06-0207_RBF CONSULTING_D3_Agenda Report2/7/2006 013 AGENDA REPORT TO: Dave Adams, City Manager q)�` FROM: Amy Amirani, Public Works Director SUBJECT: Consideration of Project Update for the Terminal Reservoir No. 3 Project (CIP No. 753) City Council Priority No. 21 By motion, receive and file SITUATION: The City is currently replacing the existing Terminal Reservoir No. 2 (T2) with a new 6 million gallon facility, Terminal Reservoir No. 3. T2 is in need of replacement due to structural stress caused by differential settlement. Construction of the project is over 60% complete. All excavation and slope stabilization work has been completed. Work on the pre -stressed concrete tank is ongoing. The tank floor slab has been completed and construction of the tank walls and structural columns is ongoing. During construction of the project, a number of unforeseen conditions required the contractor to perform out of scope work items. These include installing additional flex couplings for the reservoir inlet/outlet line, increasing the size of the proposed air gap structure, installing a supplemental blower in the proposed chloramination building, installing additional bracing for the eastern shoring wall due to unexpected differential movement, and installing a storm drain extension line for a previously undetected storm drain outlet. The total cost for these work items is $249,142.14. The majority of this cost comes from the installation of the additional bracing and the storm drain extension. These items total over $230,000. The progress of construction has been impacted by a total of 105 calendar days. 44 of the 105 calendar days are due to the additional bracing and storm drain extension work mentioned above. The balance of 61 calendar days is due to the heavy rains that hit Southern California during the last year. The contractor has therefore requested a non - compensable time extension of 105 calendar days. Completion of the project will be extended to late Fall 2006. Staff, along with the construction manager, RBF Consulting, Inc. has reviewed both the cost and schedule impacts outlined above, and determined these impacts to be r] Agenda Report Pape 2 February 7, 2006 total cost of $249,142.14 and a total of 105 calendar days of non -compensable time extension. Staff has reviewed and approved Change Order No. 1. A Mitigated Negative Declaration has been adopted for this project and mitigation measures specified in the document are being implemented. COMMISSION/BOARD REVIEW AND RECOMMENDATIONS: The Water Advisory Commission has reviewed this item at their January 24, 2006, meeting. FINANCIAL CONSIDERATIONS: On September 21, 2004, the City of San Juan Capistrano awarded a construction contract for a total of $10,527,276 to Gateway Pacific Contractors, Inc. On the same date, the City Council authorized the City Manager to approve necessary changes to the construction contract within the project budget. The recommended Change Order for a total of $249,142.14, represents approximately 2.6% of the construction contract. This Change Order can be covered within the project budget. NOTIFICATION: Not applicable. RECOMMENDATION: By motion, receive and file. Respectfully submitted, U4- 4wo--�. Amy Amirani Public Works Director Attachments: 1. Change Order No. 1 2. Location Map Prepared by, • CONTRACTOR: City of San Juan Capistrano Terminal Reservoir No. 3 Contract Change Order No.1 0 January 9, 2006 This Change Order covers changes to the subject contract as described herein. The Contractor is to construct or furnish equipment and materials, and performs all work as necessary or required to complete the Change Order items for the prices agreed upon between the Contractor and the City. The additional work contained within this Change Order can be performed incidental to the prime work and within the time allotted for the original Contract and any extensions to the Contract Time made by this and all previously issued Change Orders, if any. It is therefore mutually agreed that the number of calendar days extension of time, if any, provided for in this Change Order is required for the change of work provided herein, and that no direct or indirect, incidental or consequential costs, expenses, losses or damages have been or will be incurred by Contractor, except as expressly granted and approved by this Change Order and, further, that the payment under this Change Order is the final and complete compensation for the subject work. Payment to the contractor for this Change Order shall provide full compensation for all equipment, materials, labor, field and home office overhead, mark-ups and profit necessary to complete the work. By executing this Change Order, contractor agrees to proceed with the work