19-0115_SANCON ENGINEERING, INC_Technical Specifications (Conformed Set)
Annual Sewer Rehabilitation Program, CIP 18701 Technical Specifications Cover Sheet
City of San Juan Capistrano
TECHNICAL SPECIFICATIONS FOR THE
ANNUAL SEWER REHABILITATION PROGRAM, CIP 18701
Sewer Rehabilitation Program, CIP 18701
THIS PAGE IS LEFT INTENTIONALLY BLANK
SECTION 01025
MEASUREMENT AND PAYMENT
Sewer Rehabilitation Program - CIP 18701 Measurement and Payment
01025- 1
GENERAL
1.01 REQUIREMENTS PER GENERAL PROVISIONS
A. Monthly pay requests are due on a certain day of each month (to be established at the Pre-
Construction Meeting), and while pay requests will be accepted prior to this date, pay
request processing will not begin until this date. Failure of the Contractor to submit pay
requests by this day may be cause for delays in processing the pay request. Should the
submittal date fall on a holiday or weekend day during the month, then the Contractor shall
consider the next working day as the due date.
1.02 BID PROPOSAL
A. Measurement and payment shall be in accordance with the General Conditions and as
follows:
1. Unit Prices: Payment for a unit price bid item shall be based upon the amount
shown in the bid schedule multiplied by the total quantity measurement of the
installed item and shall be full compensation for furnishing all labor, transportation,
materials, equipment, tools and appurtenances required for construction of the item
complete in place in accordance with the Contract Documents.
2. Lump Sum Prices: The Contractor shall provide Lump Sum and Total Cost Prices in
the Bid Schedule for all Lump Sum work items of work in the Contract Documents.
Each Lump Sum price shall cover all costs and charges, including, without limitation,
the costs of material, labor, fabrication, delivery, installation or application,
transportation, fuel, supervision, overhead, profit, and taxes needed for a complete
and working installation as required by the Contract Documents. Lump Sum prices
provided to the City shall be held good and in effect until the work is completed and
accepted by City. Contractor proposed prices which are so unbalanced as to be
detrimental to the City’s interest, as determined by the City, may be rejected, or may
be cause for revision without revising the total bid amount, or may cause rejection of
the Bidder's entire bid, all at the sole discretion of the City.
3. Retention: Payment for all bid items is subject to the retention provisions of the
General Conditions.
1.03 MEASUREMENT AND PAYMENT
A. General: This article defines the manner and method to develop the bid amounts of all
items identified in the Bid Schedule. Bid amounts will include the costs of all labor,
equipment, tools, materials, fees, subcontractors, support services, safety requirements,
and any and all other items required to complete the work identified in the Contract
Documents unless specifically excluded by this section. Work required for which no
separate bid item is identified will be considered as a subsidiary obligation of the
City of San Juan Capistrano Measurement and Payment
Sewer Rehabilitation Program - CIP 17808 01025- 2
Contractor, and the cost therefore shall be borne solely by the Contractor and included in
the most applicable bid item.
B. Linear Measurements: Pipelines' and related facilities' measurements shall be made
horizontally and/or vertically along the centerline of the pipeline and related facilities
through tees, bends, valves, fittings, and as shown on the Approved Plans for its limits or as
otherwise specified in the Specifications.
C. Area Measurements: Measurement for bid items involving area units shall be based upon
the surface area measured in acres, square yards, square feet or as indicated in the bid
item.
D. Volume Measurements: Measurement for bid items involving volume units shall be based
upon the volume measured in cubic yards, tons or as indicated in the bid item.
E. Unit Measurements: Measurement for bid items involving units of the item shall be based
upon the number of units counted as indicated in the bid item.
F. Lump Sum Measurement: Measurement for a lump sum bid item shall be considered as a
complete project or a completed portion of a project constituting a unit. The items to be
included in the lump sum bid shall be as specified in the proposal bid item.
CONTRACT REQUIRED WORK - BID ITEMS
2.01 SEWER REHABILITATION PROGRAM - CIP 18701:
A. MOBILIZATION/DEMOBILIZATION (BID ITEM NO. 1)
1. Payment for mobilization and preparatory work will be made at the Contract lump
sum price bid therefore in the Bid Schedule, in accordance with the Contract
Documents. The Contract lump sum price shall include full compensation for
furnishing all labor, tools, equipment, materials and incidentals, and for doing all
work involved in mobilization and preparatory work, and for which payment is not
otherwise provided for under the Contract, and no additional compensation will be
made therefore.
2. The lump sum bid price shall include, but not be limited to, the cost of movement of
personnel, equipment, supplies and incidentals to the project site; for the
establishment of offices and temporary facilities and services at the project site; for
the securing of Insurances and City Business License, and for all permits (all
agencies) and compliance required for the work unless otherwise included under
other items of the bid schedule; for payment of premiums for bonds and insurance
for the project; for any and all necessary costs of acquisition of equipment, including
purchase and mobilization; for provision, environmental quality protection in
accordance with Appendix E and sub-section 3.9 of the General Requirements,
section 01 00 00 of these specifications, demobilization and any other work and
operations which must be performed or costs that must be incurred incident to the
initiation and completion of meaningful work at the site, all in conformance with the
Contract Documents.
City of San Juan Capistrano Measurement and Payment
Sewer Rehabilitation Program - CIP 17808 01025- 3
3. When other Contract items are adjusted, mobilization and preparatory work costs
will be deemed to have been recovered by the Contractor by the payments made for
the mobilization and preparatory work, and will be excluded from consideration in
determining compensation therefore. Progress payments for the mobilization and
preparatory work shall be subject to retainage as provided within the Contract
Documents.
B. ORANGE COUNTY FLOOD CONTROL DISTRICT (OCFCD) INSURANCE AND PERMIT
COMPLIANCE, COMPLETE (BID ITEM NO. 2)
1. Payment for OCFCD insurance and permit compliance will be made at the Contract
lump sum price bid therefore in the Bid Schedule, complete in place, in accordance
with the Contract Documents. The lump sum price for this work shall be per this bid
item and no additional compensation will be allowed. The Contract lump sum price
bid shall include full compensation for furnishing all labor, tools, equipment,
materials and incidentals, and for doing all work involved with providing insurance in
accordance with OCFCD requirements, and abiding by all permit conditions for all
work within OCFCD right of way, all for which payment is not otherwise provided for
under other items of the bid schedule, and no additional compensation will be made
therefore.
2. The Contract lump sum price shall include, but not be limited to the cost of obtaining
the necessary insurance and complying with all conditions of the permit, all in
conformance with the Contract Documents, complete in place and fully operational,
with no interruption in service.
C. SOUTHERN CALIFORNIA REGIONAL RAIL AUTHORITY (SCRRA) RIGHT OF ENTRY
AGREEMENT – APPLICATION AND FEES (BID ITEM NO. 3)
1. Payment for SCRRA Right of Entry Agreement will be made at the Contract lump sum price
bid therefore in the Bid Schedule, complete in place, in accordance with the Contract
Documents. The lump sum price for this work shall be per this bid item and no additional
compensation will be allowed. The Contract lump sum price bid shall include full
compensation for furnishing all labor, tools, equipment, materials and incidentals, and for
doing all work involved with constructing SCRRA Right of Entry Agreement, and for which
payment is not otherwise provided for under the Contract, and no additional compensation
will be made therefore.
2. The Contract lump sum price bid shall include, but not be limited to the cost of filling out
and submitting the application and paying all fees to secure and abide by the right of entry
agreement, including but not limited to plan review, administration, insurance, safety
training, flagging, protective services, and all other costs associated with the Right of Entry
Agreement all in conformance with the Contract Documents, complete in place and fully
operational with no interruption in service.
D. SHEETING, SHORING AND BRACING (BID ITEM NO. 4)
1. Payment for sheeting, shoring and bracing will be made at the Contract lump sum price bid
therefore in the Bid Schedule, complete in place, in accordance with the Contract
Documents. The lump sum price for this work shall be per this bid item and no additional
City of San Juan Capistrano Measurement and Payment
Sewer Rehabilitation Program - CIP 17808 01025- 4
compensation will be allowed. The Contract lump sum price bid shall include full
compensation for furnishing all labor, tools, equipment, materials and incidentals, and for
doing all work involved with constructing sheeting, shoring and bracing for which payment
is not otherwise provided for under the Contract, and no additional compensation will be
made therefore.
2. The Contract lump sum price bid shall include, but not be limited to the cost to furnish and
install sheeting, shoring and bracing as required by Cal-Osha to ensure safety of workers in
areas of excavation, all in conformance with the Contract Documents, complete in place and
fully operational.
E. TRAFFIC CONTROL, PUBLIC CONVENIENCE AND SAFETY (BID ITEM NO. 5)
1. Payment for Traffic Control, Public Convenience and Safety will be made at the
Contract lump sum price bid therefore in the Bid Schedule, complete in accordance
with the Contract Documents. The Contract lump sum price shall include full
compensation for furnishing all labor, tools, equipment, materials and incidentals
and for doing all work involved in providing Traffic Control, Public Convenience and
Safety as required and at multiple locations as dictated by the Contract Documents,
and no additional compensation will be allowed therefore.
2. The Contract lump sum price bid shall include, but not be limited to the cost of
implementing the measures specified in Section 7-10 of the Green Book, required
traffic and pedestrian control, and safety orders as defined in the City of San Juan
Capistrano Encroachment Permit Conditions, Manual of Uniform Traffic Control
Devices, and in accordance with all Cal Osha requirements, federal state and local
regulations, in order to allow for safe performance of the work described in these
Contract Documents. Work in the California State Department of transportation
(Caltrans) right of way is also subject to Caltrans Permit conditions.
