Loading...
04-0921_RBF CONSULTING_D3_Agenda Report• • 9/21/2004 D3 AGENDA REPORT TO: Dave Adams, City Manager FROM: Amy Amirani, Public Works Director SUBJECT: Consideration of a Personal Services Agreement for Construction Management and Inspection Services for the Terminal Reservoir No. 3 Project (RBF Consulting, Inc) (CIP# 753) RECOMMENDATION: By motion, approve a Personal Services Agreement with RBF Consulting, Inc. in the amount of $1,045,920 for Construction Management and Inspection Services for the Terminal Reservoir No. 3 Project. SITUATION: A. Summary and Recommendation This project will replace the existing Terminal Reservoir No. 2, which has sustained structural damage due to differential settlement. The new facility will be a six (6) million gallon pre -stressed concrete reservoir, referred to as Terminal Reservoir No. 3. Construction management and inspection services are required for the project. The City issued a Request for Proposal (RFP) for these services and found RBF Consulting, Inc. (RBF) to be the best qualified firm. RBF submitted a cost proposal of $1,045,920 for construction management and inspection services. Staff has reviewed this cost proposal and finds it to be reasonable for the scope of work. Also, construction management and inspection services typically fall within 6 to 10 percent of the project cost depending on the project scope and complexity. RBF's cost proposal is within this threshold, and staff, therefore, recommends that a Personal Services Agreement (Attachment 1) with RBF for construction management and inspection services be approved for a total cost of $1,045,920. B. Background The City owns two existing reservoirs located side by side in the Mission Hills Area: Terminal Reservoir No. 1 (T1) and Terminal Reservoir No. 2 (T2). T1 is a two (2) million gallon (MG) reservoir that is no longer in operation and T2 is a ten (10) MG reservoir that is currently in use. In the early spring of 1997, leaking was discovered in Agenda Report Paae 2 9 September 21, 2004 T2. Investigation and remedial repairs were completed in the spring and summer of 1997. T2 did not show any sign of leaking until February 2001 when a crack was noted in the floor of the reservoir during inspection. The crack was repaired immediately. However, since this repair, T2 has experienced continued settlement. Based on these findings, staff issued a Request for Proposal (RFP) for design services and obtained the services of Camp Dresser and McKee, Inc. (CDM) to provide engineering design services for the replacement of T2. The scope of work included geotechnical and structural testing and analysis, and preparation of the design and contract documents for a new replacement facility, referred to as Terminal Reservoir No. 3 (T3). T3 will be a new six (6) MG pre -stressed concrete reservoir to be constructed on the site presently occupied by T1. This will allow for continued use of T2 during the construction period, avoiding serious disruptions to domestic water service. T1 will be demolished to allow for construction of T3, and once T3 is completed and in service, T2 will be taken out of operation and abandoned in place. On July 20, 2004, the City Council approved the project plans and specifications and authorized the City Clerk to solicit bids for the project. Bids were opened on August 31, 2004, and the lowest responsive and responsible bid was submitted by Gateway Pacific Contractors, Inc for a total of $10,527,276. The construction contract is scheduled to be presented to the City Council for consideration at the September 21, 2004 Council meeting. The Notice to Proceed for construction of the project is scheduled to be issued in early October 2004. Substantial completion of the project is scheduled for early September 2006. Construction management and inspection services are required for the project. These services include providing constructability reviews of the plans and specifications; providing technical support during the bidding period; reviewing the contractor's construction schedule; daily monitoring of the contractor's work progress to ensure compliance with the approved construction schedule; administering the construction contract; reviewing progress payment requests, certified payroll reports and record drawing updates; reviewing and negotiating construction change orders; administering construction progress meetings; coordinating the distribution of submittals, shop drawings and RFI's to ensure a timely response; preparing monthly progress reports; monitoring the work site to ensure compliance with NPDES requirements; providing geotechnical, structural, mechanical, electrical, environmental and quality control inspections; and providing construction surveying and staking services. On August 5, 2003, the City issued an RFP to six engineering and consulting firms for construction management and inspection services for the project. These services not only include typical contract administration and construction inspection tasks, but also design constructability reviews and contract bidding support. Given the complex nature of the project, staff included these supplemental tasks to ensure the most accurate and • • Agenda Report Paqe 3 September 21, 2004 cost effective design possible and minimize the potential for costly change orders during construction. At the time the RFP was issued the design was in its preliminary stages and staff anticipated the possibility that major elements of the work, specifically, the geotechnical mitigation measures, would vary in scope once the design was finalized. For this reason, staff decided that the Construction Management and