as a change order per Section 9 of the Construction Contract and waives any right to additional compensation arising out of work listed in this change order, including without limitation, any claims relating to any cumulative effect of changer orders, delays, productivity impact or interruption. In accordance with the contract provisions, the following changes in the contract and/or contract work are hereby authorized and as compensation, the following additional to or deductions from the contract price are hereby approved. Item Description Amount 1) Furnish and Install 2 16" Flex Couplings as detailed in the attached $4,865.25 Exhibit "K Non Compensable Time extention due to inclement weather 2) (December 04 to January 05) as detailed in the attached Exhibit $ 0 'IA„ ATTACHMENT 1 0 0 3) Non Compensable Time Extension due to inclement weather "A" $ 0 (February 05 to March 05) as detailed in the attached Exhibit 4) Increase size of air gap structure as detailed in the attached "A" $4,805.82 Exhibit 5) Non Compensable Time Extension due to saturated soil "A" $ 0 conditions as detailed in the attached Exhibit 6) Furnish and Install fan for Chloramination Building as detailed in "A" $525.00 the attached Exhibit 7) Furnish and Install raker bracing system as detailed in the "A„ $183,755.23 attached Exhibit 8) Furnish and Install storm drain system extension as detailed in the "A" $55,190.84 attached Exhibit 9) Non Compensable Time Extension due to inclement weather $ 0 (April 05 to December 05) as detailed in the attached Exhibit "A" Total for Change Order No. 1 $249,142.14 The original cost for this work was: $10,527,276.00 The cost of amendments/change order(s) to date is: $ 0 The cost of this amendment/Change Order No. 1 is: $ 249-142-14 Upon approval, the total cost of this project is: $10,776,418.14 The original contract completion date for this work was: 02 August 2006 The additional work included in this Change Order shall add: 105 calendar days The contract completion date shall be revised as: 15 November 2006 K, 0 0 The Contractor agrees to furnish all labor and materials and to perform all other necessary work required to complete the Change Order items. This document will become a supplement to the contract and all provision will apply hereto. It is understood that the Change Order shall become effective when approved by the City. RECOMMENDED: & „ — � C�' - Dave Adams, City Manager Amy Ami a , Public Works Director for Civil Engineer RBF, Construction Manager Tim Brown, Gateway Pacific, Contractor 3 1 11-1%O6 Date I A0 0 Date I DC o Date f �9 ff}�J ZooG Date 119/a(a Date 0 City of San Juan Capistrano Terminal Reservoir 3 Project ATTACHMENT "A" Including: RBF Cover Letter ( 01 page) Proceed Order No. 1 ( 06 pages) Proceed Order No. 2 ( 02 pages) Proceed Order No. 3 ( 03 pages) Proceed Order No. 4 ( 10 pages) Proceed Order No. 5 ( 02 pages) Proceed Order No. 6 ( 05 pages) Proceed Order No. 7 ( 21 pages) Item No. 8 ( 03 pages) Item No. 9 ( 01 page) Total ( 54 pages) 11 0 FBF January 04, 2006 CONSULTING JN 10-103242 Mr. Peter Salgado, PE CITY OF SAN JUAN CAPISTRANO 32400 Paseo Adelanto San Juan Capistrano, CA 92675 Re: Terminal 3 Reservoir Project; Contract Change Order No. 1 Dear Peter, Based on conditions that have changed in the field, RBF Consulting recommends to the City that Contract Change Order No. 1 be approved. Below is previously approved Proceed Orders 1-7 as well as items 8,and 9 to be included in Contract Change Order No. 1. (Back up documentation for each item listed below is attached) Number Title Initiated Finalized $ Amount Non Compensable Days PCO 001 Additional Flex Couplings, 16" 06 Oct 2004 25 Oct 200 $ 4,865.25 PCO 002 Non Compensable Time extension due to inclement weather Dec 04 to Jan 05 05 Feb 2005 24 Feb 200 $ - 21 PCO 003 Non Compensable Time extension due to inclement weather Feb 05 to Mar 05 07 Apr 2005 20 Apr 200 $ - 17 PCO 004 Increased size of air gap structure per RFI 029 22 Apr 2005 05 May 200 $ 4,805.82 PCO 005 Non Compensable Time extension due to saturated soil 05 May 2005 02 Jun 200 $ - 1 CO 006 an for Chloramination Building05 Jul 200 14 Jul 200 $ 525.00 PCO 007 Raker installation - Wall Reinforcement 05 Jul 200 14 Jul 2005 $ 183,755.23 30 item 008 Storm Drain Extension/ Augmentation $ 55,190.84 1 It009 Non Compensable Time extension due to 'nclement weather r 05 to Dec 05 9 otal $249,142.14 105 Should you require additional information, or have any questions, please contact me at 949.300.9132. Thank you. Speeye�l�y,, Bill Seitz Construction Management Attachments: proceed orders, items c v m,arZwonwicnR310103142�con9tl6 o ccomcco om¢co oor aar coy r doc PLANNING DESIGN t CONSTRUCTION 14725 Alton Parkway, Irvine, CA 92618-2027 • P.O. Box 