is a written
instrument issued after execution of this Agreement signed by Design -Builder and
Contractor, stating their agreement upon all of the following as applicable:
1 Additions, deletions, changes and/or modifications to the Work;
Capistrano Valley Water District Page 52 Construction Agreement
San Juan Basin Desalter Project
4108181
410828.1
412574.1
2 Changes to the Guaranteed Maximum Price;
3 Changes to the Contract Time(s); and
4 Effect of the change on the Construction Schedule, including the critical path, and
the Schedule of Values.
12.2.2 Except for Minor Changes, the Work, the Guaranteed Maximum Price, the Contract
Time(s) and the Construction Schedule may not be changed except by written Change
Order.
12.2.3 Minor changes in the Work are those that do not increase Contractor's cost of performing
the Work and/or the Contract Time and do not materially and adversely affect the Work
including the design, quality, performance and workmanship required by the Contract
Documents. Design -Builder may make minor changes, as defined above, in the Work
consistent with the intent of the Contract Documents, provided, however, that Design -
Builder shall promptly inform Contractor, in writing, of any such changes. Design -
Builder may request minor changes, as defined in this paragraph, without an adjustment
in the Guaranteed Maximum Price and/or Contract Time.
12.2.4 All changes in the Work authorized by applicable Change Order shall be performed
under the applicable conditions of the Contract Documents except as modified by the
Change Order.
12.3 Owner -Generated Changes
12.3.1 Contractor acknowledges Owner's authority to make changes in the Work as provided in
Section 6.11 of the Service Contract.
12.3.2 Design -Builder shall promptly notify Contractor of any Owner requested or directed
changes. As provided in Section 6.11 of the Service Contract, Contractor shall promptly
thereafter submit a lump -sum quotation for the cost of performing said change including
the effect of such change on the current Construction Schedule, including extensions of
the Contract Time(s) required to perform said change, and any acceleration of the Work
required to perform said change without modifying the Contract Time(s). Contractor
shall also advise whether, in its judgment, the proposed change will affect the Project's
ability to satisfy the Performance Guarantees under the Service Contract. Contractor
assumes no responsibility in connection with any opinions expressed in connection with
Owner Requested Changes.
12.3.3 Design -Builder, with the Contractor's assistance, as required, shall promptly proceed to
negotiate the terms of such change with Owner. Contractor shall not be obligated to
Capistrano Valley Water District Page 53 Construction Agreement
San Juan Basin Desalter Project
41082&3
410428.2
412574.1
proceed with the performance of an Owner -directed change except following agreement
as to the terms of a Change Order as provided at Section 6.11 of the Service Contract.
12.3.4 Contractor shall provide Cost Substantiation for Work performed pursuant to an Owner -
directed Change Order as required under Sections 6.11(F) and 16.6 of the Service
Contract.
12.4 Uncontrollable Circumstances
12.4.1 The rights, duties and obligations of Design -Builder and Contractor with regard to
Uncontrollable Circumstances shall be the same as those between Owner and Design -
Builder as set forth at Sections 14.2(A), (B) and (C) of the Service Contract.
12.4.2 Contractor shall provide notice of any Uncontrollable Circumstance and comply with the
conditions and other provisions of Sections 14.2(B) and (C) of the Service Contract with
sufficient time for Design -Builder to satisfy all conditions precedent to its right to seek an
adjustment in its compensation or time for performance of its obligations from Owner
due to an Uncontrollable Circumstance.
.1 Should Contractor failure to provide any notice or fail to satisfy any condition
necessary to seek an adjustment in the Guaranteed Maximum Price or Contract
Time(s), and as a result of such failure Design -Builder cannot obtain a like
adjustment in its compensation or time for performance of its obligations,
Contractor shall be deemed to have waived any right it may have otherwise had to
seek an adjustment in the Guaranteed Maximum Price or Contract Time(s) as a
result of an Uncontrollable Circumstance.
12.4.3 Contractor's compensation in the event of an Uncontrollable Circumstance shall be
determined as set forth at Sections 14.2(C), 16.5 and 16.6 of the Service Contract and
Contractor shall comply with the provisions thereof.
12.5 Design -Builder Generated Changes; Changes Due to Differing Site Conditions
Except for changes governed by Sections 12.3 and 12.4 of this Agreement, any change in the
Work or the Contract Time(s) requested by Design -Builder, and any change in the Guaranteed
Maximum Price or Contract Time(s) requested by Contractor due to an occurrence, direction or
other circumstance for which Contractor reasonably believes Design -Builder is responsible and
for which Contractor reasonably believes it is entitled to a change in the Guaranteed Maximum
Price or Contract Time(s), shall be governed by this Section 12.5.
12.5.1 Change Directed by Design -Builder; Work Change Directive. Should Design -Builder
wish to direct a change in the Work, it may issue a Work Change Directive to Contractor
Capistrano Valley Water District Page 54 Construction Agreement
San Juan Basin Desalter Project
4108381
31()838.1
412574.1
describing such change. A Work Change Directive is a written order prepared and signed
by Design -Builder, directing a change in the Work prior to agreement on an adjustment
in the Guaranteed Maximum Price and/or the Contract Time(s).
.1 If directed in writing by Design -Builder, Contractor shall immediately commence
performance of the requested change.
.2 Promptly after issuance of a Work Change Directive, Contractor shall submit a
proposed Change Order for Design -Builder's consideration setting forth any
requested change in the Guaranteed Maximum Price, the Contract Time(s), and
steps that will be required to implement and perform the change without delaying
the Contract Time(s).
.3 Design -Builder and Contractor shall thereafter negotiate in good faith to arrive at
the terms of a Change Order.
12.5.2 Change Requested by Contractor. Should Contractor seek an adjustment in the Contract
Price or Contract Time(s) due to any occurrence, direction or other circumstance for
which Contractor reasonably believes Design -Builder is responsible and for which
Contractor reasonably believes it is entitled to a change in the Guaranteed Maximum
Price or Contract Time(s), Contractor shall promptly submit a Change Order Request to
Design -Builder setting for the following:
.1 The reason for the requested change, including supporting documents;
.2 Any proposed change to the Guaranteed Maximum Price; and
.3 Any proposed change to the Contract Time(s) and Construction Schedule
including steps that will be required to avoid any delay to the Contract Time(s);
12.5.3 Guaranteed Maximum Price Adjustment. The increase or decrease in Guaranteed
Maximum Price resulting from a change in the Work shall be determined by Design -
Builder by one or more of the following methods:
1 Unit prices set forth in Exhibit G to the Agreement or as subsequently agreed in
writing between the parties which shall include markup.
.2 A mutually accepted, lump sum, properly itemized as supported by sufficient
substantiating data to permit evaluation by Design -Builder which shall include
markup.
.3 Time and Materials plus markup.