Inspection services would be awarded in 2 phases. Phase 1 would be the design constructability reviews and contract bidding support, and Phase 2 would be the construction related services. Depending upon the performance of the firm selected for Phase 1, staff would either award Phase 2 to the firm selected for Phase 1, or start negotiations with the firm determined to be second best during the proposal evaluations. As mentioned earlier in the report, six firms were invited to propose on the project. Of the six firms, three submitted proposals for review and evaluation: Boyle Engineering Corporation, RBF Consulting Inc., and Tetra Tech, Inc. Fee proposals were also submitted as follows: Firm Phase 1 Fee Phase 2 Fee Tetra Tech Inc. $ 40,880 $1,387,671 RBF Consulting, Inc. $ 44,366 $ 837,814 Boyle Engineering Corp$ 45,450 $ 712,755 Staff reviewed and evaluated the proposals and found RBF Consulting, Inc. (RBF) to be the best qualified firm to perform the required construction management and inspection services for the project. RBF showed extensive experience in reservoirs of the similar size and construction, namely the recently constructed five (5) MG pre -stressed concrete reservoir for the Laguna Beach County Water District and the four (4) MG pre- stressed concrete reservoir for the City of Sierra Madre. RBF also showed a comprehensive understanding of the geotechnical issues associated with the project, the required geotechnical testing and inspection, and environmental monitoring coverage. For these reasons, RBF was selected to provide the Phase 1 services. These services were obtained under the City's Master Plan Check, Engineering and Architectural Services agreement with RBF. Since the award of the Phase 1 services, RBF has shown exceptional, responsive service and has been a valuable part of the project team. They have worked closely with staff and CDM to formulate the most cost effective design. Staff is more than satisfied with RBF's performance and is recommending they be awarded the Phase 2 services. It must be noted, however, that as the design was being finalized, slope stabilization measures required to stabilize existing landslides on both sides of the project have become more complex. In turn, these more complex slope stabilization measures have increased geotechnical testing and inspection requirements. Also, environmental mitigation and monitoring requirements have increased. These changes have resulted Agenda Report • September 21, 2004 Paqe 4 in an increase to the geotechnical and environmental aspects of RBF's original fee proposal for the Phase 2 services. Staff has negotiated a revised fee of $1,045,920. A comparison of RBF's original and revised Phase 2 services fee is shown below: Staff recommends approval of a Personal Services Agreement with RBF. COMMISSION/BOARD REVIEW AND RECOMMENDATIONS: The Water Advisory Commission has reviewed this item at their June 22, 2004, meeting. The Commission recommended approval of the Personal Services Agreement with RBF for Construction Management and Inspection Services. The Planning Commission reviewed the Domestic Water Master Plan at their April 27, 2004, meeting and determined that the master planned water facilities, including Terminal Reservoir No. 3, are consistent with the City's General Plan. Therefore, as required by the Governmental Code Section 65401, this project has been deemed consistent with the General Plan. FINANCIAL CONSIDERATIONS: The City's Domestic Water Master Plan, which was adopted in May 2004, includes a total of $15 Million for the Terminal Reservoir No. 3 Project under CIP# 753. Of this amount, $342,000 was allocated for FY 2003/2004 expenditures and $14,658,000 is allocated for projected expenditures from FY 2004/2005 through completion of the project. The amount of $14,658,000 is identified in the 7 -Year Capital Improvement Budget adopted in June 2004. RBF's Personal Services Agreement for a total of $1,045,920 is within the budgeted amount of $14,658,000. This amount will be financed through adopted rate increases and bonds issued in early September 2004. Construction Geotechnical Environmental Total Management / Testing and Monitoring Structural, Inspection Electrical, Mechanical Ins ection RBF (Original $ 668,314 $ 173,000 $ 32,500 $ 873,814 Fee RBF (Revised $ 652,752 $ 331,353 $ 61,815 $1,045,920 Fee Staff recommends approval of a Personal Services Agreement with RBF. COMMISSION/BOARD REVIEW AND RECOMMENDATIONS: The Water Advisory Commission has reviewed this item at their June 22, 2004, meeting. The Commission recommended approval of the Personal Services Agreement with RBF for Construction Management and Inspection Services. The Planning Commission reviewed the Domestic Water Master Plan at their April 27, 2004, meeting and determined that the master planned water facilities, including Terminal Reservoir No. 3, are consistent with the City's General Plan. Therefore, as required by the Governmental Code Section 65401, this project has been deemed consistent with the General Plan. FINANCIAL CONSIDERATIONS: The City's Domestic Water Master Plan, which was adopted in May 2004, includes a total of $15 Million for the Terminal Reservoir No. 3 Project under CIP# 753. Of this amount, $342,000 was allocated for FY 2003/2004 expenditures and $14,658,000 is allocated for projected expenditures from FY 2004/2005 through completion of the project. The amount of $14,658,000 is identified in the 7 -Year Capital Improvement Budget adopted in June 2004. RBF's Personal Services Agreement for a total of $1,045,920 is within the budgeted amount of $14,658,000. This amount will be financed through adopted rate increases and bonds issued in early September 2004. 