57057, Irvine, CA 92619-7057 • 949.472.3505 ■ Fax 949.472.8373 Offices located throughout California, Arizona & Nevada • www.RBrccm orm.m re,. Www PW GONF111 T:Nr Date of Issuance: 0 0 Proceed Order No.1 Terminal Reservoir No. 3 CI of San Juan Cap, Gateway Pacific Contractors, Inc JN: '0.103242 02 Dec 2004, Thursday You are directed to proceed promptly with the following change(s). Effective Date: 09 Dcc 2004. Thursday Description: Please subinii a cost to Install an additional two (2) 16" Tex couplings w) restraining harnesses as identified on Ccn;tructioa Nose Seven (7) on page C-10 -Site, Piping Plan' (14 of 74 sheets) per detail CK:27 on the 16" CMLBC inlet and outlet inies `-or TR3 (approx station 23+00). Refer to RR 002 dated 04 Oct 2004, Attachments- PCO 001 Costs dated 20 Oct 2004 REQUEST FOR CHANGE ORDER PROPOSAL dated 06 Oct 2004 RFI 002 dated 04 Oct 2004 Method of determining change in Contract Price: Unit Prices X Lump Sum Other Agreed increase in Contract Price. 54.865.25 if the ahango involves an increase, the estimated amount is riot to be eiiccoded without further authorization. Prepared by: Method of determining change in Contract Times: Contractor's records Engineer's records N,A Other No Increase in Contract Time: ,. C9 Dec 2004 Bl! Sei'-,.;�C}-ir�striren Manage,-3B.� Cansulting Reromnaentled: Peter Salgado_ Project Manager. San Juan Capistrano Approved by:--- Arny Amtrani DI ectar of Public Works, San Juan Capistrano We. the undersigned contractor, have given careful consideration to the change proposed and hereby agree, it this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above speclt€ed, and wO accept as full payment therefore the prices shown above r r - .. "_ r Accepted: Gary A Bifcnte., Vice President Gateway Pacific Contractors_ Inc 11 - -1 -1---,--- -1--1 1 0, ----- --1111 - --------- 11-11,11, GATEWAY PACIFIC CONTRACTORS, INC. RECEIVEO HI r October 20, 2004 -48F C(NSULANG Mr, Bill Seitz RBF Consulting 14725 Alton Parkway Irvine, CA 92618 RE: City of San Juan Capistrano Terminal Reservoir No. 3 PCO #1 — Additional Flex Couplings Attached please find backup for the costs associated with PCO #1 — Additional Flex Couplings, per your Request for Change Order Proposal No, 1, dated October 6, 2004, The total cost to the project is $4,86525 - Following your review, please process a change order to Gateway Pacific. If any further questions arise, please contact rne, Sincerely, Gary A. Bechtel Vice President - Operations cc File, Tim Brown, Jay Hall 8055 Freeport Boulevard, Saoramento, Callforrile 96832-9716 +(916) 6654100 - (916)666-4119 FAX Terminal Reservoir No. 3 City of San Juan Capistrano PCO No. 1 ' crintion of Work: 16" Flex Coupling ,ition _ Unit i Unit i Unit ? TOTAL —^Description (qty UUnits Cost Labor Cost Material Cost Equip ; S/C _ Labor'tr (2 ea) 16 hrs 46 95! 7v120 75920 ,CPF Quote 1 Is .. f 8.16000 3.160-00 3.150.UE"� SuhtotaIs 751,20 3,160_00 000 3 5'I 1.f0 .Jaei Tax'Ci) 7.751,,, 244 �90 _5._/p�l0� U Vl) Subtotal- 759-2v3,404 9B U 000.010 4 156 It, Marku) Lw)or 0I 2P'l, 150141 150 >4! Markup - Malls 5110 71 `,ib 741 Markup -Equip rw 15% 1 0,00 Markup Subs rd; `" j —... `j,Oul `ubtotal 901.44 1 3.915.641I 0 00 0.00 4 1717 [ifs'. i O.wl Ct00 4&'7 _ i I 4,865`251 i 0 Proceed Order No.2ftBF a Terminal Reservoir No. 3; r rn..st, rn�ra -CITY 0 .. ..anuan _ Cap. _._Cateviay Pacific Con_r_a_c.tors_,. Inc_ N 1 103 '42 1 evJ—✓. Date of Issuance: 07 tet3 2005. Monday Effective Date: You are directed to proceed promptly with the following change(s): DasCnOon Mo&f'y the completion acceptar rcf, date of the contract to allow for an add,tional ffteer, I i St werkmg days Basad n+ a ` day ww work, tuns will be an wwwrilent of %verty-one 121 i ca;endar days This wilt bring the allowed contract complel'on date from 02 Aug ?006 to 23 August 2006 They a non-ccmpe':nsab!e extension of ;he Contract to allow `o: dciays caused try nclernenr we:2iher. Tta refsect> a1i de!aps th, ongn 31 Jan 2005 Aaachreent;'- ReyueSt for additional tune :ah -d 03 f 2h 2UC5 Copy of corrent schedwe Method of detorminmg change .n Contract Pr<ce- Uort Pncr,s .�.__..._�_.. I Jf np Sum x 0,1-e. Agreed increase in Contract P=ire $0 OC; wo dcllarsl - NONc If ft , +lharrge ,. ✓o",Aos un inaFaae. ih!, g v -iced ,amount,s not to he e,reer}eri ,wNtouf fu^her aWh1;or,zat,or, Nietho; of deterr*nrvng r_hange In Contract Cuntrr omrs rec.rrds X F. r;g�neer's recurtis Other 02 Au 2ti06 Ongi, a? t7a±,e for Gomplehnn 2 t Lzter's+vn of Gcslenda: daY6 (hu- nUree:.' +adz= 7 i. .