September 2, 1997
ADDENDUM NO. 1
PREVENTATIVE STREET MAINTENANCE, 1997-1998
1. PEPPERTREE BEND
2. MISSION HILLS RANCH
3. SILVER CREEK DRIVE
4. CALLE ARROYO BIKE TRAIL AND
5. (ADDITIVE ALTERNATE) RANCHO VIEJO ROAD
The following changes to the plans and specifications are promulgated through this addendum.
Table of Contents
Delete Page 1
Add Page 1, Revised.
Section 13 - Utility Relocations
Delete Page SP-6
Add Pages SP-6R.
A signed copy of this addendum shall accompany the bid.
Contractor Brian Perry
Senior Civil Engineer
brian\adn97-98.a
32400 PASEO ADELANTO, SAN JUAN CAPISTRANO, CALIFORNIA 92675 • (714) 493-1171
•
TABLE OF CONTENTS (REVISED)
PREVENTATIVE STREET MAINTENANCE 1997-1998
1. PEPPERTREE BEND, 2. MISSION HILLS RANCH, 3. SILVER CREEK DRIVE,
4. CALLE ARROYO BIKE TRAIL, AND 5. (ADDITIVE ALTERNATE)
RANCHO VIEJO ROAD
TITLE PAGE
CONTRACT DOCUMENTS
Notice Inviting Bids 1
Bid Proposal 3
Schedule of Work Items 6
Non-Collusion Affidavit 9
Designation of Sub-Contractors 10
Instructions to Bidders 11
Bid Bond BB-1
Performance Bond PB-1
Labor& Material Bond LM-1
CONTRACT
Contract 1-4
SPECIAL PROVISIONS
Work to be Done SP-1
Section 1 Standard Specifications SP-3
Section 2 Terms Defined SP-3
Section 3 Flow and Acceptance of Water SP-3
Section 4 Water SP-3
Section 5 Insurance and Overhead Costs SP-3
Section 6 Protection of Existing Utilities SP-3
Section 7 Protection of Private Property SP-4
Section 8 Construction Zone SP-4
Section 9 Pre-Construction Coordination Meeting SP-4
Section 10 National Pollutant Discharge Elimination System SP-4
• Section 11 Preservation of Survey Monuments SP-5
Section 12 Monumentation Identification SP-5
Section 13 Utility Relocation SP-6R
Project Schedule Form
DETAIL SPECIFICATIONS AND METHOD OF PAYMENT
Bid Item 1 Project Survey DS-1
Bid Item 2 Reestablish Centerline Ties and Monuments DS-1
Bid Item 3 City Notification Signs DS-1
Bid Item 4 & 21 Traffic Control DS-1
Bid Item 5 Cold Plane Existing Concrete 0.12' Deep to Zero DS-2
Bid Item 6 Asphalt Concrete Overlay III C2 AR4000 DS-2
Bid Item 7 Adjustment of City Manhole Frames and Cover Sets to Grade DS-3
Bid Item 8 Adjustment of CVWD Valve Boxes to Grade DS-3
•
SECTION 13 - UTILITY RELOCATIONS
In accordance with Section 5-1 of the Specifications, the Contractor shall determine the location and depth of all
utilities, including service connections, which have been marked by the respective owners and which may affect
or be affected by its operations. The Contractor shall receive no direct compensation for this work. Accordingly,
full compensation for such work should be prorated to the appropriate bid items.
Utility relocations may be necessary during this construction contract. The various utilities have indicated that
the following notifications and work schedules are necessary:
1. Silver Creek Drive
Utility Facility Advance Notification Time for Utility Work
Cox Cable TV House Service 5 Working Days 1 Working Day
So. Calif. Gas House Service The Gas Co. will pothole
existing house services and,
if necessary, will lower them
to 1-foot bellow bottom of
trench prior to this construc-
tion contract.
2 Calle Arroyo Bike Trail
Utility Facility
Water Main Line These utilities have indicated
& the close proximity of their
So. Calif. Gas House Service facilities to the construction area.
It is not anticipated that relo-
cation will be necessary for these
facilities. The contract, however,
requires excavation by hand for
the installation of the street-side
Biobarrier.
3. Mission Hills Drive
Utility Facility
Pacific Bell New Line Pacific Bell has indicated that it will
construct new underground facilities
within the area of Rancho Viejo Road
and Mission Hills Drive. The contractor
shall allow for this utility work to precede
the street work.
The Contractor shall allow in his bid for all costs to accommodate this work into his construction schedule. The
Contractor shall receive no direct payment for accommodating this work. Accordingly, these costs should be
prorated to the appropriate bid items.
The Contractor shall notify the utility in writing of the work required with copy of the letter to the City Project
Manager.
SP-6R