Capistrano Valley Water District
San Juan Basin Desalter Project
4109391
410828,2
412574.1
Page 55
Construction Agreement
4 If Contractor and Design -Builder cannot agree on the terms of an adjustment to
the Guaranteed Maximum Price, they shall resolve their differences pursuant to
Article 13 of this Agreement. However, in such case, Contractor shall continue to
prosecute the Work, including any disputed extra Work, so as to complete the
Project within the Contract Time(s).
5 If Contractor and Design -Builder cannot agree on the terms of an adjustment to
the Guaranteed Maximum Price, Design -Builder's total liability to Contractor in
the event it is ultimately determined that an adjustment is warranted shall not
exceed Contractor's actual cost to perform the disputed Work plus a single, all-
inclusive mark-up of 15%. The term "actual cost" as used in this sub -section
shall not include indirect costs such as extended home -office overhead, extended
general conditions, lost revenues, lost profits and other such indirect costs.
12.5.4 Ad'ustment in the Contract Times and Construction Schedule.
1 Contractor shall update the Construction Schedule to reflect any adjustment in the
Contract Time(s) or change in the Work that alters the critical path of the
Construction Schedule.
.2 Contractor agrees that it shall not be entitled to an extension of the Contract
Time(s) that would extend the Substantial Completion date or the Scheduled
Acceptance Date as set forth at Section 7.12 of the Service Contract, unless those
deadlines are extended by Owner.
.3 To the extent that delays are caused to Contractor's Work by the acts or omissions
of the Design -Builder or someone for whom the Design -Builder is responsible,
and said delay was not caused or contributed to by the Contractor, Contractor's
relief for said delay shall, at Design -Builder's sole option, be either 1) an
extension of the Contract Times, 2) Contractor's reasonable acceleration costs to
maintain the Construction Schedule, or 3) both.
12.6 Emergencies
In any emergency affecting the safety of persons and/or property, which concerns or relates to
the Work, Contractor shall immediately take such actions as it deems necessary to prevent the
threatened damage, injury or loss. Any change in the Guaranteed Maximum Price and/or
Contract Time(s) on account of emergency work shall be determined as provided in this Article
12.
Capistrano Valley Water District
San Juan Basin Desalter Project
4108291
41h=
412574.1
Page 56
Construction Agreement
ARTICLE 13 — DISPUTE RESOLUTION
13.1 Avoidance of Disputes
The parties are fully committed to working with each other throughout the Project and agree to
communicate regularly with each other at all times so as to avoid or minimize disputes or
disagreements. If disputes or disagreements do arise, Contractor and Design -Builder each
commit to resolving such disputes or disagreements in an amicable, professional and expeditious
manner so as to avoid unnecessary losses, delays and disruptions to the Work.
13.2 Disputes Involving Owner
In the event of a dispute between Design -Builder and Contractor involving or potentially
involving Owner, Contractor agrees that the resolution of such dispute shall be governed by
Sections 13.15, 13.16 and 13.17 of the Service Contract. Contractor shall ensure that its
Subcontractors are bound to Contractor to the same extent as Contractor is bound to Design -
Builder under this Section 13.3.
13.3 Disputes Involving Contractor and Design -Builder
13.3.1 In the event of a dispute involving only Contractor and Design -Builder, Contractor and
Design -Builder will first attempt to resolve such claim, dispute or controversy at the field
level through discussions between Design -Builder's Representative and Contractor's
Representative.
13.3.2 If such efforts fail, either party may by written notice to the other demand a meeting
between the Parties attended by representatives with full authority to speak for and bind
their respective Parties. Within no more than seven (7) days thereafter, the parties shall
exchange a concise summary of their respective positions including supporting
documentation and identifying key persons with personal knowledge of the issue in
dispute. The parties shall then meet in person within no more than ten (10) days after the
date of the initial notice to attempt to resolve their differences.
13.3.3 If the parties are unable to resolve their dispute under Sections 13.3.1 and 13.3.2, the
parties shall be entitled to pursue all available legal remedies except as provided in this
Article 13.
13.4 Continuation of Work
Contractor shall continue to diligently perform and prosecute the Work in the event of a dispute
and take all steps necessary to achieve the Contract Time(s) including, as necessary, devoting
more labor to the Work, scheduling additional shifts and/or otherwise accelerating the Work.
Capistrano Valley Water District Page 57 Construction Agreement
San Juan Basin Desalter Project
4lesss4
41828
412574.1
Except as expressly and specifically provided otherwise in this Agreement, Contractor shall be
liable for all Loss and Expense and all consequential, liquidated and other damages incurred by
Design -Builder should Contractor abandon, stop, cease performing or otherwise terminate this
Agreement.
13.5 Attorneys Fees
In addition to any other relief to which a Party may be entitled, the prevailing Party in any
dispute arising from or relating to this Agreement shall be entitled to recover its reasonable
attorneys' fees and expert witness fees.
ARTICLE 14 — MISCELLANEOUS
14.1 Assignment
14.1.1 Contractor shall not, without the written consent of Design -Builder, assign, transfer or
sublet any portion or part of the Work or the obligations required by the Contract
Documents.
14.1.2 Contractor expressly acknowledges that at some point during the performance of the
Work Owner may transfer its interest in the Project to the City or another Governmental
Body as provided at Section 16.9 of the Service Contract. Contractor agrees to be bound
to the provisions of Sections 16.9(B), (C) and (D) of the Service Contract.
14.1.3 Contractor expressly acknowledges that at some point during the performance of this
Agreement, Design -Builder will transfer and assign all of its rights and obligations
hereunder to a Special Business Entity ("SBE"). Contractor agrees to the assignment of
this Agreement to said SBE and agrees to release ECO Resources, Inc. from any
obligations or liability hereunder upon such Assignment.
14.1.4 In further consideration for Contractor's agreement to the assignment described in
Section 14.1.3 above, Design -Builder shall advance and pay to Contractor, as part of the
Guaranteed Maximum Price set forth in Section 6.1.1 hereunder, 5% of the Guaranteed
Maximum Price ($825,000), with half of said amount ($412,500) to be paid to Contractor
within ten (10) days of Design -Builder's receipt of Contractor's first Payment
Application, and the balance($412,500) to be paid within thirty (30) days of Design -
Builder's receipt of said Payment Application, and 2) Design -Builder shall use its best
efforts to maintain ARB in a cash neutral position with respect to the payments for its
performance of the Work during the term of this Agreement.
Capistrano Valley Water District Page 58 Construction Agreement
San Juan Basin Desalter Project
U08284
tea.+
412574.1
14.2 Successors and Assigns
This Agreement shall inure to the benefit of the Parties respective successors and assigns.
14.3 Governing Law, Jurisdiction and Venue
The Agreement shall be governed by the laws of the State of California. Jurisdiction and venue
for any lawsuit or other proceeding arising from or relating to this Agreement shall lie in a
Federal or State court located in Orange County, California.
