1980-0507_CROSBY COMPANY, T.J._H4_Agenda Report0 0
AGENDA ITEM May 7, 1980
TO: James S. Mocalis, City Manager
FROM: W. D. Murphy, Director of Public Works
SUBJECT: Award of Contract - Calle Aspero Street Improvements
SITUATION
On April 29, 1980, ten bids were received for the construction of
improvements to Calle Aspero. The top four are as follows:
Contractor Price
T. J. Crosby Company $58,998.30
Griffith Company 62,129.00
Porter Construction Company 62,551.50
Sully -Miller Contracting Company 67,060.66
FINANCIAL CONSIDERATIONS
The City has an agreement with Bear Brand Ranch Company (Tract
9030) where the City will pay S25,000, and Bear Brand Ranch
Company will pay the balance of the construction costs. There
is $25,000 allotted in the 1979-80 budget. Bear Brand Ranch
Company has deposited $16,000 toward construction of the project
The Engineers estimate for the project was $65,000.
ALTERNATE ACTIONS
1. Accept the low bid of $58,998.30 from T. J. Crosby Company.
2. Reject the bids.
3. Refer to staff for more information.
RECOMMENDATION
By motion, accept the bid of $58,998.30 from T. J. Crosby Company
for the construction of improvements to Calle Aspero and authorize
the Mayor to execute the contract on behalf of the City.
Respectfully submitted,
W. D. Plurphy
WDM:MG/rh