-..._ E.xtensrmn of `:a?endar 7ay5 anprovcd to ,IW, 23 Au,06, Revised Detc for nn,clolion. Prepared by Rrl Seitz Cor straction Pdlaneger R[3F Cone.rlting }' f;OYnmended _ Peter Sa§gado Project Manager San Joan Caprstramn " r a ApproveG Am;y Arrirant. Uvectcr of P b1 c Works, San Juan t p, tranc Wethe undersgne o contractor- have given carefu; consderalion to the change proposed and hereby agree df Crus paler is approved. that we, MI provide all equipment. furnish all materials, except as sn.ay otherwise be noted above, and pa.'rocn a?l servioes necessary for the work above speafied, and will trccept as full payment flies®fate the prkRes shown above _. rmry A Ben ta- h:ce Preerriert. Gateway Pac4ic Cortmz.. r., Irc 0 0 GATEWAY PACIFIC CONTRACTORS, INC. February 3, 2005 Mr. Bill Seitz RBF Consulting 14725 Alton Parkway Irvine. CA 92618 RE: City of San Juan Capistrano Terminal Reservoir No. 3 Weather Delays Due to inclement weather conditions, Gateway Pacific was unable to perform work on fifteen scheduled working days. These days were previously agreed upon during the weekly progress meetings. This request covers all rain delays for December and January, during these unusually heavy rains winter months. In accordance with Section 7 of the Construction Contract, and Article 12.02 of the General Conditions, we request 15 scheduled working days be granted to extend the time for successful completion of this project. This will be a non - compensable extension of time. This will move the final completion date from August 2, 2006 to August 23, 2006. Please contact us if you should have any questions regarding this request. Sincerely, r � Jaythi'al1 Project Manager cc: File, Gary A. Bechtel, Tim Brown 8055 Freeport Boulevard, Sacramento, California 95832-9716 • (916) 665-4100 • (916) 665-4119 FAX 0 0 ppiC' Proceed Order No.3 4! ��'�■ Terminal Reservoir No. 3 ' c:aN�u �n n+c;. +Ci of San Juan (11P toPacific Contract ors. Inc, JN 1.0-1M,12 Date of Issuance: 0? Apr 2005. Thursday Effective Date: You are directed to proceed promptly with the following change(s) Description Modify the completion acceptance date of the contract to allow for an additional twelve (12) working days Based on a 5 day work week, this will bean equivalent of sventeen (17) calendar days. This will bring the allowed contract coinp)enon, date, from 23 Aug 2006 to 09 September 2006_ This a non -compensable extension of the contract to allow for delays caused by inclement weather This reflects all delays through 31 Mar 2005. Attachments, Request for additional time dated 06 April 2005 Copy of airreni schedule Method of determining change in Contract Price_ Unit Prices `... Lump Sum 4-_ X --Other Agreed Increase in Contract Price - SO L70 "no,dofarsr, - NONE`_ If the change involves an increase, the estimated amount is not to be exceeded without further authorization. (Method of determining change in Contract Times: --.--,,—Contractor's records x Engineer's records Other 02 Auq 2006 Original Date for Completion 17 FzCension of Cale,tdar days this proceed ordar 21 _ Lxtens.c r of Caiendar days approved to date 09 Sep_2006 Revised Date for Completion Prepared by: 01Apr 2005 _-,_...--------- Bill Seitz,,gpgstrjction Manages RBF Consulting , Recommended Peter. Salgado, Pr¢;ectjvlartage;,& j's Juan Capistrano Approved by r_l,r. '_""'>l' �,)- f' ry,_'-i'y7y----"" 'Yd cnj�t9� Amy Amirani, Director of Public'Norks. San Juan Capistrano We, the undersigned contractor, have given careful consideration to the change proposed and 'hereby agree if this order is approved. that we will provide all equipment furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified., and will accept as full payment therefore I he prices shown above Acc:epted- ary cx,si At. _,-.—e-a1Bah, Z r,,, tc ,,,._ ins GATEWAY PACIFIC CONTRACTORS, INC. April 6, 2005 Mr. Bill Seitz RBF Consulting 14725 Alton Parkway Irvine, CA 92618 RE: City of San Juan Capistrano Terminal Reservoir No. 3 February & March Weather Delays Due to inclement weather conditions, Gateway Pacific was unable to perform work on twelve scheduled working. days. These days were previously agreed upon during the weekly progress meetings. This request covers all rain delays for February and March, In accordance with Section 7 of the Construction Contract, and Article 12.02 of the General Conditions, we request 12 scheduled working days be granted to extend the time for successful completion of this project. This will be a non - compensatory extension of time. This will move the final completion date from August 23, 2006 to September 9, 2006. Please contact us if you should have any questions regarding this request. Project Manager cc: File, Gary A. Bechtel, Tim Brown Ci J E 0 Proceed Order No.4 Terminal Reservoir No. 3 conrsr..r u'i NU Ci of San Juan Cap. Gateway Pacific Contractors, Inc. JN10-103242 Date of Issuance: 25 Apr 2005, Monday Effective Date: You are directed to proceed promptly with the following change(s): Description