09-0120_M.S. CONSTRUCTION_Change Order No.2 LITTLE HOLLYWOOD PHASE II CONTRACT CHANGE ORDER NO. 2
In accordance with the contract provisions, the following changes in the contract and/ or contract work
are hereby authorized and as compensation, the following additions to or deductions from the contract
rice are hereby approved.
Change Order: No. 2, Page 1 of 1 Beginning Contract Date: January 20, 2009
Date: July 21, 2009 Contract Amount: $2,083,853.33
Project Number: 28-00000-67301-07921-000 Change Order No.1:$ 24,425.96
Location: Little Hollywood Phase II This Change Order: $ 56,158.20
Ramos and Mission Street Adjusted Contract : $2,164,437.49
ITEM DESCRIPTION OF CHANGES DECREASE M INCREASE IN
No. TO ORIGINAL SCOPE OF WORK CONTRACT CONTRACT
PRICE PRICE
Requirement for Equestrian Bridge
1. Rip-Rap from Bioswale. Item Originally $ 0.00 $ 11,037.91
Excluded From Specs. (LH #4)
2 Additional H2O Line Gas Line Along Ramos St $ 0.00 $ 5,168.78
Work Requires H2O Line Detour (LH#5)
Additional Headwall & Requirement for Pipe Inlets to
3' Pipe Gates Bioswale. Item Originally Excluded $ 0.00 $ 2,721.29
From Specs. (LH #6)
4 Additional Gas Line Requirement for Gas Connection, $ 0.00 $ 32,293.56
Trenching Per The Gas Co. (LH #7)
5 Raise Existing Manhole Site condition & grade requires to $ 0.00 $ 4,936.66
to Grade raise manhole by 4 ft. (LH #9)
TOTALS $ 0.00 $ 56,158.20
Change in Contract Price Due to this Change Order: $56,158.20
The additional work contained within this Change Order can be performed incidental to the prime work
and within the time allotted for the original Contract and any extensions to the Contract Time made by
this and all previously issued Change Orders, if any. It is therefore mutually agreed that the number of
calendar days extension of time, if any, provided for in this change order is required for the change of
work provided herein, and that no direct or indirect, incidental or consequential costs, expenses, losses
or damages have been or will be incurred by Contractor, except as expressly granted and approved by
this Change Order, and further that the payment under this change order is the final and complete
compensation for the subject work.
ACCEPTANCE DATE
Accepted by
Mike Saghafi, Pres. M.S. Construction
Recommended by
Douglas D. Dumhart, Econ. Dev. Mgr.
Approved by
Joe Tait, Interim Executive Director
Page 1 of 1
ATTACHMENT 1