F. POTHOLING (BID ITEM NO. 6)
1. Payment for potholing will be made at the Contract unit price bid therefore in the Bid
Schedule, complete in place, in accordance with the Contract Documents. The unit
price for this work shall be per this bid item and no additional compensation will be
allowed. The Contract unit price bid shall include full compensation for furnishing all
labor, tools, equipment, materials and incidentals, and for doing all work involved
with potholing, and for which payment is not otherwise provided for under the
Contract, and no additional compensation will be made therefore.
2. The Contract unit price bid shall include, but not be limited to the cost to furnish all
materials and labor to pothole locate all utilities in the project area that are incidental
to the work or are in conflict with the alignments shown on the Construction
Drawings, furnishing the City with a pothole report that lists at a minimum the
location, type, depth, diameter and material of the utility being protected in place,
backfill, compaction and surface restoration, complete in place and in conformance
with the Contract Documents.
G. DIG AND REPLACE 6” AND 8” SEWER LINE, DEPTH ≤ 10 FEET (BID ITEM NO. 7)
City of San Juan Capistrano Measurement and Payment
Sewer Rehabilitation Program - CIP 17808 01025- 5
1. Payment for dig and replace 6” and 8” sewer line, depth less than or equal to ten
feet will be made at the Contract unit price bid therefore in the Bid Schedule,
complete in place, in accordance with the Contract Documents. The unit price for
this work shall be per this bid item and no additional compensation will be allowed.
The Contract unit price bid shall include full compensation for furnishing all labor,
tools, equipment, materials and incidentals, and for doing all work involved with this
dig and replace item, and for which payment is not otherwise provided for under
other items of the bid schedule, and no additional compensation will be made
therefore.
2. The Contract unit price bid shall include, but not be limited to the cost to furnish all
materials and labor to dig and replace 6” and 8” sewer line, depth less than or equal
to 10 feet, including but not limited to sawcut and remove pavement, excavation to
expose sewer line, bypass pumping to dewater the line, cut and remove
compromised portion of pipeline and dispose of all waste material in accordance
with all federal, state and local regulations, furnish and install replacement pipeline
of equal diameter with band couplings as indicated on the detail in appendix A,
bedding, backfill and compaction, and pavement replacement per City standard 700,
complete in place and fully operational in conformance with the Contract
Documents.
H. DIG AND REPLACE 6” AND 8” SEWER LINE, DEPTH > 10 FEET (BID ITEM NO. 8)
1. Payment for dig and replace 6” and 8” sewer line, depth greater than ten feet will be
made at the Contract unit price bid therefore in the Bid Schedule, complete in place,
in accordance with the Contract Documents. The unit price for this work shall be per
this bid item and no additional compensation will be allowed. The Contract unit price
bid shall include full compensation for furnishing all labor, tools, equipment,
materials and incidentals, and for doing all work involved with this dig and replace
item, and for which payment is not otherwise provided for under other items of the
bid schedule, and no additional compensation will be made therefore.
2. The Contract unit price bid shall include, but not be limited to the cost to furnish all
materials and labor to dig and replace 6” and 8” sewer line, depth greater than 10
feet, including but not limited to saw-cut and remove pavement, excavation to
expose sewer line, bypass pumping to dewater the line, cut and remove
compromised portion of pipeline and dispose of all waste material in accordance
with all federal, state and local regulations, furnish and install replacement pipeline
of equal diameter with band couplings as indicated on the detail in appendix A,
bedding, backfill and compaction, and pavement replacement per City standard 700,
complete in place and fully operational in conformance with the Contract
Documents.
I. TEMPORARY SEWER BYPASS 6” & 8” (BID ITEM NO.’S 9 AND 11)
1. Payment for Temporary Sewer Bypass will be made at the Contract lump sum price
bid (separate price for each pipe size and respective bid item numbers listed above)
therefore in the Bid Schedule, complete and in accordance with the Contract
Documents. The Contract lump sum price shall include full compensation for
furnishing all labor, power, tools, equipment, materials, appurtenances and
City of San Juan Capistrano Measurement and Payment
Sewer Rehabilitation Program - CIP 17808 01025- 6
incidentals and for doing all work involved in providing temporary sewer bypass
facilities of each size, and no additional compensation will be allowed therefore.
2. The Contract lump sum price shall include, but not be limited to the cost of providing
all required equipment such as pumps, generators, piping, valving, site cleanup and
restoration, all in conformance with the Contract Documents, complete in place and
fully operational,
J. CURED IN PLACE PIPE 6”, 8”, 15”, 18” (BID ITEM NO.’S 10, 12, 13, 14 & 15)
1. Payment for Cured-In-Place-Pipe, Diameter as indicated in the bid schedule, will be
made at the Contract unit price bid (separate price for each pipe size and respective
bid item number listed above) therefore in the Bid Schedule, complete in
accordance with the Contract Documents. The unit price for this work shall be per
the corresponding bid item and no additional compensation will be allowed. The
Contract unit price bid for each item shall include full compensation for furnishing all
labor, tools, equipment, materials and incidentals, and for doing all work involved
with constructing cured-in-place-pipe of each size, and no additional compensation
will be made for the bid items listed therefore.
2. The Contract unit price bid shall include, but not be limited to the cost of pre-bid
verification of diameter and linear length, pre-installation inspection video, sewer
cleaning, removal and disposal of material not otherwise covered under item K
below, to provide an unimpeded flow diameter and thereby make way for the cured
in place pipe, installation and curing of liner, trimming, sealing and finishing manhole
connection, reestablishing laterals and post-construction video, cost for temporary
sewer bypass for 15 inch short liner if necessary, all in conformance with industry
standard practices and the Contract Documents, complete in place and fully
operational with no interruption in service.
K. CUT AND REMOVE PROTRUDING LATERALS, HANGING GASKETS, ROOT BALLS
AND OTHER OBSTRUCTIONS (BID ITEM NO. 16)
1. Payment for removal of protruding laterals, hanging gaskets and other obstructions
to make way for installation of Cured in Place Pipe will be made at the unit price
indicated in the Bid Schedule, complete in accordance with the Contract
Documents. The unit price for this work shall be per the corresponding bid item and
no additional compensation will be allowed. The Contract unit price bid for each
item shall include full compensation for furnishing all labor, tools, equipment,
materials and incidentals, and for doing all work involved with removal and disposal
of protruding laterals, hanging gaskets, root balls and other obstructions to make
way for installation of cured in place pipe, and no additional compensation will be
made therefore.
2. The Contract unit price bid shall include, but not be limited to the cost of removing
protruding laterals, hanging gaskets, root balls and other obstructions, with robotic
cutting and grinding tools, or by other means, in which case the bid item includes
the cost of adherence to confined space entry program in accordance with
Greenbook Section 7-10.4.4 and all Cal Osha requirements, all in conformance with
City of San Juan Capistrano Measurement and Payment
Sewer Rehabilitation Program - CIP 17808 01025- 7
industry standard practices and the Contract Documents, complete in place and fully
operational with no interruption in service.
L. MANHOLE REHABILITATION WITH PRESSURE GROUTING (BID ITEM NO. 17)
1. Payment for Manhole Rehabilitation with pressure grouting will be made at the
Contract unit price bid therefore in the Bid Schedule, complete in place, in
accordance with the Contract Documents. The unit price for this work shall be per
this bid item and no additional compensation will be allowed. The Contract unit
price bid shall include full compensation for furnishing all labor, tools, equipment,
materials and incidentals, and for doing all work involved with constructing Manhole
Rehabilitation with pressure grouting, and for which payment is not otherwise
provided for under the Contract, and no additional compensation will be made
therefore.
2. The Contract unit price bid shall include, but not be limited to the cost of manhole
cleaning, remove corroded metal access steps and grind flush with manhole wall,
reconstruction of manhole bench and channels, root removal, crack and infiltration
repair, pressure grouting of all manholes with root intrusion and evidence of
infiltration, surface preparation and spray application of calcium aluminate mortar
seal in accordance with the manufacturer’s instructions, all in conformance with the
Contract Documents, complete in place and fully operational with no interruption in
service.
M. MANHOLE REHABILITATION WITHOUT PRESSURE GROUTING (BID ITEM 18)
1. Payment for Manhole Rehabilitation without pressure grouting will be made at the
Contract unit price bid therefore in the Bid Schedule, complete in place, in
accordance with the Contract Documents. The unit price for this work shall be per
this bid item and no additional compensation will be allowed. The Contract unit
price bid shall include full compensation for furnishing all labor, tools, equipment,
materials and incidentals, and for doing all work involved with constructing Manhole
Rehabilitation without pressure grouting, and for which payment is not otherwise
provided for under the Contract, and no additional compensation will be made
therefore.
2. The Contract unit price bid shall include, but not be limited to the cost of manhole
cleaning, remove corroded metal access steps and grind flush with manhole wall,
reconstruction of manhole bench and channels, root removal, crack and infiltration
repair, surface preparation and spray application of calcium aluminate mortar seal in
accordance with the manufacturer’s instructions, all in conformance with the
Contract Documents, complete in place and fully operational with no interruption in
service.
N. MANHOLE FRAME AND COVER (BID ITEM NO. 19)
1. Payment for manhole frame and cover will be made at the Contract unit price bid
therefore in the Bid Schedule, complete in place, in accordance with the Contract
Documents. The unit price for this work shall be per this bid item and no additional
compensation will be allowed. The Contract unit price bid shall include full
City of San Juan Capistrano Measurement and Payment
Sewer Rehabilitation Program - CIP 17808 01025- 8
compensation for furnishing all labor, tools, equipment, materials and incidentals,
and for doing all work involved with constructing manhole frame and cover, and for
which payment is not otherwise provided for under the Contract, and no additional
compensation will be made therefore.