Based on CDM's response to RFI 029, GPC has submitted an estimate to increase the size of the air gap structure from r0^ to 84' Additionally, a Fiberglass reinforced plastic grate shall be provided in lieu of aluminurn. Attachments: RFI 028, 029 Request for additional funds dated 18 Apr 2005 Method of determining change in Contract Price: Unit Prices X Lump Sum Cather Agreed increase in Contract Price: $4,80582 utile change involves an Increase, tite estimated amounts not to be exceeded without farther authorization Method of determining change in Contract T`mes. Contractors records Engineer's records N;A Other Ne increase in Contract Time: Prepared by _ �•'--"i. _ 22 Apr 2005 Bill Seitz, Con etrftton _ , RBF Consulting Recommended. Approved by: Manager, San Juan Capistrano Amy Amiranr Dlrecfor of Public Works, San Juan Capistrano We, the undersigned contractor, have giver careful consideration to the change proposed and hereby agree. if this order's approved, that we will provide all equipment, furnish all materials. except as may otherwise be noted above. and perform all services necessary for the work above specified., and will accept as full payment therefore the prices shown above.t,.� Accepted: { .,fc�`•m-t,,,Y'w Gary A_ Bechtel, Vice President. Gateway Pacific Contrac.ois_ Inc 1 - T1; t .....,_r i .,r .;. ", n Grnse'. ,:aea 0 s. .c.. N","i '! 11 lillf ., GATEWAY PACIFIC CONTRACTORS, INC. April 18, 2005 Mr, Bill Seitz RBF Consulting 14725 Alton Parkway Irvine, CA 92618 RE: City of San Juan Capistrano Terminal Reservoir No. 3 PCO #2 — Increased Air Gap Structure REVISED Attached please find backup for the costs associated with PCO #2 — Increased Air Gap Structure. The total cost to the project is $4,805.82. The 60" inside diameter Air Gap Structure was found structurally unstable with one (1) 14" SDR 35 PVC Drain and two (2) 36" RCP Culvert pipe penetrations. Per engineer's response to RFI #20, the Air Gap Structure inside diameter shall be increased to 84" and a fiberglass reinforced plastic (FRP) grate with a 150lb/sqft loading shall be provided in lieu of an aluminum grate called out in the contract documents. For product data and shop drawing details associated with this change please refer to Submittal #43B - Air Gap Structure. Gateway Pacific is requesting a change order for the additional material cost. The extra excavation and installation cost is negligible. Please issue a change order for this extra cost, so we can proceed with the fabrication of the Air Gap structure. If any further questions arise, please contact me. Sincerely, ',� Ja�Hall Project Manager cc: File, Gary A. Bechtel, Tim Brown 8055 Freeport BOuleVard, Sacramento, Glllornle 95832-9716 • (916) 665-4190 • (916) 6651119 FAX E Terminal Reservoir No. 3 City of San Juan Capistrano PCO No. 2 Description of Work: Increase Air Gap Struture to 84" diameter with FRP Grating 0 '' • .• • •- �®-- :•111 :•111--- :•111 __- 111_ :•111- 111 111 :•111 - - • __- � . 1 11 �- 111 1 11 • • • -• __- • 1 11 ��� 1 11 1 11 • • __----- 1 11 1 I1 �� CLIENT PROJECT DETAIL JOB NO. DATE CHECKED CHECKED BY COMPUTEDBY DATE PAGE NO. rnnl . Date of Issuance: Proceed Order No.5 Terminal Reservoir No. 3 of San Juan 05 May 2005. Thursday 0 Pacific Contractors, Inc, JN 10�103242 — -- — ------ You are directed to proceed promptly with the following change(s): Ciescnpron Effective Date: Modify the completion acceptance date of the contract to allow for an addifiona! twelve (10) working days Based ona5day work week, this will bean equivalent Of fourteen (14) calendar days This will bang the allowed contract completion date from 09 Sep 2006 to 23 September 2006 This a non -compensable extension of the contract to allow for delays of saturated soil caused by nclemen! weather I This reflects att delays through 28 Apr 2005 Attachments Request for additional time dated 28 Mar 2005 Method of determining change in Contract Price Unit Prices Lump Sum X Other Agreed increase sn Contract Price: 10 g 9rLe d c L11a m I NONE _L _ If the 617awfe ifivolves an Increase, the estimated arnoutil is riot to ho VKCeeded without further rulthrolizatroli, Prepared by Recommended Approved by Bill Seitz, Corisiructon Amy Method of determining Change in Contract Times Contractors records X Engineer's records Other 02 Aum _?006_ Onginal Date for Completion 14 Extenson of Calendar days this Drocecu croe, 38 Exiensiori of Calendar days loprove:u Zo nate _23 Sep OQ6 Revised Date for Completion _L ManaVqt—RUF Consulting U—A Manager. San Juan Capistrano of Public Works, San Juan Capistrano On May 2005 We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree if hi s order is approved, that we vv;II provide all equipment furnish all matenais, except as may otherwise be noted above, and perform all services necessary for the work above specifed and will accept as full payment :herefore the prices shown above By executing this proceed order, and subsequent change order, we the contractor agree to waive any right to addi2onai compensation arising out of work included in this proceed order, including without limitation. any claims relating to any cumulative effect of the proceed orders delays 'productivity mpact or interruption Accepted "L,,,t,,.r-,..., -Di A zst . 