14.4 Severability
If any provision or any part of a provision of the Contract Documents shall be finally determined
to be superseded, invalid, illegal, or otherwise unenforceable pursuant to any Applicable Laws or
court order, such determination shall not impair or otherwise affect the validity, legality, or
enforceability of the remaining provision or parts of the provision of the Contract Documents,
which shall remain in full force and effect as if the unenforceable provision or part were deleted.
14.5 No Continuing Waiver
The failure of either Design -Builder or Contractor to insist, in any one or more instances, on the
performance of any of the obligations required by the other under the Contract Documents shall
not be construed as a waiver or relinquishment of such obligation or right with respect to future
performance.
14.6 Headings
14.6.1 The headings used in this Agreement, or any other Contract Document, are for ease of
reference only and shall not in any way be construed to limit or alter the meaning of any
provision.
14.7 Notice
Notices required under this Agreement shall be given using the fastest means warranted by the
circumstances providing for proof of delivery. Whenever the Contract Documents require that
notice be provided to the other party, notice will be deemed to have been validly given, four (4)
days after being sent by registered or certified mail, postage prepaid, addressed as indicated
below or, if transmitted to the other party by fax, at the fax number indicated below. Any notice
sent by fax will be deemed to have been validly given by the time stated in a machine generated
fax confirmation notice showing that notice was received at the number of the intended recipient.
Capistrano Valley Water District
San Juan Basin Desalter Project
U08284
410828 2
412574.1
Page 59
Construction Agreement
If to Design -Builder:
Chris Costello
Construction Manager
ECO Capistrano Valley, Inc.
32234 Paseo Adelanto
Suite D
San Juan Capistrano, California 92675
Tel: (949) 218-7714
Fax: (949) 218-7716
If to Contractor:
Tim Healy
Vice President
ARB, Inc.
26000 Commer Centre Drive
Lake Forest, Ca. 92630
Tel: 949- 454- 7144
Fax: 949- 454-7190
14.8 Amendments
This Agreement may not be changed, altered, or amended in any way except in writing signed by
a duly authorized representative of each party as provided herein.
14.9 Prevailing Wages
Contractor shall comply and shall ensure that its Subcontractors comply with California Labor
Code Section 1770 and the provisions that follow regarding the payment of prevailing wages and
the keeping and production of certified payroll records. A schedule of the general prevailing
wage rates as determined by the Director of Industrial Relations will be on file at Design -
Builder's principal office and will be made available to any interested party upon request. By
this reference, the applicable schedule of prevailing wage rates is made a part of the Contract
Documents.
14.9.1 Contractor shall pay not less than the prevailing wage rates to all covered workers
employed by Contractor in the performance of the Work.
14.9.2 Contractor shall require all Subcontractors to pay not less than the prevailing wage rates
to all covered workers employed by such Subcontractors in the performance of the Work.
Capistrano Valley Water District Page 60 Construction Agreement
San Juan Basin Desalter Project
ROU84
410928
W
412574.1
14.9.3 Contractor shall be subject to the penalties provided by the California Labor Code for
failing to pay workers less than the applicable prevailing wage rate. Such penalties may
be deducted by Design -Builder from payments otherwise due Contractor hereunder.
14.9.4 Certified Payroll Records
.1 In accordance with Section 1776 of the California Labor Code Contractor and
each Subcontractor shall keep an accurate payroll record, showing the name,
address, social security number, work classification, straight time and overtime
hours worked each day and week, and the actual per diem wages paid to each
journeyman, apprentice, worker, or other employee employed by him or her in
connection with the public work. Each payroll record shall contain or be verified
by a written declaration that it is made under penalty of perjury, stating both of
the following: (a) the information contained in the payroll record is true and
correct, and (b) the employer has complied with the requirements of Sections
1771, 1811, and 1815 of the California Labor Code for any work performed by
his or her employees on the public works project.
.2 The payroll records enumerated under Paragraph 17.2.1 shall be certified and
shall be available for inspection at all reasonable hours at the principal office of
the Contractor on the following basis:
3 A certified copy of an employee's payroll record shall be made available for
inspection or furnished to the employee or his or her authorized representative on
request.
4 A certified copy of all payroll records enumerated in Paragraph 17.2.1 shall be
made available for inspection or furnished upon request to a representative of the
Owner, the Division of Labor Standards Enforcement, and the Division of
Apprenticeship Standards of the Department of Industrial Relations.
5 A certified copy of all payroll records enumerated in Paragraph 17.2.1 shall be
made available upon request by the public for inspection or copies thereof made;
provided, however, that a request by the public shall be made through either the
body awarding the contract, the Division of Apprenticeship Standards, or the
Division of Labor Standards Enforcement. The public shall not be given access to
the records at the principal office of the Contractor.
14.9.5 Certified payroll records shall be on forms provided by the Division of Labor Standards
Enforcement or shall contain the same information as the forms provided by the division.
Capistrano Valley Water District Page 61 Construction Agreement
San Juan Basin Desalter Project
UOU84
.9 3 OR2R.�
412574.1
14.9.6 Any copy of records made available for inspection as copies and furnished upon request
to the public or any public agency by the awarding body, the Division of Apprenticeship
Standards, or the Division of Labor Standards Enforcement shall be marked or obliterated
in such a manner as to prevent disclosure of an individual's name, address, and social
security number. The name and address of the Contractor awarded the contract or
performing the contract shall not be marked or obliterated.
14.9.7 The Contractor shall inform the body awarding the contract of the location of the certified
payroll records including the street address, city and county, and shall, within 5 working
days, provide a notice of change of location and address.
14.9.8 The Contractor shall have 10 days in which to comply subsequent to receipt of written
notice specifying in what respects the Contractor must comply with this Section. In the
event that the Contractor fails to comply within the 10 -day period, he or she shall, as a
penalty to the state or political subdivision on whose behalf the contract is made or
awarded, forfeit twenty-five dollars ($25.00) for each calendar day, or portion thereof, for
each worker, until strict compliance is effectuated. Upon the request of the Division of
Apprenticeship Standards or the Division of Labor Standards Enforcement, these
penalties shall be withheld from progress payments then due. A contractor is not subject
to a penalty assessment pursuant to this section due to the failure of a subcontractor to
comply with this section.
14.9.9 Notwithstanding any contrary provisions in the Contract Documents, Design -Builder
shall have discretion to require that Contractor file copies of its and its Subcontractors'
certified payroll records with Design -Builder as a condition precedent to Design -
Builder's obligation to make any of the payments to Contractor required by the Contract
Documents.
14.10 Employment of Apprentices
Contractor shall comply and shall ensure that its Subcontractors comply with the requirements of
Sections 1777.5 and 1777.6 of the Labor Code in the employment of apprentices. Information
relative to apprenticeship standards, wage schedules, and other requirements may be obtained
from the Director of Industrial Relations, ex officio the Administrator of Apprenticeship, San
Francisco, California, or from the Division of Apprenticeship Standards and its branch offices.