2. The Contract unit price bid shall include, but not be limited to the cost of preparing
the manhole, furnish and install the new manhole frame and cover in accordance
with City of San Juan Capistrano standard plan no. 807, haul and dispose of old
manhole frame and cover at an approved facility in accordance with all federal state
and local regulations, all in conformance with the Contract Documents, complete in
place and fully operational with no interruption in service.
O. SERVICE LATERAL CONNECTION REPAIR - TOP HAT STYLE (BID ITEM NO. 20)
1. Payment for Service Lateral Connection Repair - Top Hat Style will be made at the
Contract unit price bid therefore in the Bid Schedule, complete in place, in
accordance with the Contract Documents. The unit price for this work shall be per
this bid item and no additional compensation will be allowed. The Contract unit
price bid shall include full compensation for furnishing all labor, tools, equipment,
materials and incidentals, and for doing all work involved with Top Hat Style Lateral
Repair in accordance with the Contract Documents, and no additional compensation
will be made therefore.
2. The Contract unit price bid shall include, but not be limited to the cost of pre-bid
verification of diameter and linear length, pre-installation video, sewer cleaning,
removal of roots and obstructions to allow for proper installation of top hat liner,
installation and curing of liner, trimming and finishing, post-construction video, and
all associated work to provide a neat and fully functional top hat style lateral repair
and connection in accordance with industry standard practices and in accordance
with the Contract Documents, complete in place and fully operational with no
interruption in service.
P. RAISE MANHOLE (BID ITEM NO. 21)
1. Payment for raise manhole will be made at the contract unit price bid therefore in
the Bid Schedule, complete in accordance with the Contract Documents. The
Contract unit price shall include full compensation for furnishing all labor, tools,
equipment, materials, appurtenances and incidentals and for doing all work involved
in raising manholes to grade, and no additional compensation will be made
therefore.
2. The Contract unit price shall include, but not be limited to the cost of excavation to
expose existing top of manhole, remove existing frame and cover and salvage to
City staff, clean and prep existing manhole top section, furnish and install concrete
riser, cone and grade ring, seal all joints, furnish and install new frame and cover
with grout seal, backfill and compact per City standards and in accordance with the
raise manhole detail in appendix A, complete in place and fully operational.
City of San Juan Capistrano Measurement and Payment
Sewer Rehabilitation Program - CIP 17808 01025- 9
Q. RAISE CLEANOUT (BID ITEM NO. 22)
1. Payment for raise cleanout will be made at the contract unit price bid therefore in the
Bid Schedule, complete in accordance with the Contract Documents. The Contract
unit price shall include full compensation for furnishing all labor, tools, equipment,
materials, appurtenances and incidentals and for doing all work involved in raising
cleanout to grade, and no additional compensation will be made therefore.
2. The Contract unit price shall include, but not be limited to the cost of excavation to
expose existing top of cleanout, remove existing frame and cover and salvage to
City staff, clean and prep existing cleanout top section, furnish and install pipe riser
to match existing diameter and solvent weld coupling to grade, furnish and install
new frame and cover backfill and compact per the raise cleanout detail in Appendix
A, and in accordance with the Contract Documents, complete in place and fully
operational.
EXECUTION
3.01 GENERAL PROGRESS PAYMENT REQUIREMENTS
A. The City Representative will verify measurements and quantities. Each activity necessary to
manage and complete the work is identified on the contract schedule. Each activity will be
assigned its respective value, a portion of the contract price, as shown on the Schedule of
Values.
B. Payment for all lump sum costs and services incurred on this Contract shall be based on
the earned value of work accomplished during the reporting period. Earned value is
determined by the completion percentage of each activity applied to the total value of the
activity. No construction activity shall be deemed 100% complete until the Contractor has
completed the physical check out and inspection of the completed work and has submitted
the signed inspection form to the City Representative.
C. The Contractor shall not take advantage of any apparent error or omission on the Drawings
of Specifications, and the City Representative shall be permitted to make corrections and
interpretations as may be deemed necessary for fulfillment of the intent of the Contract
Documents at no additional cost to the City.
D. One legible copy of the application for payment shall be submitted. Application shall be
made monthly.
E. The Application for Payment shall contain all necessary references and attachments that
substantiate the invoice for progress payment; including, but not limited to the following:
Summary of Earned Value on a percent complete basis, as confirmed by both the City
inspector and the project manager.
F. The Application for Payment is submitted according to the format and instructions provided
by the City and is based on work completed through the last day of the previous month or
through the date established by the City Representative.
END OF SECTION 01025
Sewer Rehabilitation Program, CIP 18701
THIS PAGE IS LEFT INTENTIONALLY BLANK
Sewer Rehabilitation Program, CIP 18701 13500 - 1
CURED-IN-PLACE-PIPE
SECTION 13500 – CURED-IN-PLACE-PIPE (CIPP)
PART 1 - GENERAL
1.1 INTENT
A. It is the intent of this specification to provide for the rehabilitation of sewers by
the installation of a resin-impregnated flexible liner, which is inserted using an
inversion process to fit tightly against the original host pipe. The resin is cured
using hot water, steam or ultraviolet light (UV). The cured-in-place-pipe (CIPP)
will be continuous and tight fitting.
B. Contractor shall provide materials, labor, equipment, and services necessary for
pre-installation cleaning, rehabilitation of existing sewer pipes by lining,
reinstatement of lateral connections, initial and final closed circuit television
inspection, and final testing of the CIPP system.
1.2 RELATED DOCUMENTS
A. This specification references standards from the American Society for Testing
and Materials, such as:
1. ASTM F1216 (Rehabilitation of Existing Pipelines and Conduits by the
Inversion and Curing of a Resin-Impregnated Liner);
2. ASTM F1743 (Rehabilitation of Existing Pipelines and Conduits by Pulled-
in-Place Installation of Cured-in-Place Thermosetting Resin Pipe (CIPP));
3. ASTM D5813 (Cured-in-Place Thermosetting Resin Sewer Pipe);
4. ASTM D790 (Test Methods for Flexural Properties of Un-reinforced and
Reinforced Plastics and Electrical Insulating Materials); and
5. D2990 (Tensile, Compressive, and Flexural Creep and Creep-Rupture of
Plastics).
1.3 SUBMITTALS – As a minimum, Contractor shall submit the following for review:
A. Liner, resin, sealant fittings, adapters and specials.
B. The standard dimension ratio is the ratio of the outside diameter of the pipe to
its minimum wall thickness. All CIPP wall thicknesses calculated by a
Sewer Rehabilitation Program, CIP 18701 13500 - 2
CURED-IN-PLACE-PIPE
professional engineer registered in the state of California, SDR’s by diameter,
and depth ranges corresponding to this specification, shall be submitted to the
engineer for approval prior to installation.
C. Critical Damage Reports as described in this specification, if applicable.
D. The contractor shall submit to the City at least 24 hours prior to installation, a
“wet out” schedule detailing time and location.
E. The manufacturer, prior to installation, shall provide the inversion pressures
necessary for proper installation. Installation forces shall be limited so the liner
is not stretched longitudinally by more than 5% of the original length.
F. Before installation begins, the tube manufacturer shall provide the minimum
pressures required to hold the tube tight against the existing host pipe, and the
maximum allowed pressure that will not damage the tube.
G. Acceptance testing samples as described in section 2.4.
H. Copy of the Southern California Regional Rail Authority right of entry permit for
work within the railroad right of way shall be submitted to the City prior to
commencing work.
I. Pre and Post Construction CCTV videos.
J. Certificates and Affidavits (to be furnished prior to shipment)
1. Affidavit of compliance with applicable standards for resins and liner
materials.
2. Certification that Contractor is a licensed installer of any patented process.
1.4 PRODUCT, MANUFACTURER AND INSTALLER QUALIFICATION
REQUIREMENTS
A. The sewer repairs specified herein are intended to have a 50-year design life. In
order to minimize the Owner’s risk, only proven products with substantial
successful long-term track records will be approved. All trenchless rehabilitation
products and installers must meet the minimum requirements of these
specifications.
B. Products and Installers seeking approval must meet all of the following criteria
to be deemed Commercially Acceptable:
1. For a Product Manufacturer to be considered Commercially Proven, a
minimum of 1,000,000 linear feet or 4,000 manhole-to-manhole line
sections of successful wastewater collection system installations in the
U.S. must be documented to the satisfaction of the Owner to assure
commercial viability. Acceptable documentation indicating that this
Sewer Rehabilitation Program, CIP 18701 13500 - 3
CURED-IN-PLACE-PIPE
requirement has been satisfied must be submitted to the Engineer for
review.
2. For an Installer to be considered as Commercially Proven, the Installer
must have had at least 5 (five) years active continuous experience in the
commercial installation of cured-in-place-pipe. In addition, the Installer
must have successfully installed at least 50,000 feet of the CIPP in
wastewater collection systems. Acceptable documentation indicating that
this requirement has been satisfied must be submitted to the Engineer for
review.
3. Sewer rehabilitation products submitted for approval must provide third
party test results supporting the structural performance (short-term and
long-term) of the product and such data shall be satisfactory to the City.
Test samples shall be prepared so as to simulate installation methods and
trauma of the product. Products without independent third party testing
verification are not acceptable. Acceptable documentation indicating that
this requirement has been satisfied must be submitted to the City for
review.
4. Both the rehabilitation manufacturing and installation processes shall
operate under a quality management system which is third-party certified
to ISO 9000 or other recognized organization standards. Proof of
certification shall be required for approval. Acceptable documentation
indicating that this requirement has been satisfied must be submitted to
the Engineer for review.