7-- te, /Zl'0 -5 Inc 0 1-1 GATEWAY PACIFIC CONTRACTORS, INC. L L5 Ir `--,f April 11, 2005 Mr. Bill Seitz R—DF Curlsulting 14725 Alton Parkway Irvine, CA 92618 RE: City of San Juan Capistrano Terminal Reservoir No. 3 Wet Soil Delay Due to inclement weather conditions, Gateway Pacific was unable to perform work on ten scheduled working days. This request covers cumulative wet soil delays for March. In accordance with Section 7 of the Construction Contract, and Article 12.02 of the General Conditions, we request 10 scheduled working days be granted to extend the time for successful completion of this project. This will be a non - compensatory extension of time. This will move the final completion date from September 9, 2006 to September 24, 2006. P!eese feel free to oontact as if you should hove ary questic.. Sincerely, 1 a Jay 1 -tall Project Manager cc: File, Gary A. Bechtel, Tim Brown 8056 Freeport Boulevard, Sacramento, CalltorMa 95832-9716 • (916) 665-4100 • (916) 665-4119 FAX 0 PW Lr9NLiUL'1"ING Date of Issuance: 01 Jul 2005 Friday is Proceed Order Noll Terminal Reservoir No. 3., # r Gateway Pacific contractors. Inc. A '0-103242 Effective Date: You are directed to proceed promptly with the following change(s): Description: Based on recommendation *rcm CDM, install hydrogen dilution blower in the chlorammation building. Attachments: Proposed Cost adjustment from GPC dated 24 Jun 2005 Email dated 16 Sep 2004 from Steve Speakman re: Hypochlorite Storage Tank Ventilation Method of determining change in Contract Price: Method of detenm ning change in Contract Times- _ Una Prices _Contractor's records X ~ Lurnp Sum Engineer's records Other NIA Other Agreed increase in Contract Price: S525.00 If the change involves an incroaso the eslimated amount is not to he exceeded wit6otrf further authoriza8on- No increase in Contract Time: r' Prepared by j - `� - 05 Jul 2005 Bili Seitz i(retruetrcul RAarrvtger, RBF Cons thing recommended. ?'elerSa• d�. roject Manager, Sar: Juan Capistrano Approved by t ------- Airy Amirani .Director of Public Works_ San J.ian Capistrano We, the undersigned contractor, have given careful consideration to the chance proposed and hereby agree if this order is approved, that we will provide all equipment. furnish all materials. except as may otherwise be noted above, and perform all services necessary for the work above specified. and will accept as fu:I payment therefore the prices shown above. By executing this proceed order_ and subsequent change order, we the contractor agree to waive any right to additional compensation arising out of work included in this proceed order, including without limitationany ctainns relating to any cumulative effect of the proceed orders_ delays. productivity impact or interruption. Accepted Gary A. _ - _i.,.t'.ss" , J(:-"? _. 4 .:'t;;:.': .. ?•:.Cit •'a G3w inc lJ June 24, 2005 U 0 GATEWAY PACIFIC CONTRACTORS, INC. Mn Bill Seitz RBF Consulting 14725 Alton Parkway Irvine, CA 92618 p ECE0ME D JUN 2 7 2005 RBF CONSULTING CONSTRUCTION MAWFMFNT RE: City of San Juan Capistrano Terminal Reservoir No. 3 PCO #6 — Hydrogen Dilution Blower ftC&QED JUN 2 7 ?005 ��nNG Attached please find backup for the costs associated with PCO #6 — Hydrogen Dilution Blower. The total cost to the project is $525.00. Following your review, please process a change order to Gateway Pacific. If any further questions arise, please contact me. Sincerely, Ja all Project Manager cc: File, Gary Bechtel, Tim Brown 8065 Fneport Boula rd, Sacramento, Califomla 99932-8719 • (919) 9664190 • (919) 9664119 FAX 0 0 Tenriinal Reservoir No. 3 City of San Juan Capistrano PCO No. 6 Description of Work: Hydrogen Dilution Blower two 1] L", Proceed Order No.7 Terminal Reservoir No. 3 ICity of San Juan Cap. Gateway Pacific Contractors. Inc. JN10-1032421 Date of Issuance: 01 Sep 2005. Thursday You are directed to proceed promptly with the following changers): Effective Date: Description. Based on plans signed by John Newby of CDM dated 30 Aug 2005, Contractor is directed to complete work. Gateway Pacific is to submit a separate request for additional days for time separately. Attachments: 2005 08 30 Caisson and Raker Drawing CDM 30 Aug 2005 2005 09 01 Calex Breakdown 2005 09 01 GPC Breakdown