Willful violations of Section 1777.5 will result in a forfeiture of the maximum statutory amount
for each calendar day of non-compliance which may be withheld from progress payments by
Design -Builder upon notice from the Department of Industrial Relations pursuant to Labor Code
Section 1777.7. Willful violations of Section 1777.5 may also result in the suspension of the
Contractor's right to bid on or receive the award of any public works construction contract, as
provided in Section 1777.7.
Capistrano Valley Water District Page 62 Construction Agreement
San Juan Basin Desalter Project
410828,1-
412574.1
14.11 Working Hours
Contractor shall comply with all applicable provisions of Section 1810 to 1815, inclusive, of the
California Labor Code relating to working hours.
14.12 Workers' Compensation; Certification Re: Workers' Compensation
In accordance with the provisions of Section 3700 of the California Labor Code, the Contractor
shall secure the payment of compensation to its employees. By submitting a bid for the Project
and by executing the Agreement, Contractor shall be deemed to have made the following
certification:
"I am aware of the provisions of Section 3700 of the Labor Code which require every employer
to be insured against liability for workers' compensation or to undertake self-insurance in
accordance with the provisions of that code, and I will comply with such provisions before
commencing the performance of the Work of this Contract."
Notwithstanding the foregoing provisions, before the Contract is executed on behalf of the
Design -Builder, a bidder to whom a contract has been awarded shall furnish satisfactory
evidence that it has secured in the manner required and provided by law the payment of workers'
compensation.
14.13 Concrete Forms, Falsework, And Shoring
Without limiting Contractor's obligation to comply with all Applicable Laws regarding safety,
Contractor shall comply fully with the requirements of Section 1717 of the Construction Safety
Orders, State of California, Department of Industrial Relations, regarding the design of concrete
forms, falsework and shoring, and the inspection of same prior to placement of concrete. Where
said Section 1717 requires the services of a civil engineer registered in the State of California to
approve design calculations and working drawings of the falsework or shoring system, or to
inspect such system prior to placement of concrete, the Contractor shall employ a registered civil
engineer for these purposes, and all costs therefore shall be deemed included in the Guaranteed
Maximum Price.
14.14 Protection Of Workers In Trench Excavations
Without limiting Contractor's obligation to comply with all Applicable Laws regarding safety, as
required by Section 6705 of the California Labor Code and in addition thereto, whenever the
Work involves the excavation of any trench or trenches 5 feet or more in depth, Contractor shall
submit for acceptance by Design -Builder or by a registered civil or structural engineer, employed
by the Design -Builder, to whom authority to accept has been delegated, in advance of
excavation, a detailed plan showing the design of shoring, bracing, sloping, or other provisions to
Capistrano Valley Water District Page 63 Construction Agreement
San Juan Basin Desalter Project
Ues184
412574.1
be made for worker protection from the hazard of caving ground during the excavation, of such
trench or trenches. If such plan varies from the shoring system standards established by the
Construction Safety Orders of the Division of Occupational Safety and Health, the plan shall be
prepared by a registered civil or structural engineer employed by Contractor, and all costs
therefore shall be included in the Guaranteed Maximum Price. Nothing in this Section shall be
deemed to allow the use of a shoring, sloping, or other protective system less effective than that
required by the Construction Safety Orders. Nothing in this Section shall be construed to impose
tort liability on Design -Builder or Owner, or any of their officers, agents, representatives, or
employees. Excavation shall not start until Contractor has obtained a permit from the California
Division of Industrial Safety and has posted it at the site.
14.15 Non -Discrimination
Contractor shall not discriminate against any employee or applicant for employment because of
race, religious creed, color, national origin, ancestry, physical disability, mental disability,
medical condition, marital status, sex, sexual orientation or age in any manner prohibited by law.
Contractor shall take affirmative action to ensure that applicants are hired and that employees are
treated during employment in accordance with this non-discrimination obligation. Such action
shall include, but not be limited to, employment, upgrading, demotion or transfer, recruitment or
recruitment advertising, layoff or termination, rates of pay or other forms of compensation, and
selection for training, including apprenticeship. Contractor shall post in conspicuous places,
available to employees and applicants for employment, notices setting forth the provisions of this
Article.
14.16 Publicity
Contractor shall not make any written or oral statement relating to the Work or the Project to any
member of the press or public media without prior written approval of Design -Builder. Design -
Builder reserves the right to review and approve all Contractor -related copy prior to publication.
Contractor agrees not to allow Design -Builder -related copy to be published in the Contractor's
advertisements or public relations programs without prior approval from the Design -Builder's
Representative.
Capistrano Valley Water District Page 64 Construction Agreement
San Juan Basin Desalter Project
41083&4
41(!&Sv
a1Ma. 1
14.17 Authority
Each person executing this Agreement represents and warrants that they have the authority to do
so on behalf of the Party for whom they are signing and that they are fully authorized to bind
said Party to all of the terms, conditions and obligations herein.
In executing this Agreement, Design -Builder and Contractor each individually represents
that it has the necessary financial resources to fulfill its obligations under this Agreement, and
each has the necessary corporate approvals to execute this Agreement, and perform the Work
described herein.
ECO RESOURCES, INC.
("Design -Builder")
(Signature)
Printed Name: Peter J. Moerbeek
Title: President
Date:
Capistrano Valley Water District
San Juan Basin Desalter Project
008284
412574.1
ARB, INC.
("Contractor")
(Signature)
Contractor's License Number
Printed Name:Tim Healy
Title:Vice President
Date:
Page 65
Construction Agreement
EXHIBIT A — SCOPE OF WORK
1.0 General
The Work shall generally consist of furnishing all labor, materials, equipment, supplies, tools,
temporary facilities, sanitary facilities, temporary power and light, chemicals, parking, traffic
control, security, temporary utilities, dumpsters and trash collection and other services and
materials necessary to construct and complete the Project in accordance with the Contract
Documents. The Guaranteed Maximum Price shall be deemed good and sufficient consideration
for performing the Work.
2.0 Project Elements
The Work shall include the following elements described in Section 6.2(A), (C), (D), and (E) of
the Service Contract and as described in greater detail Appendix 1 of the Service Contract,
excluding Capital Modifications:
Plant
Project Structures (listed in Attachment 1 to Appendix 1 of the Service Contract)
Project Equipment (listed in Attachment 2 to Appendix 1 of the Service Contract)
Project Wells (listed in Attachment 1 to Appendix 1 of the Service Contract)
Project Pipelines (listed in Attachment 1 to Appendix 1 of the Service Contract)
Raw Water Transmission Line
Booster Pumping Station
Additional Assets
Finished Water Transmission Line
Concentrate Disposal Line
Abandonment of Existing Wells
3.0 Permits
Contractor shall be responsible for obtaining the Permits described at Exhibit B.