1.5 BIDDER’S INSPECTION – Bidder shall examine CCTV video files of sewers
provided by the City on a web based account and become familiar with the
existing sewer and site conditions prior to submitting a bid. Location of the web
based account will be provided by the City during the bidding phase of the
project.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Liner - The sewn liner shall consist of one or more layers of absorbent non-
woven felt fabric and meet the requirements of ASTM F1216, Section 5.1 or
ASTM F1743, Section 5.2.1 The liner shall be constructed to withstand
installation pressures, have sufficient strength to bridge missing pipe, and
stretch to fit irregular pipe sections.
1. The wet out liner shall have a relatively uniform thickness that when
compressed at installation pressures will equal or exceed the calculated
minimum design thickness.
Sewer Rehabilitation Program, CIP 18701 13500 - 4
CURED-IN-PLACE-PIPE
2. The liner shall be manufactured to a size that when installed will tightly fit
the internal circumference and length of the original pipe. Allowance
should be made for circumferential stretching during inversion.
Overlapped layers of felt in longitudinal seams that cause lumps in the
final product shall not be utilized.
3. The outside layer of the liner shall be coated with an impermeable, flexible
membrane that will contain the resin and all the resin impregnation (wet
out) procedure to be monitored.
4. The liner shall be homogeneous across the entire wall thickness
containing no intermediate or encapsulated elastomeric layers. No
material shall be included in the liner that may cause delamination in the
cured CIPP. No dry or unsaturated layers shall be evident.
5. The wall color of the interior pipe surface of CIPP after installation shall be
a relatively light reflective color so that a clear detailed examination with
closed circuit television inspection equipment may be made.
6. Seams in the liner shall be stronger than the non-seamed felt material.
7. The liner shall be marked for distance at regular intervals along its entire
length, not to exceed 5 ft. Such markings shall include the manufacturers
name or identifying symbol.
B. Resin - The resin system shall be a corrosion resistant polyester, vinyl ester, or
epoxy system including all required catalysts, initiators or hardeners that when
cured within the liner create a composite that satisfies the requirements of
ASTM F1216 and ASTM F1743, the physical properties herein, and those
which are to be utilized in the design of the CIPP for this project. The resin
shall produce a CIPP that will comply with the structural and chemical
resistance requirements of this specification.
2.2 STRUCTURAL REQUIREMENTS
A. The CIPP shall be designed per ASTM F1216, Appendix X.1. The CIPP
design shall be based on the assumption that no bonding to the original
pipe wall occurs.
B. The layers of the cured CIPP shall be uniformly bonded. It shall not be possible
to separate any two layers with a probe or point of a knife blade so that the
layers separate cleanly or the probe or knife blade moves freely between the
layers. If the layers separate during field sample testing, new samples will be
required to be obtained from the installed pipe. Any reoccurrence will serve as
grounds for rejection of the work.
C. The cured in place pipe material (CIPP) shall conform to the structural
properties, as listed below.
Sewer Rehabilitation Program, CIP 18701 13500 - 5
CURED-IN-PLACE-PIPE
Material Strength Standards
Property Test Method Low Modulus High Modulus
Modulus of
Elasticity
ASTM D790 300,000 PSI 400,000 PSI
Flexural Strength ASTM D790 5,500 PSI
Tensile Strength ASTM D638 3,000-5,000 PSI
Tensile Load
Capacity per
layer
ASTM D638 775 lbs/inch
D. The required structural CIPP wall thickness shall be based as a minimum, on
the physical properties identified above and in accordance with the design
considerations and equations in ASTM F1216 and its Appendix X1, and the
following design parameters:
1. Design Life = 50 years
2. Minimum Design Safety Factor = 2.0
3. Retention Factor for Long-Term Flexural Modulus = 50%
4. Ovality (calculated per ASTM F1216 X1.1) = 2%
5. Enhancement Factor, K = 7
6. The CIPP is subject to a groundwater elevation 5 feet below the ground
surface.
7. Soil Depth (above crown of existing pipe) per table in sec 013500, part
1.1.B
8. Soil Modulus = 1,000-psi
9. Soil Density = 120-pcf
10. Highway Live Load = AASHTO HS20-44
11. Design Condition = fully deteriorated, no existing pipe strength.
12. Minimum thickness shall be per the table in section 2.3 below
13. If calculations require thicker wall, round to next higher multiple of 0.5mm
E. Layers of the liner that are not saturated with resin prior to insertion into the
existing pipe shall not be included in the required design structural CIPP wall
thickness.
Sewer Rehabilitation Program, CIP 18701 13500 - 6
CURED-IN-PLACE-PIPE
2.3 LINING DESIGN – The minimum CIPP liner thickness for the various sewer
diameters shall be no less than indicated below.
Minimum CIPP Thickness
Nominal
Sewer Diam-
eter (inches)
Pipe Invert Depth
Up to 10 feet
(mm)
10 – 15 feet
(mm)
15 – 20 feet
(mm)
20-25 feet
(mm)
6 4.5 4.5 4.5 6.0
8 6.0 6.0 6.0 7.5
10 6.0 7.5 7.5 9.0
12 7.5 7.5 9.0 10.5
15 9.0 10.5 12.0 12.0
18 10.5 12.0 13.5 15.0
21 12.0 13.5 16.5 18.0
36 19..5 24.0 27.0 30.0
These values represent the minimum thickness for the installed CIPP after curing has
been completed based on the following design assumptions:
1. The existing sewer is considered fully deteriorated.
2. The existing sewer is considered to have an ovality of 2 percent in circum-
ference.
3. The CIPP is subjected to a full soil load of 120 pounds per cubic foot.
4. The CIPP is subjected to traffic line loads as calculated by AASHTO
Standard Specifications for Highway Bridges, HS-20-44 Highway Loading.
5. The modulus of soil reaction for pipe zone backfill material is 700 psi.
6. The CIPP is subject to a groundwater elevation 5 feet below the ground
surface.
7. The CIPP Flexural Strength shall be 4,500 psi (ASTM D-790).
8. The CIPP Short term flexural Modulus of Elasticity shall be 250,000 psi
(ASTM D-790).
2.4 TESTING REQUIREMENTS
A. Gravity pipe leakage testing – For 24 inch diameter or less, CIPP low pressure
air test per City of San Juan Capistrano (CSJC) standard specification section I-
08 shall be required after liner has been installed in existing pipe. For pipe
diameters greater than 24 inches, follow the infiltration testing requirements of
CSJC standard specification section I-08.
B. CIPP properties test – One minimum 12 inch long restrained pipe section shall
be cut from the cured liner of each segment and labeled with upstream and
downstream manholes numbers for that section. Contractor shall submit the
sample to the City with thickness measurements taken and witnessed by the
Sewer Rehabilitation Program, CIP 18701 13500 - 7
CURED-IN-PLACE-PIPE
City inspector, from four locations on each test section. The average thickness
of the measurements shall be equal to or greater than the required minimum or
design thickness (whichever is greater). In addition, Contractor shall collect the
coupons from the service line connection restorations for each setup tested,
label with upstream and downstream manhole numbers, and submit to the City.
These coupons will be used for testing liner thickness. Failure of the thickness
test shall be grounds for rejection of the CIPP liner.
C. Resin properties test – “Wet-out” facility resin mixing equipment shall have a
valve downstream of the mixing functions and immediately upstream of the
application of the mixed resin to the tube where the City can draw resin
samples. Sampling and testing of the mixed batch shall be conducted by a
laboratory approved by the City. Submitted “wet-out” schedule cannot be
modified without 24 hour notice to the City. The City representative drawing the
samples will arrive unannounced and shall be afforded immediate access to the
equipment.
D. CCTV Visual Test – The Contractor shall inspect each installation visually by
CCTV. Variations from true line and grade may be inherent because of
conditions of the original piping. No infiltration of groundwater shall be
observed. All lateral entrances shall be accounted for and be fully functional.
No visible leak around liner at manhole connections will be allowed. The pre
and post installation video data shall be submitted to and will become the
property of the City.
E. Contractor shall correct liner that has failed any of the above tests. Remedy for
failed thickness test shall be defined as shown in the following table. Where
liner removal and replacement is required, it shall be for the entire segment
length from manhole to manhole. No additional payment shall be made for
removal and replacement of faulty liners.
Pipe Correction
Test Required
Value
Test Result Remedy
Thickness, (T)
Minimum or
Design,
whichever is
greater
>=90% to 100% No unit price reduction
90% > T >=80% 15% Unit Price Reduction
< 80% Liner Replacement
2.5 DELIVERY AND STORAGE – Delivery and storage of lining and other materials
shall conform to the published requirements of the manufacturer. Contractor is
responsible to furnish required storage facilities. Handle lining materials in
Sewer Rehabilitation Program, CIP 18701 13500 - 8
CURED-IN-PLACE-PIPE
compliance with manufacture’s published recommendations. Damaged
material will be unacceptable for installation.
PART 3 - EXECUTION
3.1 INSTALLATION RESPONSIBILITIES FOR INCIDENTAL ITEMS
A. It shall be the responsibility of Contractor to locate and verify the designated
manholes are adequately accessible for the work. Where traffic control is
required, it shall be the responsibility of Contractor to prepare traffic control
plans for the City’s review and implement the traffic control devices as approved
by the City. Owner shall also provide access to water hydrants for cleaning,
installation and other process related work items requiring water at no charge.
Contractor shall procure construction meter from the City for placement on
hydrant prior to collecting water for cleaning.
B. Cleaning of Sewer Lines – Before lining each segment of sewer pipe,
Contractor shall remove all internal debris from the sewer line that could
interfere with proper installation of the CIPP. It shall be Contractor’s
responsibility remove and legally dispose of debris removed from the sewers
during the cleaning operation.
C. The contractor shall be solely responsible for preventing service line back-ups
during construction.
D. Bypassing Sewage – Contractor shall provide for the flow of sewage around the
section or sections of pipe designated for repair. Plugging the line at an existing
upstream manhole and pumping the flow into a downstream manhole or
adjacent system shall be considered an acceptable bypass. The pump(s) and
bypass line(s) shall be of adequate capacity to accommodate the sewage flow.