Method of determining change in Contract Rice: Method of determining change in Contract Times: Unit Prices X Lump Sum - not to exceed Other Agreed increase in Contract Price: S 100.531 28 If the change involves an increase, the estimated amount is not to be exceeded without Further auh-onzatrnn. Contractor's records Engineer's records x Other (to be supplied) Prepared by: —1 fd -ys/ 01 Sep 2005 Bil(-TSellz, Co [r Manager. onsuiting . Recommended: / qf /11q_ er S�lga pr=M M San Capistrano Approved by: Amy AAmiram, Director of Public rks. San Juan Capistrano T We the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this order is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted aboveand perform all services necessary for the work above specified, and will accept as full payment therefore the prices shown above. By executing this proceed order, and subsequent change order, we the contractor agree to waive any right to additional compensation arising out of work Included in this proceed order. including without limitation. any claims relating to any cumulaLve effect of the proceed orders, delays, productivity impact or interruption. Accepted. :2t 4m - ii�d�,A yji -I /1 /0-5 Gary A. Bechtel. J Ce FFresident, Gateway Pacific Contractors, inc. .�@ I0'S' =421120'1 '5__^ CCOi%:20G 09 01 111 11_,17 P"1nfI _i$e,-00J5 I— GATEWAY PACIFIC CONTRACTORS, INC. December 8, 2005 Mr. Bill Seitz RBF Consulting 14725 Alton Parkway Irvine, CA 92618 RE: City of San Juan Capistrano Terminal Reservoir No. 3 PCO #.7 — Raker Installation Dear Mr. Seitz: Per your direction, Gateway Pacific Contractors, Inc. has completed the installation of the additional caissons and rakers. This work was completed in September / October. Please issue a change order for One hundred eighty three thousand seven hundred fifty-five dollars and twenty-three cents, ($ 183,755.23). This work delayed our work by 30 calendar days. Please contact us if you should have any questions regarding this PCO. ,/s. 'ncerely, C._ J II Project Manager cc: File, Gary A. Bechtel, Tim Brown 6665 Freeport Boulevard, Sacramento, CalBorala 06882-0716 • (016) 086-4100 • (016) 665.4119 FAX Terminal Reservoir No. 3 City of San Juan Capistrano PCO No. 8 Description of Work: Installation of Caisson and Raker System Unit Unit Unit TOTAL Description Qty Units Cost Labor Cost Material Cost Equip S/C Supervisor 136 hrs 82.00 11,152.00 11,152.00 Operator 40 hrs 63.95 2,558.00 2,558.00 hrs 0.00 0.00 Road Repair 1 Is 1,500.00 1,500.00 Excavator 5 day 5,000.00 5,000.00 Calex 1 Is 113,468.25 113,468.25 Coat Beams Laborer 64 hr 48.93 3,131.52 3,131.52 Carboline 16 gal 52.35 837.60 837.60 Rollers 1 Is 97.85 97.85 97.85 Encase Beams w/ Rock Operator 20 hr 1 63.95 1,279.00 1.279.00 314" Crushed Rock ###f to 26.52 27,846.00 27,846.00 Backhoe 3 dy 265.00 795.00 795.00 Subtotals 18,120.52 28,781.45 5,795.00 114,968.25 167,665.22 Sales Tax @ 7.75% 2,230.56 449.11 2,679.67 Subtotals 18,120.52 31,012.01 6,244.11 114,968.25 170 344.89 Markup Labor @ 20% 3,624.10 3,624.10 Markup - Mat'Is @ 15% 1 3,101.20 3,101.20 Markup - Equip @ 15% 936.62 936.62 Markup Subs @ 5% 5,748.41 5,748.41 Subtotal 21,744.621 34,113.21 7,180.73 120,716.66 183,755.23 TOTAL 183,755.23 r Terminal Reservoir No. 3 City of San Juan Capistrano PCO No. 8 Description of Work: Installation of Caisson and Raker System 0 Unit Unit Unit TOTAL Description qty Units Cost Labor Cost Material Cost Equip SIC Supervisor 80 hrs 82.00 6,560.00 6,560.00 Operator 40 hrs 63.95 2,558.00 2,558.00 Gradesetter 40 hrs 63.95 2,558.00 2,558.00 hrs 0.00 0.00 hrs 0.00 0.00 Road Repair 1 Is 1,500.00 1,500.00 Excavator 5 day 5,625.00 5,625.00 Calex 1 Is 131,500.00 131,500.00 Subtotals 11,676.00 0.00 5,625.00 133,000.00 150,301.00 Sales Tax @ 7.75% 0,001 435.94 435.94 Subtotals 11,676001 0.00 6,060.94 133,000.00 150,736.94 Markup Labor @ 20% 2,335.201 2,335.20 Markup - Mafls @ 15% 0.00 0.00 Markup - Equip @ 15% 909.14 909.14 Markup Subs @ 5% 6,650.00 6,650.00 Subtotal 14,011.20 0.00 6,970.08 139,650.00 160,631.28 TOTAL 160,631.28 e�ALE,x -OP4 :5 1pts F-04- 70.e -rC:7RInit*L Re:5CRVO,vz )VX5 07- Of, A -4 , A —A x l A " 11,3/4.4 0 =oA-70_5 0 N'T 5 CLIENT/,,qql��� JOB NO. ��'9 COMPUTED BY / cm PROJECT �f1�l•'�N bV SFR- a`r%�?7 DATE CHECKED DATE of/14/O�j DETAIL R-D'I�ry4- G /((jN S CHECKED BY PAGE NO. I/ Fb04- I ii M coh NCdloff (jf ,-1 46440-1- tee% , I, (%It%i1v ve"I T plMc-rcSioH> ee-iorc--r0 4. M6 -XI MUM L71G1(LF ''IiT i/ ri �i°wllGrt F.�'6'�'� TO riolG GSI Ssr9+.l r�g6-M 5fj Zg�_�, 5/'. µ6m1MUH Oj% 5!- 1 -to /t. /-wi.- �,dtql NW w, r,a N, yf Aw5 GY/�Tlt IGS ws�,25 tor- o2N1 N(q .fo (�gicA Ve.gl rz C.eq; AW." (�, �Ny �1��D Me�i�lca.rfto^IS f� co+�N�cfil� v�if�ll� Suc.N �-s /h717iNu SHIM P�llis sHs L K� 'F�/�✓��v6Nn 5( weiw Coltn� �... N CrfG^t�(1�v oj'iTVhG '�rag1N��2 rot- yf�/VIOW dR!2 Arrrl, �.6L \YOF CA1.