4.0 Site Work
The Work shall include all grading, excavation, demolition and other preparatory work for the
Project Sites. Contractor shall be responsible for the import of necessary soils and the disposal
of all unsuitable or excess materials, both in preparation for and following construction, except
as provided in the Contract Documents.
Capistrano Valley Water District Exhibit A — Scope of Work Construction Agreement
San Juan Basin Desalter Project Page 1
UON84
412574A
5.0 Initial Work
Contractor shall be responsible to perform any initial construction as defined in Section 4.4 of
the Service Contract.
6.0 Underground Utilities
The Work shall include re-routing or replacing any known interfering underground utilities.
Contractor shall be responsible for coordinating and performing such work in cooperation with
and subject to the requirements of the affected utility owner.
7.0 Project Wells
The Work shall include construction of the Project Wells in accordance with Attachment 1 to
Appendix 5 of the Service Contract. Contractor shall promptly advise Design -Builder of any
inconsistency between the Project Design and Attachment 1 to Appendix 5 of the Service
Contract.
8.0 Plant Foundation Construction Method
Pursuant to Section 5.4 of the Service Contract, the District has elected to use the pile driving
foundation construction method for the construction of the Plant foundation on the Plant Site.
Said construction shall comply with this Agreement, the Service Contract, and the requirements
set forth in that certain Contract Administration Memorandum No. SC 2002-3, dated November
_, 2002 entitled "District Election as to Foundation Construction Method pursuant to Section
5.4(E) of the Service Contract".
9.0 Reports and Meetings
Guaranteed Maximum Price shall include compensation to Contractor to attend all meetings and
to produce all reports, in the required quantities, which are reasonably required by Design -
Builder. Contractor shall anticipate the need for substantial coordination with the City, the
District, the Trustee and their various representatives.
10.0 Start -Up and Testing
The Work shall include the cost of assisting the Design -Builder and the Project Engineer with
Project start-up and testing as provided at Section 7.3, Section 7.6 of the Service Contract and
Appendix 8 of the Service Contract. The Work shall include the furnishing of all utilities
required to conduct such tests, except raw water. The Work shall include the furnishing of all
chemicals required to conduct such tests. No start up or testing work shall be performed without
advance written notice to the Design -Builder and Contractor shall comply with all permit
Capistrano Valley Water District Exhibit A — Scope of Work Construction Agreement
San Juan Basin Desalter Project Page 2
4108191
410828.2
412574.1
requirements relating to said start-up and testing. Contractor shall be responsible for the lawful
disposal of all water generated for start-up and testing.
11.0 Training; Operations and Maintenance Manual
The Work shall include providing Design -Builder with assistance as needed for the production of
the Operations and Maintenance Manual as described in the Service Contract and for providing
training for specialized equipment necessary for operation and maintenance of the Project after
completion.
Capistrano Valley Water District Exhibit A — Scope of Work Construction Agreement
San Juan Basin Desalter Project Page 3
4108284
410328.2
412574.1
EXHIBIT B — CONTRACTOR PERMITS
Contractor shall be responsible to obtain the following construction -related permits:
Permit Agenc
Excavation Permits CAL -OSHA
Grading Permits City of San Juan Capistrano
Building Permits City of San Juan Capistrano
Equipment Permits SCAQMD
Traffic Control Plan City of San Juan Capistrano
Capistrano Valley Water District Exhibit B — Contractor Permits
San Juan Basin Desalter Project Page 1
UOU84
41 W92&
412574.1
Construction Agreement
EXHIBIT C — PROJECT SCHEDULE AND MILESTONES
1.0 Progress of the Work
It is expressly understood and agreed that the time of beginning, the rate of progress, and the
time of completion of the Work are of the essence of this Agreement. Design -Builder is entitled
to extensions of time under the Service Contract to complete construction of the Project only
under extremely limited circumstances and is liable to Owner and others for substantial
liquidated damages in the event of delay. Accordingly, time is of the utmost essence in the
performance, prosecution and completion of the Work and the Project, and the Project Schedule
requirements set forth herein are critical toward achieving that requirement. Contractor,
therefore, expressly agrees that it shall prosecute and perform the Work with such progress as
required to prevent any delay to the completion of the Work and the Project. Any float in the
Contractor's construction schedule is owned by the Project and Contractor waives any claim for
delays that adversely affect any float in Contractor's construction schedule.
2.0 Contractor's Construction Scheduler
Contractor shall employ or retain the services of a construction scheduler who shall have
verifiable experience as the person primarily responsible for preparing and maintaining the
construction schedule on projects of the same or similar size and nature as this Project. The
person in charge of scheduling shall be required to attend each Project Progress meeting.
3.0 General
3.1 Intent. The Project Schedule shall provide Design -Builder with a tool to monitor and
follow the progress of all phases of the Work and shall serve as the basis for all payments
by Design -Builder to Contractor. The Project Schedule shall provide for the completion
of all elements of the Work within the Contract Times
3.2 Schedule Methodology. The scheduling method to be used shall be a critical path
method schedule in the form of an activity on node precedence diagram network capable
of identifying the critical path.
3.3 Scheduling System. Contractor shall use Primavera Project Planner, P3 Version 3.0 or
later or comparable system commonly in use in the industry for projects of commensurate
size and complexity acceptable to Design -Builder. The system shall be capable of
handling, processing, printing, and plotting data to satisfy all scheduling requirements
herein.
Capistrano Valley Water District Exhibit C — Project Schedule and Milestones Construction Agreement
San Juan Basin Desalter Project Page 1
uesas 1-
4iftUa.2
412574.1
4.0 Contents of Schedule
4.1 Network Details. The Project Schedule shall include time -scaled network diagrams as
well as computer tabulations. The Project Schedule shall be constructed to show the
order in which the Contractor proposes to carry out the Work, to indicate restrictions of
access and to show availability of Work areas, and availability and use of manpower,
materials and equipment. The Contractor shall utilize the Project Schedule in planning,
scheduling, coordinating, and performing the work under the Contract (including all
activities of Subcontractors, equipment vendors, and Suppliers). The degree of detail
shall include factors to the satisfaction of Design -Builder including, but not limited to,
the following required elements:
4.1.1 Notice to Proceed, which shall provide for the commencement of the Work no later than
December 4, 2002.
4.1.2 All Project Milestones identified in Appendix 21 to the Service Contract.
4.1.3 The following additional events, constraints and/or activities shall described in the
Service Contract:
.1 Issuance of all Governmental Approvals required to commence, prosecute and
complete the Work, including start-up operations, Acceptance Testing, and
operations.
.2 The commencement and completion of construction, furnishing and/or installation
of the Project Improvements, Project Equipment and Project Structures described
in Appendix 1 to the Service Contract.