The Contractor shall also provide a functional back-up pump of adequate
capacity, and a reliable back up power supply. Contractor shall submit a detail
of the bypass plan for Engineer’s review prior to starting work on any segment.
E. Inspection of Pipelines - Inspection of pipelines shall be performed by
experienced, NASSCO PACP certified personnel trained in locating breaks,
obstacles and service connections using close circuit television (CCTV)
inspection techniques. The pipeline interior shall be carefully inspected to
determine the location of any conditions that may prevent proper installation of
CIPP. These locations shall be noted and corrected. A videotape and suitable
written log for each line section shall be produced and submitted to Engineer for
review.
F. Line Obstructions - It shall be the responsibility of the Contractor to clear the
line of obstructions (at no additional cost to the City) such as solids, roots and
Sewer Rehabilitation Program, CIP 18701 13500 - 9
CURED-IN-PLACE-PIPE
protruding gaskets, which will prevent or hinder the insertion of CIPP. If pre-
installation inspection reveals an obstruction such as a protruding service
connection, dropped joint, or a collapse, that cannot be repaired with
conventional sewer cleaning equipment, the Contractor shall notify the City
immediately. This should be submitted to the City as a Critical Damage Report
(CDR). The CDR shall include all adverse conditions from manhole to manhole
for the pipe segment in question. The pre-inspection video and report of the
deficient segment shall be submitted to the City, along with recommendation
from CIPP Contractor for each adverse condition. After reviewing this
information, the City will direct the Contractor on how to proceed
G. Public Notification - Contractor shall make every effort to maintain sewer
service usage throughout the duration of the project. In the event that a
connection will be out of service, the longest period of no service shall be 4
hours. A public notification program shall be implemented, and shall as a
minimum, require Contractor to be responsible for contacting each home or
business connected to the sanitary sewer and informing them of the work to be
conducted, and when the sewer will be off-line. Contractor shall also provide
written notice to be delivered to each home or business 24-hours prior to the
beginning of work being conducted on the section, and a local telephone
number of the Contractor they can call to discuss the project or any potential
concerns.
H. The Contractor shall be responsible for confirming the locations of all branch
service connections prior to installing the CIPP.
3.2 INSTALLATION
A. CIPP installation shall be in accordance with ASTM F1216, Section 7, or ASTM
F1743, Section 6, with the following modifications:
1. Resin Impregnation - The quantity of resin used for liner impregnation
shall be sufficient to fill the volume of air voids in the liner with additional
allowances for polymerization shrinkage and the loss of resin during
installation through cracks and irregularities in the original pipe wall.
2. If a vacuum impregnation process is used, the point of vacuum shall be no
further than 25-feet from the point of initial resin introduction. After vacuum
in the liner is established, a vacuum point shall be no further than 75-feet
from the leading edge of the resin. The leading edge of the resin slug shall
be as near to perpendicular to the longitudinal axis of the liner as possible.
A roller system shall be used to uniformly distribute the resin throughout
the liner. If the Installer uses an alternate method of resin impregnation,
the method must produce the equivalent results. Any alternate resin
Sewer Rehabilitation Program, CIP 18701 13500 - 10
CURED-IN-PLACE-PIPE
impregnation method must be documented to the Owner’s satisfaction that
the saturation of the CIPP is sufficient.
3. Delivery, storage and handling of approved materials are the responsibility
of the Contractor. The Contractor shall keep them safe from damage and
stored with the proper environmental containment as outlined by the
manufacturer. No products should be used that have exceeded the
designated shelf life as outlined by the manufacturer. Remove damaged
products from site. Promptly replace damaged products with new
products at no additional cost to the City.
4. Maintain resin impregnated tubes in refrigerated truck trailers at a
temperature below 45 degrees F to prevent premature curing. Prior to
beginning inversion, no portion of the resin impregnated tubes liner shall
be subjected to sunlight or ultraviolet radiation. Resin impregnated tubes
with signs of premature curing shall not be installed and shall be removed
from the project site.
5. Liner Insertion – The wet out liner shall be positioned in the pipeline using
either inversion or a pull-in method. If pulled into place, a power winch
should be utilized and care should be exercised not to damage the liner as
a result of pull-in friction. The liner should be pulled-in or inverted through
an existing manhole or approved access point and fully extend to the next
designated manhole or termination point.
6. Temperature gauges shall be placed between the liner and the host pipe’s
invert position to monitor the temperatures during the cure cycle.
7. Lubricant shall be used to reduce friction between the host pipe and the
liner during the inversion or pulled in process. The lubricant shall be
poured into the water in the down-tube or applied directly to the tube or
inflation bladder. The lubricant used shall be a non-toxic, oil based
product that has no detrimental effects on the tube, heating source and
pump system, will not support the growth of bacteria, and will not
adversely affect the fluid to be transported.
8. Curing shall be accomplished by utilizing hot water, steam or ultraviolet
light in accordance with the manufacturer’s recommended cure schedule.
B. POST INSTALLATION VIDEO – Contractor shall provide one copy of the
electronic video files on CD, showing the pipe after lining. Video shall be
annotated to indicate all restored services. Video shall indicate liner free of
visual defects, such as foreign inclusions, dry spots, keel, boat hull, fins,
pinholes, wrinkles, and other deformities. Such defects may be cause for
rejection, at the City’s discretion, in which case the liner will be removed and
replaced by the Contractor at no additional cost to the City.
Sewer Rehabilitation Program, CIP 18701 13500 - 11
CURED-IN-PLACE-PIPE
C. REINSTATEMENT OF BRANCH CONNECTIONS - It is the intent of these
specifications that branch connections be re-opened without excavation,
utilizing a remotely controlled cutting device, monitored by a CCTV. The
Contractor shall certify a minimum of two complete functional cutters plus key
spare components are on the job site before each installation or are in the
immediate area of the jobsite and can be quickly obtained. Unless otherwise
directed by the Owner or his authorized representative, all laterals will be
reinstated. No additional payment will be made for excavations for the purpose
of reopening connections and the Contractor will be responsible for all costs
and liability associated with such excavation and restoration work.
D. PARTIAL CIPP LINERS
1. The partial CIPP liner shall be installed in accordance with ASTM F2599
and same requirements for a full length liner.
2. The saturated tube, along with the inversion bladder shall be inserted into
the carrying device and pulled into the host pipe. The pull is complete
when the end of the launching device is aligned with the beginning of the
section to be repaired. The resin and tube shall be completely protected
during the pull such that no resin is lost by contact with manhole walls or
pipe. The resin that provides a structural seal shall not contact the pipe
until positioned at the point of repair.
3. The installer shall be capable of viewing the beginning of the liner
contacting the host pipe verifying the exact placement of the liner. No
measuring from a CCTV counter or estimating will be allowed.
4. The tube will be extracted out of the carrying device by controlled air or
water pressure. The tube is held tightly in place against the wall of the
host pipe by the pressure until the cure is complete.
5. Any service lateral connections covered by the sectional repair shall be
restored in accordance with section C above.
E. INSPECTION
1. CIPP samples shall be prepared and physical properties tested in
accordance with ASTM F1216 or ASTM F1743, Section 8, using either
method proposed. The flexural properties must meet or exceed the values
listed in Table 1 of the applicable ASTM.
2. Wall thickness of samples shall be determined as described in paragraph
8.1.6 of ASTM F1743. The minimum wall thickness at any point shall not
be less than the minimum design wall thickness identified above.
Sewer Rehabilitation Program, CIP 18701 13500 - 12
CURED-IN-PLACE-PIPE
3. Visual inspection of the CIPP shall be in accordance with ASTM F1743,
Section 8.6.
F. CLEAN-UP - Upon acceptance of the installation work and testing, the
Contractor shall restore the project area affected by the operations to a
condition at least equal to that existing prior to the work.
* END OF SECTION 13500 *
Sewer Rehabilitation Program, CIP 18701
13600 - 1
MANHOLE REHABILITATION
SECTION 13600 – MANHOLE REHABILITATION
PART 1 - GENERAL
1.1 SUMMARY
A. This specification defines the method and material for the rehabilitation of
sanitary sewer manholes, utilizing a spray applied calcium aluminate
cementitious structural rehabilitation system. The purpose of this project is to
obtain a dense and durable concrete lining that is resistant to biogenic corrosion
and biosulfuric acid attack and meets the strength requirements described
elsewhere in this specification. The work covered in this specification consists
of furnishing all labor, equipment, materials, and supervision necessary to
accomplish the rehabilitation as specified. When complete the rehabilitated
structure shall:
1. Provide for a uniformly smooth surface of specified thickness.
2. Eliminate sources of inflow/infiltration (I/I).
3. Provide a service life that is supported by documented test analysis.
B. IDENTIFICATION OF MANHOLES TO BE REHABILITATED
1. The manholes to be rehabilitated are identified on the Contract Exhibits
located in Appendix B. Those manholes that display root intrusion or
evidence of infiltration upon visual inspection shall include pressure
grouting as part of the rehabilitation process, as further described in this
specification. Manholes that do not display root intrusion or evidence of
infiltration shall be rehabilitated without inclusion of the pressure grouting
process. The estimated quantities for each type of rehabilitation are
provided in the bid schedule.
1.2 SUGGESTED SEQUENCE OF WORK
A. The Contractor's sequence of operation relative to structural rehabilitation shall
include, but not be limited to the following:
1. Remove and dispose of existing ladders and/or steps when corroded.
2. Eliminate all sources of groundwater infiltration and voids in walls.
3. Provide a clean, rough sub-surface sufficiently prepared in accordance
with the International Concrete Repair Institute (ICRI) Guideline No. 03732
– Selecting and Specifying Concrete Surface Preparation for Sealers,
Coatings, and Polymer Overlays to a degree further defined in Part 3 of
these specifications.