�e/ CDM 5 C CLIENT USS l��i Y(YLD,Nd JOBNO. �IO�-%FAO?gj COMPUTED BY /TW PROJECT�1,,..�I DATE CHECKED DATE DETAIL �`f'Y�'�� M CHECKED BY PAGE NO. W�opD,�h�M6ECi ( f ti* l FIE a� h %VAI � C/ 9 ^ Irox l M1 -i'0- 50-4-4 G� )?. F- 7- 17,'W71- Iq a S yolAli�/� (OM41DN TOIL T^ 13 CDM 5 CLIENT JOB NO. COMPUTED BV I� m PROJECT DATECHECKED DATE q 1'V�J DETAIL CHECKED BY PAGE NO. ct, w Y-wv ff j qe� 4 Ao-i ,so 4 u.yy ��i�r'Wxw" 44-m (-&w t /c-flofy v(j'(QI, )N CDM5 W H g a z Z K ¢ W m m w w &J n »aa cr w J 0 U) z 0 U LU z z 0 or w Y Q CL 0 H I I �I I , _ a c m ry n n n. � r _ z Y m o o " o w ryy Y x € b € S o E f u E 0 v 'm .. __. • _. d --- a -- - --- I s. m a m I f E I I E_t m I I m g Y L < N F r .- I � e I c _ _ w I y w u Yl u S E Eo g 3 a a S m q n V N U I 0 0 GATEWAY PACIFIC CONTRACTORS, INC. December 8, 2005 Mr. Bill Seitz RBF Consulting 14725 Alton Parkway Irvine, CA 92618 RE: City of San Juan Capistrano Terminal Reservoir No. 3 PCO # 8— Storm Drain Revision Dear Mr. Seitz: Per your direction, Gateway Pacific Contractors, Inc. has completed the cost for the Storm drain revision plan, dated July 5, 2005. 1 have prepared additional cost analysis using FtBPE pipe instead of the designated C900 pipe. s�a-3S Gateway will install the additional four hundred lineal feet of 18" sdr35 and upgrade the designed 14" sdr 35 drain line for the extra cost of Fifty-five thousand one hundred ninety dollars and eighty-four cents, ($ 55,190.84). Gateway is also requesting a contract time extention of 14 days for this work. Please contact us if you should have any questions regarding this PCO. incerel J y Hall Project Manager cc: File, Gary A. Bechtel, Tim Brown 8055 Freeport Boulevard, Sacramento, Calltomie 86852.9716 • (916) 66544100 -(918) 868.4119 FAX 0 Terminal Reservoir No. 3 City of San Juan Capistrano PCO No. 7 Descri tion of Work: Storm Drain Revision 18" SDR 35 1* Unit Unit Unit TOTAL Description Qty Units Cost labor Cost Material Cost Equip S/C Laborer (2 ea 120 hrs 46.95 5,634.00 5,634.00 Operator 64 hrs 64.90 4,153.60 4,153.50 0.00 0.00 Excavator Rental 2 wk 2,500.00 5,000.00 5,000.00 Sharing Rental 1 wk 2,000.00 2,000.00 1 2,000.00 0.00 0.00 Concrete Collar 3 cy 200.00 600.00 600.00 0.00 48" Manhole 1 ea 2,650.00 2,650.00 2,650.00 \ 0.00 24" PVC SOR-35 80 If 36.96 2,958A0 2,958.40 18" PVC SDR 35 820 If 20.95 17,179.00 17,179.00 18" 45 de bend 3 ea 437.00 1,311.00 1,311.00 18" 22.5 d bend 9 ea 437.00 3,933.00 3,933.00 18"11.25 deg bend - 1 ea 437.00 437.00 437.00 18" Wye 1 as 985.00 985.00 985.00 18" x 8" W e 2 ea 985.00 1,970.00 1,970.00 22" x 12" Wall Spool 2 ea 485.00 970.00 970.00 0.00 14" PVC sdr35 -500 If - 11.00 -5,500.00 -5,500.00 14"45 de bend sdr35 -3 ea 171.00 -513.00 -513.00 14" 22.5 dLg bend sdr35 -6 ea 171.00 -1,026.00 -1,026.00 14" W e sdr35 -1 as 211.00 -211.00 -211.00 14"x 8" W e sdr 35 -2 ea 211.00 -422.00 -422.00 18" x 12" Wall S 001 -1 ea 292.00 -292.00 -292.00 Air Gap Modifications 1 Is 1,126.80 1,126.80 750.00 750.00 750.00 750.00 2,626.60 0.00 0.00 0.00 0.00 0.00 Subtotals 10,914.40 25,779.40 77750.00 0.00 44,443.80 Sales Tax @ 7,75% 1,997.90 600.63 2,598.53 Subtotals 10,914.40 27,777.30 8,350.63 0.00 47,042.33 MarkuD Labor 0 20% 2,182.88 - 2,182.88 Marku -MaVls @ 15% 4,166.60 4,166.60 Marku -E ui 19% 1,252.59 1,252.59 Markup Subs 5% - 0.00 0.00 Subtotal 13,097.28 31,943.90 9,603.22 0.00 54,644.40 Bond 1% 10,855.61 0.00 546.44 TOTAL 1 55,190.84 = o Z V ewz awl EZ w 'mpam3a F f� a U 1 ti9$ O OwQQW Z zo / 1 e, oww /nz 1 o a n 14, In V N b m N N I C n m I Z 3 z wN o gch / mZ i N.zow m r I N iu 1 U MSU VI n,nzn OWry T w a I 1`ry M� ¢O ZF Finz 1. yV Ozel l� Ir- O I /ryry \ Al 3g . .. i GATEWAY PACIFIC CONTRACTORS, Inc. January 09, 2005 Mr. Bill Seitz RBF Consulting 14725 Alton Parkway Irvine. CA 92618 RE: City of San Juan Capistrano Terminal Reservoir No. 3 2005 Rain Delays, April to December Due to inclement weather conditions, Gateway Pacific was unable to perform work on seven (7) scheduled working days (calendar equivalent of 9.6 days). These days were previously agreed upon during the weekly progress meetings. This request covers all rain delays from April until December of 2005. In accordance with Section 7 of the Construction Contract, and Article 12.02 of the General Conditions, we request 7 scheduled working days be granted to extend the time for successful completion of this project. This will be a non - compensable extension of time. Please contact us if you should have any questions regarding this request. Sincerely, Jay Hall Project Manager cc: File, Gary A. Bechtel, Tim Brown 8055 Freeport Boulevard, Sacramento, California 95832-9716 • (916) 665-4100.(916) 6654119 FAX ATTACHMENT 2