11-0106_LEGEND PUMP & WELL SERVICE_Action Reminder Fi✓5 - l
CITY CLERK'S DEPARTMENT- ACTION REMINDER
TO: Justin Kirk, Sr. Management Analyst
FROM: Kristen Lewis, Administrative Specialist DATE: April 1 , 2011
SITUATION:
On January 6, 2011, the City of San Juan Capistrano entered into a Contract with Legend
Pump and Well Service to provide pump replacement for CVWD Well No. 1 .
ACTION REQUESTED:
Contractor agrees to begin and complete the work within 90 days from Notice to Proceed,
dated January 18, 2011 .
(*The project manager will need to amend the Agreement if services are to continue after
April 18, 2011")
Please notify this office if agreement will be extended or is complete.
ACTION TO BE TAKEN:
DATE WHEN NEXT ACTION (S) SHOULD BE TAKEN:
SIGNATURE OF OFFICIAL TAKING ACTION:
DATE SIGNED: I L .
***FOR CITY CLERK'S DEPARTMENT USE ONLY***
Tickler Date: 04/01/2011
Deadline Date. 04/18/2011
Cc: Betsy Dubois, Administrative Specialist
(600.30/Legend)