4. Rehabilitate all interior surfaces including walls, ceilings, benches and
channels, unless otherwise indicated.
5. Application of curing compound to all repaired surfaces.
Sewer Rehabilitation Program, CIP 18701
13600 - 2
MANHOLE REHABILITATION
6. All manholes in unpaved areas that are identified for rehabilitation shall be
raised so that the top of the manhole frame and cover surface is a
minimum 6” above surrounding grade.
7. Install New Manhole Frame and Cover where indicated per City Std. Plan
No.’s 801 & 807.
8. Third party testing of lining and other structural rehabilitation materials.
1.3 SUBMITTALS
A. Contractor shall furnish detailed and complete data pertaining to the
rehabilitation product, surface preparation, curing compound and installation.
B. Work Plan. The work plan at a minimum shall include details of the surface
preparation, how operating air pressure is kept uniform to ensure adequate
nozzle velocity, uniform flow of product to nozzle, regulate water content so that
applied materials consistently achieve proper compaction. The work plan shall
further demonstrate that all spray application operators and foreman each have
a minimum of 2 years of experience with application of Sewpercoat PG or equal
product.
C. Safety plan. It is the contractor's responsibility to comply with OSHA standards
and all regulations pertaining to the work including confined space entry.
Contractor shall provide the necessary training and take the necessary
measures to provide a safe working environment for workers as well as the
public.
D. Manufacturer’s ISO 9001 certificate and supporting documentation.
E. Certified test reports and certificates.
1.4 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and other technical specifications as they apply to
this Section.
B. ASTM C109 – Standard Test Method for Compressive Strength of hydraulic
Cement Mortars
C. ASTM C293 – Standard Test Method for Flexural Strength of Concrete
D. ASTM C321 – Standard Test Method for Bond Strength of Chemical-Grout
Mortars
E. ASTM C496 – Standard Test Method for Splitting Tensile Strength
Sewer Rehabilitation Program, CIP 18701
13600 - 3
MANHOLE REHABILITATION
F. ASTM C596 – Standard Test Method for Drying Shrinkage of Mortar Containing
Hydraulic Cement
G. ASTM C597B – Standard Test Method for Pulse Velocity Through Concrete
H. ASTM C666 – Standard Test Method for Resistance of Concrete Rapid
Freezing
I. ASTM C882 – Standard Test Method for Bond Strength of Epoxy-Resin
Systems
J. ACI RAP-3 – Spall Repair by low Pressure Spraying
K. ACI 546R (Chapter 2) - Concrete Surface Repair Using Mortar
1.5 SUMMARY
A. Section Includes:
1. Prepackaged Mortar Mix Properties
2. Sampling and Testing Requirements
3. Qualifications of Work Crew
4. Surface Preparation and Mortar Application Procedures
5. Infiltration Remediation
6. Curing
Sewer Rehabilitation Program, CIP 18701
13600 - 4
MANHOLE REHABILITATION
PART 2 - PRODUCTS
2.1 LINING MATERIALS
A. Lining material furnished under this specification shall be a prepackaged mortar
mix, including all cement, aggregates, and any required additives. It is the
intent of this specification that the Contractor only be required to add the proper
amount of potable water so as to produce concrete suitable for spray
application. Under no circumstances, shall Contractor add Portland cement,
other aggregates, or any admixtures whatsoever to the pre-packaged lining
material. Typical bag weights shall not be less than 65 lbs. and shall be
identical for all material furnished on this project.
B. The chemical composition of the cement portion as well as the aggregates of
the mortar mix shall be as follows:
Al2O3 CaO FeO + Fe2O3 SiO2
40-46% 34-40% 9-15% 4-9%
C. The properties of the mortar mix shall meet the following:
Compressive Strength per ASTM C109 >5,500 PSI 24 Hours after mixing
Flexural Strength per ASTM C293 >1,300 PSI 24 Hours after mixing
Splitting Tensile Strength per ASTM C496 >900 PSI -
Bond Strength by Slant Shear per ASTM
C882
>2,300 PSI At 28 Days
Shrinkage at 28 Days per ASTM C596 <0.08% cured @ 90% Relative Humidity at 28
days
D. The lining material mortar mix shall be “SewperCoat PG” as manufactured by
Kerneos Inc. – Chesapeake, Virginia or Approved Equal.
E. The lining material mortar mix must have at least seven (7) years of successful
performance in similar applications and be supplied by an ISO 9001 certified
manufacturer.
F. In addition, the lining material mortar mix shall be designed to withstand long-
term exposure to a bacterially corrosive hydrogen sulfide environment that may
Sewer Rehabilitation Program, CIP 18701
13600 - 5
MANHOLE REHABILITATION
be expected to produce a pH of 1 on normal Portland cement based concrete or
typical brick and mortar surfaces.
G. Water used in mixing shall be fresh, clean, potable water, free from injurious
amounts of oil, acid, alkali, vegetable, sewage and/or organic matter. Water
shall be considered as weighing 8.32 pounds per gallon.
H. Lining material mortar mix shall be stored with adequate provisions for the
prevention of absorption of moisture. It shall be stored in a manner that will
permit easy access for inspection and identification of each shipment.
PART 3 - EXECUTION
3.1 SAMPLING AND TESTING
A. A recognized independent testing laboratory shall test mortar materials used on
the project.
B. The cost of sampling and testing of the mortar mix during placement and the
surface to which it is applied shall be borne by the Contractor. Other testing
required showing conformance with these specifications shall also be the
responsibility of the Contractor.
C. Any materials failing to meet the requirements of these specifications shall not
be incorporated into the Work. If the materials have already been installed
when it is determined that they don’t meet these specifications, then the subject
materials shall be removed and the work repeated with materials that meet the
specifications.
3.2 QUALIFICATIONS OF THE WORK CREW
A. The manufacturer shall maintain a listing of competent contractors that have
demonstrated requisite skill and training to be qualified applicators of their
materials.
B. Prior to project commencement, Contractor must verify that all Contractor’s
work crew personnel have performed satisfactory work in similar capacities
elsewhere for a sufficient period of time to be fully qualified to properly perform
the work in accordance with the requirements of the related specifications.
C. Foreman shall have at least 4 years of experience with similar work and project
conditions.
D. Nozzle and spray equipment operators shall be qualified by having had similar
work experience.
Sewer Rehabilitation Program, CIP 18701
13600 - 6
MANHOLE REHABILITATION
E. Work Crew responsibilities prior to application of lining material shall include the
following:
1. Surface preparation in accordance with section 3.4.
2. Ensure the operating air pressure is uniform and provides adequate
nozzle velocity for proper compaction.
3. Continuously regulate the water content so that the applied materials
consistently achieve proper compaction with a low percentage of rebound
and no visible “sag”.
4. Ensure that the installation equipment nozzle is held at the proper
distance away from and as nearly perpendicular to the prepared sub-
surface as the working conditions will permit to secure maximum material
compaction with minimum rebound and no visible “sag”.
5. Follow a sequence routine that will fill corners with adequately compacted
material applied at a maximum practicable layer thickness.
6. Determine necessary operating procedures for placement in confined
spaces, extended distances or around unusual obstructions where
placement velocities and mix consistency may need to be adjusted.
7. Direct the crew as to when to start and stop the flow of materials during
installation and to immediately stop all work when material is not arriving
uniformly at the nozzle.
8. Ensure that slough pockets are removed and prepared for installation of
replacement material.
9. Bring the installed materials to established finished elevations in a neat
and timely manner and within established tolerances.
F. Applicator’s job foreman shall operate the mixing/placing equipment and direct
the work of mixing crew personnel. Applicator’s work crew shall also maintain
proper line pressures throughout the mixing/placing equipment to ensure the
necessary consistent nozzle velocity. Applicator’s work crew shall further see
that all material fed to the nozzle is uniformly fed through this equipment.
Sewer Rehabilitation Program, CIP 18701
13600 - 7
MANHOLE REHABILITATION
3.3 EQUIPMENT - Equipment shall be of spray type and approved by the material
manufacturer. Alternate equipment may be utilized provided it meets the
performance requirements of the specification. All equipment must be in good
condition and fully functional.
3.4 SURFACE PREPARATION
A. Sub-surfaces shall be cleaned and made free of laitance, loose material,
residue and all existing coating and lining materials. Surface preparation shall
meet the requirements of American Concrete Institute (ACI) RAP-3 “Spall
Repair by Low Pressure Spraying” and ACI 546R “Concrete Repair Guide”,
chapter 2.
B. Sub-surfaces shall be thoroughly saturated with water prior to the application of
the lining materials. In no instance shall shotcrete be applied in an area where
running water exists. It is the intent of this specification that the existing surface
be saturated but free of any running water just prior to installation, otherwise
known as “saturated surface dry condition” (SSD). To achieve this condition it
may be necessary to presoak the sub-surface for at least 24 hours.
3.5 OPERATIONS
A. The Contractor shall provide all equipment necessary to individually gauge,
control, and monitor the actual amounts of all component materials necessary
to complete the lining installation. The type of equipment and methods used to
gauge, control, and monitor component materials shall be subject to approval
by the Engineer.
B. All lining materials shall be thoroughly mixed by mechanical means to ensure all
agglomerated particles are reduced to original size or removed prior to
placement into the application equipment (i.e. the hopper). Each batch of
material should be entirely discharged before recharging with fresh material.
Mixing equipment shall be cleaned at regular intervals to remove all adherent
materials.
C. The addition of water to the mix shall be in strict accordance with the
Manufacturer’s recommendations.
D. Re-mixing or tempering shall not be permitted. Rebound materials shall not be
reused.