.3 All purchases, submittals, submittal reviews, manufacturer, test, delivery, and
installation activities for all major material and equipment, and a separate list of
all major items or items of equipment for which the Contractor intends to seek
payment prior to installation.
.4 Preparation, submittal and approval of shop and/or working drawings including a
time frame for at least one (1) re -submittal on all major equipment.
5 Plans for all subcontract work.
6 Assignment of responsibility for performing specific activities.
Capistrano Valley Water District Exhibit C — Project Schedule and Milestones Construction Agreement
San Juan Basin Desalter Project Page 2
4109281
s'2
412574.1
.7 Access to and availability of the Project Sites and Work areas.
.8 Resource loading for cost, manpower, material, and equipment.
.9 Identification of any manpower, material, or equipment restrictions, as well as any
activity requiring unusual shift work, such as two shifts, five (5) or six (6) day
weeks, specified overtime or work at times other than regular days or hours, shall
be clearly identified in the Project Schedule.
.10 Substantial Completion as provided by Section 7.2 of the Service Contract.
.11 Submittal of Acceptance Test Plan in accordance with Section 7.3(A) and
Appendix 8 of the Service Contract including a time frame for at least one (1) re-
submittal.
.12 Issuance of all permits and authorizations required by Applicable Law to
commence Acceptance Test.
.13 Commencement and completion of Acceptance Test as provided in Section 7.6
and Appendix 8 of the Service Contract.
.14 Provisional Acceptance Date as provided in Section 7.8 of the Service Contract.
.15 Issuance of CADHS Approval for the delivery of Finished Water to the Water
System for potable consumption by Owner's customers.
.16 Performance of punch list work as provided in Section 7.15 of the Service
Contract.
17 Final Completion as provided in Section 7.16 of the Service Contract.
4.2 Activity Details
4.2.1 The Project Schedule shall show the critical path and sequence and interdependence of
activities required for complete performance of the Work within the Contract Times,
beginning with the date of the Notice to Proceed and concluding with the date of Final
Completion of the Contract.
4.2.2 Use of float suppression techniques such as preferential sequencing, special lead/lag logic
restraints, extended activity times or imposed date shall be cause of rejection of the
Project Schedule and any revisions or updates. Float belongs to the Project.
Capistrano Valley Water District Exhibit C — Project Schedule and Milestones Construction Agreement
San Juan Basin Desalter Project Page 3
a;esaar
alos:az
412574.1
4.2.3 The activities included in the Project Schedule shall be analyzed in detail to determine
activity time duration in units of project working days. Durations shall be based on the
labor, equipment, and materials required to perform each activity on a normal work day
basis.
4.3 Schedule of Values
4.3.1. The Schedule of Values to be used as the basis for making all payments to Contractor
under the Agreement shall be approved by the Design -Builder. The estimated cost to
perform each work activity shall be noted for each activity in the network on a tabular
listing. The sum of the cost assigned to all activities shall equal the Guaranteed
Maximum Price. The accepted cost loaded Project Schedule shall constitute the Schedule
of Values from which payments will be made to Contractor in accordance with the
provisions of the Agreement.
4.3.2. Contractor shall submit its initial draft Schedule of Values, to Design -Builder in printed
and electronic form at least three (3) days prior to the initial conference described in
Section 2.6 of the Agreement. At the initial conference Contractor and Design -Builder
shall discuss and review Contractor's initial draft Project Schedule of Values.
4.4 Proiect Schedule Reports
4.4.1 The Project Schedule submitted to Design -Builder shall include the time scaled network
diagram. Network diagrams shall be based on early start and early finish dates of
activities shown. The network diagrams submitted to Design -Builder shall also be
accompanied by a computer generated analysis for each activity included in the Project
Schedule. Such analysis shall include at a minimum, the following:
.1 Predecessor and successor activity number and descriptions;
.2 Activity number and description;
.3. Activity code(s);
.4 Scheduled and actual/remaining duration for each activity;
.5 Earliest start date (by calendar date);
.6 Earliest finish date (by calendar date);
.7 Actual start date (by calendar date);
Capistrano Valley Water District Exhibit C — Project Schedule and Milestones Construction Agreement
San Juan Basin Desalter Project Page 4
4109291
4LO82 .z
412574,1
.8 Actual finish date (by calendar date);
.9 Latest start date (by calendar date);
.10 Latest finish date (by calendar date);
.11 Float in work days;
.12 Monetary value of each activity;
.13 Percentage of activity and remaining duration for incomplete activities;
.14 Cumulative value of work complete, based on the Contractor's reported portion of
activities complete and accepted;
.15 Imposed constraints.
5.0 Baseline Schedule
5.1 Initial Submittal and Pre -Construction Conference. Contractor shall submit its initial
draft Project Schedule, including Schedule of Values, to Design -Builder in printed and
electronic form at least three (3) days prior to the initial conference described in Section
2.6 of the Agreement. At the initial conference Contractor and Design -Builder shall
discuss and review Contractor's initial draft Project Schedule and Schedule of Values.
5.2 Variances from Contract Times. Should the initial draft Project Schedule show variances
from the requirements of this Agreement, Contractor shall make specific mention of such
variances in the letter or transmittal.
5.3 Form of Submittal of Initial Draft Project, Schedule: The initial draft Project Schedule
submittal shall include the Project Schedule network diagram and computer tabulation,
including Schedule of Values in the following quantities:
5.3.1 Three (3) sets of the Network Diagram in hard -copy;
5.3.2 Three (3) sets of Computer tabulations in hard -copy;
5.3.3 Three (3) sets of Schedule of Values in hard -copy;
5.3.4 Electronic copy of initial draft Project Schedule in computer storage media acceptable to
Design -Builder.
Capistrano Valley Water District Exhibit C — Project Schedule and Milestones Construction Agreement
San Juan Basin Desalter Project Page 5
4iesssi
41082all
412574.1
5.4 Submittal of Revised Project Schedule for Approval; Acceptance of Baseline Schedule.
Within seven (7) days after the Pre -Construction Conference, Design -Builder shall
provide its written comments and revisions to the initial draft Project Schedule to
Contractor. Contractor shall submit a complete revised Project Schedule incorporating
Design -Builder's comments and revisions within ten (10) days of receipt of Design -
Builder's initial comments and revisions. Design -Builder shall approve or disapprove, in
writing, Contractor's revised Project Schedule within five (5) days after receipt of all
required information. If Design -Builder disapproves Contractor's revised Project
Schedule, Contractor shall make all required corrections and resubmit the Project
Schedule for acceptance. Design -Builder and Contractor shall meet and confer as
necessary to achieve acceptance of the Project Schedule before Contractor's first
payment is due under the terms of this Agreement. The Project Schedule, once accepted
in writing by Design -Builder, shall becomes the Baseline Schedule which shall be used
for monitoring and evaluating all facets of Contractor's performance, including but not
limited to: progress, changes, and delays. The Baseline Schedule shall serve as the basis
for all updates or revisions to the Project Schedule and may not be changed except with
Design -Builder's express written approval.