3.6 PROTECTION OF ADJACENT SURFACES - During progress of the work,
adjacent areas or grounds which may be discolored, stained or otherwise
damaged by dust and rebound material, shall be adequately protected. If spills
Sewer Rehabilitation Program, CIP 18701
13600 - 8
MANHOLE REHABILITATION
or overspray occur, the area shall be immediately cleaned by scraping,
brushing or washing.
3.7 CURING
A. Several layers of liquid membrane curing compound shall be applied to all
surfaces and shall meet the requirements of ASTM C309. Curing compound
shall be approval by the Engineer prior to use.
B. Moist curing may also be used in lieu of curing compound. If moist curing is
selected, it should be implemented just after the notice of uniform heat
generation of the installed lining. Moist curing can consist of the use of soaker
hoses, water sprinklers, or vapor/misting machines to achieve a 100% humid
moisture condition. Regardless of delivery method, moist curing shall continue
for a minimum of 18 hours.
3.8 INFILTRATION REMEDIATION
A. If infiltration is observed or voids are present after surface preparation is
complete, a rapid setting crystalline enhanced hydraulic cement repair mortar
product specifically formulated for infiltration control shall be used to stop minor
infiltration flows and fill voids in accordance with the manufacturer's
recommendations. The material shall meet the following strength requirements:
Compressive Strength per ASTM
C597B
600-PSI
1,000-PSI
24-Hours
7-Days
Bond Strength per ASTM C321
30-PSI
80-PSI
1-Hour
24-Hours
B. All manholes displaying evidence of minor infiltration upon visual inspection in
the presence of the City inspector shall be repaired by filling space between
joints, cracks, voids and other structural deficiencies with repair mortar. Repair
mortar shall be Thoroc Plug, Octocrete, Burke Plug or Engineer approved equal
and shall be installed in accordance with the manufacturer’s published
instructions.
C. All manholes displaying evidence of heavy infiltration upon visual inspection in
the presence of the City inspector shall be sealed by pressure grouting prior to
installation of the Sewpercoat lining. The material for pressure grouting shall be
Avanti A-220, DeNeef or Engineer approved equal installed in accordance with
the manufacturer's published instructions.
Sewer Rehabilitation Program, CIP 18701
13600 - 9
MANHOLE REHABILITATION
D. If steel reinforcement is exposed and corroded, it shall be cleaned by brushing
or wet grit blasting until all corrosion is removed prior to application of repair
mortar.
E. All materials, labor, equipment, and incidentals required to replace missing
concrete or correct infiltration conditions will be considered incidental to
rehabilitation and no additional compensation will be made.
3.9 APPLICATION OF LINING
A. Lining material shall not be applied to a frozen surface or to a surface that may
freeze within 24 hours of application. Frozen conditions shall be defined as
ambient temperatures of 32 degrees Fahrenheit or below.
B. Sequence of application may be from bottom to top or vice versa and rebound
shall be properly removed.
C. Application shall be from an angle as nearly perpendicular to the surface as
practicable, with the nozzle held at least 1 foot from the working sub-surface
(except in confined control). If the flow of material at the nozzle is not uniform
and slugs, sand spots, or wet sloughs result, the nozzle operator shall direct the
nozzle away from the work until the faulty conditions are corrected. Such
defects shall be removed and replaced as the work progresses.
D. Application shall be suspended if:
1. Air velocity separates the cement from the aggregate at the nozzle.
2. Ambient temperature approaches freezing and the newly placed lining
cannot be protected and insulated.
E. The time interval between successive layers of material application must be
sufficient to allow “tackiness” to develop but not final set. If final set does occur,
this surface shall be prepared as in the case of initial application, which is
described above.
F. Construction joints within a manhole shall be avoided. In the event a
construction joint is necessary and approved by the Engineer, it shall be sloped
off to a thin, clean, regular edge, at a 45-degree angle. Prior to placement of
the adjoining materials, the sloped portion and adjacent applied material shall
be thoroughly cleaned as necessary, then moistened and scoured with an air
jet.
G. The nozzle operator shall bring the material to an even plane and to well-
formed corners.
Sewer Rehabilitation Program, CIP 18701
13600 - 10
MANHOLE REHABILITATION
H. After the body coat has been placed, the surface shall be trued with a thin-edge
screed to remove high areas and expose low areas. Low areas shall be
properly filled with additional material to insure a true, flat surface.
I. The minimum thickness of concrete lining shall be a ¾ inch cover over all
surfaces.
* END OF SECTION 13600 *
Annual Sewer Rehabilitation Program, CIP 18701 13700 - 1
SERVICE LATERAL
CONNECTION REHABILITATION
SECTION 13700 – SERVICE LATERAL CONNECTION REHABILITATION
PART 1 - GENERAL
1.1 INTENT
A. It is the intent of this portion of the specification to provide for the rehabilitation
of service lateral connections (SLC) to rehabilitated sewer lines, without
excavation, by installation and ultraviolet (UV) light curing of a resin-
impregnated, flexible fiberglass insert with sealing epoxy element in the form of
a tube and top hat that will be installed into the existing service lateral utilizing a
pressure apparatus and ultraviolet light curing device positioned in the mainline
pipe. Service lateral connections may be a combination of tee's, wye's or break-
in taps of varying sized and angle from 30 to 90 degrees and may include over-
cut lateral openings, pilot holes or defects in relined sewer pipe. The resin shall
be rapidly cured to transform the flexible insert into a hard, impermeable top hat
seal around and in the lateral connection. The SLC product shall extend from
the mainline into the lateral connection a minimum distance of 2 feet, in a
continuous tight fitting, watertight pipe within-a-pipe to eliminate ground water
leakage and future root growth at the lateral to mainline connection. SLC
product system shall be compatible with the mainline liner. If, within the
warranty period, the SLC product installed in the sewer system is not
acceptable due to leakage or any other defects, the contractor shall repair or
replace the affected portion at no cost to the City of San Juan Capistrano.
1.2 RELATED DOCUMENTS
A. This specification references standards from the American Society for Testing
and Materials that are hereby made a part of these specifications by reference:
1. ASTM D543 – Standard Practices for Evaluating the Resistance of
Plastics to Chemical Reagents.
2. ASTM F1216 – Standard Practice for Rehabilitation of Existing Pipelines
and Conduits by the Inversion and Curing of a Resin Impregnated Tube.
3. ASTM D3681 – Standard Test Method for Chemical Resistance of
Fiberglass (Glass-Fiber-Reinforced Thermosetting Resin) Pipe in a
Deflected Condition.
4. ASTM D2990-09 – Standard Test Methods for Tensile, Compressive, and
Flexural Creep and Creep Rupture of Plastics and Electrical Insulating
Materials.
Annual Sewer Rehabilitation Program, CIP 18701 13700 - 2
SERVICE LATERAL
CONNECTION REHABILITATION
5. ASTM D790 – Standard Test Methods for Flexural Properties of
Reinforced and Unreinforced Plastics.
6. ASTM D5813 – Standard Specifications for Cured-In-Place Thermosetting
Resin Sewer Piping Systems.
7. ASTM D578 - Standard Specifications for Glass Fiber Strands.
8. ASTM D638 – Standard Test Methods for Tensile Properties of Plastics.
9. ASTM D1600 – Standard Terminology for Abbreviated Terms Relating to
Plastics.
B. Reference is further made to National Association of Sewer Service Companies
(NASSCO) Standard: Recommended Specification for Sewer Collection
Systems Rehabilitation.
1.3 QUALIFICATIONS
A. The SLC rehabilitation contractor must have a minimum of a two (2) year
history of satisfactory performance with a minimum of 2,000 Top Hat lateral
repair installations of similar size and configuration as proposed in this project.
In addition, the onsite Superintendent must have installed over 1,000 Top Hat
lateral repairs of similar condition and have a minimum of 2 years of CIPP
industry experience.
B. The sewer repairs specified herein are intended to have a 50-year design life. In
order to minimize the Owner’s risk, only proven products with substantial
successful long-term track records will be approved.
1.4 SUBMITTALS – As a minimum, Contractor shall submit the following for review:
A. Resin. Long term test creep data confirming the resin system’s 50 year design
life in accordance with ASTM D2990. Chemical Resistance per ASTM F 1216.
Certificate of Compliance with ASTM F 1216
B. Tube. Certificate of Compliance with ASTM F1216. If glass fiber reinforcement
is used, CIPP strain Corrosion testing data in accordance with ASTM D3681.
C. CIPP wall thickness design calculations (for lateral liner) in accordance with
ASTM F1216.
D. The Contractor shall provide the inversion pressures necessary for proper
insertion and tube installation. The tube manufacturer shall provide the
minimum pressure required to hold the tube tight against the existing host pipe,
Annual Sewer Rehabilitation Program, CIP 18701 13700 - 3
SERVICE LATERAL
CONNECTION REHABILITATION
and the
maximum allowable pressure that will not damage the tube. Forces or
pressures shall be limited so the tube is not stretched longitudinally by more
than 5% of the original length.
E. The contractor or subcontractor performing the lateral lining work shall provide
a list of references, including Owner Name, Contact Name with phone number,
start and completion dates and Quantity of Laterals Lined, with the CIPP Lateral
Lining system used for that specific project provided, verifying compliance with
the qualifications indicated in section 1.3 above.
F. License or Certification that the contractor is approved to install the proposed
product.
G. Post Construction CCTV Videos, Reports and Photographs which clearly show
the lateral repairs
1.5 BIDDER’S INSPECTION – Bidder shall examine pre-construction CCTV video
files of sewers and become familiar with the existing sewer conditions prior to
submitting a bid. Videos will be made available for review on a web based
account for rapid sharing. Refer to the Notice Inviting Bids for more information.
PART 2 - PRODUCTS
2.1 MATERIALS
A. The finished SLC product shall be an ECR (E-glass corrosion resistant)
fiberglass laminate impregnated with a UV light reactive polyester resin which
when cured is chemically resistant to domestic sewage over the expected
lifetime of the rehabilitated pipe.
B. The carrier material for the tubes shall be of fibrous absorbent composition
tailored to achieve the following:
1. Allow the migration of resin from its internal structure by compressing to a
thickness of less than 90% of its uncompressed thickness under a
pressure of 1psi.
2. The carrier material must consist of non-degradable fibers such as
polyester or polypropylene or corrosion resistant fiberglass. The carrier
may use stitched or glued joints of material with sufficient strength to
comply with the following minimum requirements:
Table 1
CIPP Initial Structural Properties
Annual Sewer Rehabilitation Program, CIP 18701 13700 - 4
SERVICE LATERAL
CONNECTION REHABILITATION
3. The material must have an abrasion resistant, chemically resistant, fully
bonded coated surface in the lateral portion to ensure that on curing a
smooth surface free from blemishes, pinholes or loose non wetted fibers.
4. Where fiberglass is used, a surface veil or a layer of felt must be used to
prevent osmosis or wicking of the strands.
5. PET resins, resin filters, resin additives, and resin enhancement agents
are prohibited. Only neat resins are acceptable. Old resins and reworked
resins are prohibited, regardless of whether or not they are mixed with
new resin.
6. Proven resistance to the municipal wastewater environment that may
comprise, as a minimum, all of the following factors:
a. Immersion in septic sewage at temperatures up to 75 degrees F.
b. Exposure in hydrogen sulfide gas from septic sewage at
temperatures up to 75 degrees F.
c. Resistance to ultra-violet light (sunlight) at any stage prior to
installation.
d. Solvent free epoxy, polyester, silicate, and vinyl ester resins are
acceptable.
e. Shall not use silicones, stereates, or natural waxes that would
adversely affect the adhesive properties or any other chemical or
physical properties of the CIPP liner.
C. The SLC product shall be compatible with the lining system utilized for the
sewer main.
D. The flexible fiberglass top hat tube insert shall be fabricated to a size that when
installed will key into the internal surface irregularities of the lateral joint and
neatly fit tight to the internal circumference of the lateral. The top hat tube shall
be a laminate made of non-woven fiberglass materials (as outlined above) that
allow for circumferential stretching and angular alignment with the lateral pipe
connection geometry during insertion.
E. The insert laminate shall seal to the inside wall of the sewer main a minimum of
3 inches around the lateral opening and to the lateral pipe wall and12 inches up
into the lateral pipe from the main.
Table 1
CIPP Initial Structural Properties (ASTM F1216)
Property ASTM Method Minimum Value
Tensile
Strength
D638 3,000 psi
Flexural
Strength
D790 4,500 psi
Modulus of
Elasticity
D790 250,000 psi
Annual Sewer Rehabilitation Program, CIP 18701 13700 - 5
SERVICE LATERAL
CONNECTION REHABILITATION
F. Unless otherwise specified, the installer shall furnish a specially formulated
polyester resin and catalyst system compatible with the SLC process that
provides cured physical strength equal to or greater than that of the main line
CIPP liner.
G. A secondary epoxy sealing component shall be used to form a sealing bond
between the SLC product and the host lateral and sewer main CIPP liner.
2.2 PHYSICAL PROPERTIES
A. The cured SLC shall have a minimum Flexural Modulus of Elasticity equal to
800,000 psi in accordance with ASTM D790.
B. The top hat service lateral connection (SLC) repair system fiberglass and resin
composite shall have the minimum physical properties given below and in
accordance with the guidelines in the appendix of ASTM F1216.
1. Design Life: 50 Years.
2. Ovality: 2%
3. Pipe Condition: Fully deteriorated
4. External Water: ground surface
5. Flexural Strength: 4,500 psi
6. Short Term Flexural Modulus: 250,000 psi
7. Reduction Factor: 50%
8. Long Term Flexural Modulus: 125,000 psi
9. k (enhancement Factor): 7
10. Soil Modules: 1,000 psi
11. Soil Density: 120 pcf
12. Highway Live Load: AASHTO HS20-44
13. Safety Factor: 2 minimum
14. Min. Thickness 3 mm
15. If calculations require thicker wall, round to the next higher multiple of 0.5
mm.
C. Any layers of the tube that are not saturated with resin prior to insertion into the
existing host pipe shall not be included in the required design structural CIPP
wall thickness.
Annual Sewer Rehabilitation Program, CIP 18701 13700 - 6
SERVICE LATERAL
CONNECTION REHABILITATION
2.3 Delivery, Storage and Handling. Delivery, storage and handling of approved
products are the responsibility of the Contractor. The Contractor shall keep
them safe from damage and stored with the proper environmental containment
as outlined by the manufacturer. No products should be used that have
exceeded the designated shelf life as outlined by the manufacturer. Remove
damaged products from site. Promptly replace damaged products with new
products at no additional cost to the City of San Juan Capistrano.
PART 3 - EXECUTION
3.1 LINE PREPARATION
A. Contractor shall video inspect the service lateral immediately prior to the repairs
of the lateral and connection. The Contractor shall use a self-leveling camera to
determine the structural condition of the service lateral. Waste product build up,
hard scale, roots, lateral cutting debris, resin slugs or any other material that
interferes with proper installation of the top hat repair must be removed using
high pressure water jetting or in line cutters.
B. The section of lateral pipe to be lined must be free of debris, obstructions,
scale, or any other material that reduces the effective diameter of the pipe.
C. Break in connection and/or lateral pipe protruding into the mains shall be
ground back to no more than a 1/8 inch protrusion into the mainline.
D. Built up deposits on the main and lateral pipe walls shall be removed. The
removal shall reach at least one foot beyond the SLC repair to allow the bladder
to inflate tightly against the pipe walls ensuring a smooth transition from the
SLC repair to the existing pipe wall.
E. The contractor shall notify the Engineer immediately if the inspection reveals an
obstruction or if other conditions exists that will interfere with the proper
installation of the SLC repair.
F. In relined pipes, the lateral must be opened 95 percent or more and edges
finished without “teeth”. Over-cuts shall not exceed one inch beyond the
internal diameter of the lateral. The top hat contractor is responsible for
coordinating with the CIPP contractor (should they be different entities) for
proper opening of service lateral connections.
G. The contractor shall be responsible for preparation and distribution of public
notification flyer that explains the repair operation, when it will be performed,
how long it will take, and what the homeowner needs to do to help facilitate
installation of the SLC repair. SLC repair operation shall not require a
disruption of flow that exceeds four (4) hours. Coordinate homeowner
notification with the City of San Juan Capistrano.
Annual Sewer Rehabilitation Program, CIP 18701 13700 - 7
SERVICE LATERAL
CONNECTION REHABILITATION
H. The SLC repair contractor is responsible for cleaning the main sewer pipe and
lateral as required to facilitate the repair, and as a minimum within one foot of
the work area only. Remaining portions of the main sewer pipe will be cleaned
by the main sewer pipe CIPP contractor.
3.2 INSTALLATION
A. The resin impregnated SLC product shall be loaded on the applicator
apparatus, attached to a robotic manipulator device and positioned in the
mainline pipe at the service connection that is to be rehabilitated. The robotic
device, in conjunction with a television camera, will be used to align the SLC
repair product with the service connection opening. Air pressure, supplied to
the applicator through an air hose, shall be used to insert the resin impregnated
connection repair product into the lateral pipe. The inserted product will then be
inspected using a TV camera to confirm the SLC product is correctly positioned
and centered in the lateral opening prior to curing. The insertion pressure will
be adjusted to fully deploy the SLC product into the lateral connection and hold
it tightly to the main and lateral pipe walls.
B. The pressure apparatus shall include a bladder of sufficient length in both the
main and lateral line such that the inflated bladder extends beyond the ends of
both the lateral tube and main line brim segments of the SLC product. The
pressure apparatus shall press the end edges flat against the internal pipe wall
thus forming a smooth transition from SLC product to pipe diameters without a
step, ridge or gap between the SLC product and the inner diameter of the
lateral and mainline pipe.
C. After insertion is completed, recommended pressure must be maintained on the
impregnated SLC product for the duration of the UV light curing process.
D. The finished SLC repair shall be free of dry spots, lifts and delamination. The
installed SLC product (top hat) should not inhibit the post installation video
inspection, using a closed circuit television camera, of the mainline or service
lateral pipes or future pipe cleaning operations.
E. After the work is completed, the contractor will provide the City of San Juan
Capistrano with the post installation CCTV video, report and photographs
identifying the location and showing the completed work and restored condition
of each top hat repair.
F. During the warranty period, any defects with the SLC repairs shall be corrected
at the contractor’s expense in a manner acceptable to the City of San Juan
Capistrano.
Annual Sewer Rehabilitation Program, CIP 18701 13700 - 8
SERVICE LATERAL
CONNECTION REHABILITATION
3.3 INSPECTION
A. The finished liner shall be free from visual defects such as foreign inclusions,
dry spots, pinholes, wrinkles and other deformities.
B. The contractor shall inspect each installation visually by CCTV. No infiltration of
groundwater shall be observed. The repair product shall be inspected closely
for excessive wrinkling, exposed unwetted fibers, pinhole leaks and infiltration
around the terminations. The pre and post connection CCTV videos, reports
and photographs shall become the property of the City of San Juan Capistrano.
3.4 CLEANUP
A. The Contractor shall restore the project area affected by the operations to a
condition at least equal to that existing prior to the work. During the warranty
period, any defects with the SLC repair that affect the performance or cleaning
of the lateral connection shall be repaired at the contractor’s expense in a
manner acceptable to the City of San Juan Capistrano.
* END OF SECTION 13700 *