5.4.1 Design -Builder's acceptance of the Project Schedule, or any subsequent revisions
or updates thereto, shall not constitute a waiver by Design -Builder of Contractor's
obligation to prosecute the Work and complete the Project within the deadlines
imposed by this Agreement or the Service Contract, except as such deadlines may
be modified by written Change Order entered into by the Parties.
5.5 Concurrence of Subcontractors. Contractor, Contractor's Construction Scheduler, and
those major trade Subcontractors required by Design -Builder shall be required to
participate in all meetings necessary to reach mutual agreement and approval of the
Project Schedule.
6.0 Monthly Reports and Meetings
6.1 Contractor shall have a continuing obligation to regularly update the Project Schedule in
all respects during the entire term of this Agreement and shall devote sufficient resources
to ensure that it is able to perform all of its scheduling obligations.
6.2 On the 15th day of each month, the Contractor shall submit monthly updates to the Project
Schedule with each request by Contractor for payment under the Agreement which shall
be a condition precedent to Design -Builder's obligation to make any payment required
under the Agreement. All updated or revised schedules shall be submitted in the same
detail as the original submittal.
Capistrano Valley Water District Exhibit C — Project Schedule and Milestones Construction Agreement
San Juan Basin Desalter Project Page 6
4108281
Mss
412574.1
6.2.1 The update report shall show the activities or portions of activities complete during the
reporting period and their total value as the basis for Contractor's requests for payment.
The report shall state the percentage of the work actually complete as of the report date.
If the project is behind schedule, progress along other paths with negative float shall also
be reported.
6.2.2 At each regularly scheduled construction meeting, Contractor shall provide Design -
Builder with two-week look ahead schedules projecting the scheduled work activities to
be performed during the two week period following said construction meeting.
6.2.3 With each monthly update, and each revision, Contractor shall also submit a schedule of
cost loading and update to the Schedule of Values. There shall be a strict correlation
between the sum of individual activity costs and the Guaranteed Maximum Price,
including approved Change Orders.
6.3 Contractor shall revise the Project Schedule to reflect the progress of the Work. If any of
the required submissions are returned to the Contractor for corrections or revisions they
shall be resubmitted along with a new computer diskette(s) and a hard copy listing of
each change for approval within seven (7) days after receipt.
6.4 Contractor and Design -Builder shall meet no less than twice a month for the duration of
the Agreement to review the entire Project Schedule.
6.5 Update schedules prepared by the Contractor shall include all information available as of
the cutoff date. A detailed list of all proposed schedule changes (logic, duration, status,
additions, and deletions) shall be submitted with the update. Prior to the bi-monthly
update review meeting, Contractor shall obtain from its Subcontractors and staff all
necessary information as required to reflect progress to date. A proposed Monthly
Update Schedule containing the information set forth below shall be available for review
at the meeting.
6.6 The schedule update shall reflect, at a minimum, the following:
6.6.1 For activities started and/or completed during the previous period: actual start and actual
completion dates, and number of shifts used to accomplish the activity.
6.6.2 For activities begun but not yet complete to date: Remaining duration of the work,
estimated percent complete, and estimated completion date.
6.6.3 For activities not yet started: Estimated start dates, revised durations, and estimated
completion dates, as necessary.
Capistrano Valley Water District Exhibit C — Project Schedule and Milestones Construction Agreement
San Juan Basin Desalter Project Page 7
U082sa
A I fIR2R.?
412574.1
6.6.4 For authorized Change Orders: Revised activities, number of shifts, and crew sized by
craft, construction equipment required, and durations, and status of all outstanding
Notices of Non -Compliance, where required.
6.7 The monthly update of the Network Diagram shall be for the month preceding the
meeting and for the remainder of the project. The previous month's activities shall be
reported as they actually took place and designated as actually complete, if actually
completed, on the network diagram update.
6.8 Portions of the network diagram on which all activities are complete need not be
reprinted and submitted in subsequent updates. However, the electronic disk file of the
submitted Network Diagrams and the related reports shall constitute a clear record of
progress of the work form Notice to Proceed to final completion.
6.9 The monthly submittal shall be accompanied by a Schedule Narrative Report. The
Schedule Narrative Report shall describe the physical progress during the report period,
plans for continuing the work during the forthcoming report period, actions planned to
correct any negative float predictions, and explanation of the potential delays and/or
problems and their estimated impact on performance and the overall project completion
date. In addition, alternatives for possible schedule recovery to mitigate any potential
delay and/or cost increases shall be included for consideration by Design -Builder. The
report shall follow the outline set forth below:
• Transmittal Letter
• Description of problem areas
■ Current and anticipated delays
+ Cause of delays
■ Corrective action and schedule adjustments to correct delays
■ Impact of delays on other activities, milestones, and completion dates
■ Changes in construction sequences
• Pending items and status thereof
• Permits
+ Change Orders
■ Time extensions
+ Non -Compliance Notices
■ Contract completion date (s) status
• Ahead of schedule and number of working days
■ Behind schedule and number of working days
■ Other project or scheduling concerns
Capistrano Valley Water District Exhibit C — Project Schedule and Milestones Construction Agreement
San Juan Basin Desalter Project Page 8
4109381
�nszs�
412574.1
6.10 Predicated on the results of Design -Builder's review of monthly submissions of the
updated Project Schedule and accompanying reports, Contractor may be required to
revise the Project Schedule. Conditions under which a revision will be made are as
follows:
6.10.1 When a delay in the completion of any work item or sequence of work items results in an
indicated extension of the project completion or interim milestone dates detailed herein
by ten (10) working days or more.
6.10.2 When delays in submittals or deliveries or work stoppages are encountered which make
re -planning, rescheduling, or re -sequencing of the work necessary.
6.10.3 When the schedule does not represent the actual prosecution and progress of the Work.
6.11 Required revisions of the monthly update schedules are due within five (5) days of notice
by Design -Builder that a revision is required. All revisions and additions to the Project
Schedule are subject to acceptance by Design -Builder which shall not be unreasonably
withheld. When the Monthly Schedule Update or its required revision is approved by
Design -Builder, it then becomes the current Project Schedule. The current Project
Schedule will be used for the period from which it is approved until its successor is
submitted and approved.
6.12 Failure of the Contractor to submit schedule updates in a timely, accurate manner and in
accordance with the requirements of this Exhibit C will result in progress payments being
withheld until such time as the Contractor submits the required update requirements.
6.13 In accordance with the updating procedures, when an activity, is deemed substantially
complete by Design -Builder, then such activity will no longer be treated as an activity
affecting the critical path or successor activities on the project. The cost of correction of
any punchlist items associated with substantially completed activities will be covered by
withheld retention or other amounts deemed by Design -Builder to be adequate to cover
such costs.
7.0 Responsibility For Completion
7.1 Whenever it becomes apparent from the current monthly updated Project Schedule that
phasing, milestone, constraint, restrain, or Contract completion dates will not be met,
Contractor shall execute some or all of the following remedial actions:
7.1.1 Increase construction manpower in such quantities and crafts as necessary to eliminate
the backlog of work.
Capistrano Valley Water District Exhibit C — Project Schedule and Milestones Construction Agreement
San Juan Basin Desalter Project Page 9
Ueszs4
A � f�R2R.2
412574.1
7.1.2 Increase the number of work hours in conformance with Applicable Laws.
7.2 Prior to implementing any of the above actions, Contractor shall notify and obtain
approval from Design -Builder. If such actions are approved, the Project Schedule
revisions shall be incorporated by the Contractor into the Network Diagram before the
next update.
7.3 Under no circumstances will the addition of equipment or construction forces, increasing
the working hours or any other method, manner, or procedure to return to the
contractually required completion date be considered justification for a Change Order or
be treated as acceleration where the need for a recovery schedule has been caused by
Contractor and/or its Subcontractors.
7.4 Design -Builder may elect to withhold progress payments until the Contractor's progress
indicates that the milestone date(s) and/or the Contract completion date will be met.
8.0 Changes
Upon approval of any change to the Guaranteed Maximum Price or Contract Time(s), Contractor
shall incorporate such change in a proposed update to the current Construction Schedule,
including the Schedule of Values, and shall submit such proposed update for approval to Design -
Builder for approval in the same manner as Contractor's regular monthly updates.
9.0 As -Built Project Schedule
As a condition precedent to any release of retention, the last update to the Project Schedule
submitted shall be identified by the Contractor as the As Built Schedule. The As Built Schedule
shall reflect the exact manner in which the project was actually constructed (including start and
completion dates, activities, sequences, and logic) and shall be signed and certified by the
Contractor's Project Manager and Construction Scheduler as being a true reflection of the way in
which the project was actually constructed.
Capistrano Valley Water District Exhibit C — Project Schedule and Milestones Construction Agreement
San Juan Basin Desalter Project Page 10
410818.1
410x2.8,
412574.1
EXHIBIT D — INSURANCE REQUIREMENTS
1.0 Required Polices
Contractor shall obtain the following policies of insurance with the indicated coverages and
endorsements:
1.1 Workers Compensation Insurance as required by Applicable Laws.
1.2 Employer's Liability Insurance with limits of $1,000,000 per occurrence.
1.3 Commercial General Liability Insurance with contractual liability and products
completed operations coverage, with a combined single limit of liability of $1,000,000
per occurrence for bodily injury and for property damage, a general aggregate limit of
$2,000,000 (excluding products completed operations), an aggregate limit of $2,000,000
for products and completed operations, and a limit of $1,000,000 for personal injury and
advertising injury, $100,000 for fire damage, and a $10,000 medical expense for any one
person.
1.4 Excess Liability Insurance above the required commercial general, pollution (on a claims
made basis), commercial automobile and employer's liability insurance to result in an
overall liability coverage in the amount of $10,000,000 per occurrence and an annual
aggregate limit of $10,000,000.
1.5 Commercial Automobile Liability Insurance including owned, non -owned and leased or
hired vehicles, with a $1,000,000 combined single limit for bodily injury and property
damage, including non -owned and hired coverage.
1.6 Pollution Legal Liability Insurance with limits of $5,000,000 per loss and an annual
aggregate limit of $10,000,000.
1.7 Builder's Risk Insurance covering loss, damage, or destruction to the Project (including
boilers and machinery coverage) caused by physical damage in an amount equal to the
full replacement value of the Project.
2.0 Qualifications of Insurers
All insurers for the polices listed in Paragraph 1.0 shall be authorized to do business in the State
of California and shall have an A.M. Best Company rating of "A-" or better.
Capistrano Valley Water District
San Juan Basin Desalter Project
U08284
AI (IR2R 2
412574.1
Exhibit D — Insurance Requirements Construction Agreement
Page 1
3.0 Additional Insureds
All policies listed in Paragraph 1.0 except Workers Compensation Insurance shall list the
following as additional insureds: ECO Resources, Inc., Southwest Water Company, the
Capistrano Valley Water District and their respective officers, directors, officials, employees and
agents.
4.0 Subrogation Waivers
All policies listed in Paragraph 1.0 shall be considered primary to any insurance maintained by
the District. All policies shall include waivers of subrogation in favor of Design -Builder and its
insurers.
5.0 Occurrence Basis
All policies listed in Paragraph 1.0 shall be written on an occurrence basis.
6.0 Cancellation and Modification of Coverages
All policies listed in Paragraph 1.0 shall provide that thirty (30) days prior written notice to
Design -Builder must be provided before cancellation or modification of coverage provisions.
7.0 No Limitation of Liability
The coverages provided by policies of insurance listed in Paragraph 1.0 shall not be construed as
limitations of Contractor's liability to Design -Builder.
Capistrano Valley Water District
San Juan Basin Desalter Project
410828.1
4�sza.2
412574.1
Exhibit D — Insurance Requirements Construction Agreement
Page 2
EXHIBIT E - CONCEPTUAL DESIGN DRAWINGS
Capistrano Valley Water District
San Juan Basin Desalter Project
410828.1
4lNZ8-1
412574)
Exhibit E — Construction Documents Construction Agreement
Page 1
EXHIBIT F
TIME AND MATERIAL RATES, UNIT PRICES AND EQUIPMENT COSTS
Pursuant to Section 12.5.3 of this Agreement, if Design -Builder determines to
utilize time and material rates or, alternatively, unit prices to calculate an increase or decrease the
Guaranteed Maximum Price, the following time and material rates or alternatively unit prices,
small tools and equipment costs shall be utilized for said pricing:
Capistrano Valley Water District Exhibit G — Service Contract Construction Agreement
San Juan Basin Desalter Project Page 1
EXHIBIT G
SERVICE CONTRACT
Capistrano Valley Water District Exhibit G — Service Contract Construction Agreement
San Juan Basin Desalter Project Page 1
EXHIBIT H
CONTRACTOR'S PROPOSAL
4125741
Document comparison done by DeltaView on Wednesday, November 20, 2002
19.001.09
Input:
Document 1 Ipcdocs://mwdocs/410828/1
Document 2 cdocs://mwdocs/410828/2
Rendering set IStandard
Legend:
Insertion
ne
MOVCcl to
Format change
Inserted cell
Deleted cell
Moved cell
Split/Merged cell
Padding cell
Statistics:
Count
Insertions
77
Deletions
65
Moved from
1
Moved to
1
Format chan ed
0
Total changes
144
4125741