9 Agenda Report Page 5 NOTIFICATION: RBF Consulting, Inc. RECOMMENDATION: September 21, 2004 By motion, approve a Personal Services Agreement with RBF Consulting, Inc. in the amount of $1,045,920 for Construction Management and Inspection Services for the Terminal Reservoir No. 3 Project. Respectfully submitted, Amy Amirani Public Works Director AA/PS:mp Attachments: 1. Personal Services Agreement 2. Location Map Prepared by, 0 9 PERSONAL SERVICES AGREEMENT THIS AGREEMENT is made and entered into this _ day of 2004, by and between the City of San Juan Capistrano (hereinafter referred to as the "City") and RBF CONSULTING, (hereinafter referred to as "Consultant"). RECITALS: WHEREAS, City desires to retain the services of Consultant regarding the City's proposal to provide construction management services for the Terminal Reservoir No. 2 Replacement Project; and WHEREAS, Consultant is qualified by virtue of experience, training, education and expertise to accomplish such services. NOW, THEREFORE, City and Consultant mutually agree as follows: Section 1. Scope of Work. The scope of work to be performed by Consultant shall consist of those tasks as set forth in Exhibit 'A" attached and incorporated herein by reference. Consultant warrants that all of its services shall be performed in a competent, professional and satisfactory manner and in accordance with the prevalent standards of its profession. Section 2. Term. This Agreement shall commence on the effective date of this Agreement and services required hereunder shall be completed no later than December 31, 2006. Section 3. Compensation. 3.1 Amount. Total compensation for the scope of services for this Project shall be for a lump sum of One Million Forty -Five Thousand Nine Hundred Twenty Dollars ($1,045,920) as set forth in Exhibit'A," attached and incorporated herein by reference. 3.2 Rate Schedule. The services shall be billed to the City as set forth in Exhibit "A," attached and 1 ATTACHMENT incorporated herein by reference. Included within the compensation are all the Consultant's ordinary office and overhead expenses incurred by it, its agents and employees, including meetings with the City representatives and incidental costs to perform the stipulated services. Submittals shall be in accordance with Consultant's proposal. 3.3 Method of Payment. Notwithstanding the payment terms outlined in Exhibit "A", Consultant shall submit monthly invoices based on total services, which have been satisfactorily completed and specifying a percentage of projected completion for approval by the City. The City will pay monthly progress payments based on approved invoices in accordance with this Section. For extra work not part of this Agreement, a written authorization from City is required prior to Consultant undertaking any extra work. 3.4 Records of Expenses. Consultant shall keep complete and accurate records of all costs and expenses incidental to services covered by this Agreement. These records will be made available at reasonable times to City. Section 4. Independent Contractor. It is agreed that Consultant shall act and be an independent contractor and not an agent or employee of City, and shall obtain no rights to any benefits which accrue to City's employees. Section 5. Limitations Upon Subcontracting and Assignment. The experience, knowledge, capability and reputation of Consultant, its principals and employees were a substantial inducement for City to enter into this Agreement. Consultant shall not contract with any other entity to perform the services required without written approval of the City. This Agreement may not be assigned, voluntarily or by operation of law, without the prior written approval of the City. If Consultant is permitted to subcontract any part of this Agreement by City, Consultant shall be responsible to City for the acts and omissions of its subcontractor as it is for persons directly employed. Nothing contained in this Agreement shall create any contractual relationships between any subcontractor and City. All persons engaged in the -work will be considered employees of Consultant. City will deal directly with and will make all payments to Consultant. Section 6. Changes to Scope of Work. 2 In the event of a change in the Scope of Work provided for in the contract documents as requested by the City, the Parties hereto shall execute an addendum to this Agreement setting forth with particularity all terms of the new agreement, including but not limited to any additional Consultant's fees. Section 7. Familiarity with Work and Construction Site. By executing this Agreement, Consultant warrants that: (1) it has investigated the work to be performed; (2) it has investigated the proposed construction site, including the location of all utilities, and is aware of all conditions there; and (3) it understands the facilities, difficulties and restrictions of the work under this Agreement. Should Consultant discover any latent or unknown conditions materially differing from those inherent in the work or as represented by City, it shall immediately inform City of this and shall not proceed with further work under this Agreement until written instructions are received from the City. Section 8. Time of Essence. Time is of the essence in the performance of this Agreement. Consultant shall complete the Scope of Services as set forth in the schedule included in Exhibit "A", attached and incorporated herein by reference. Section 9. Compliance with Law. Consultant shall comply with all applicable laws, ordinances, codes and regulations of federal, state and local government. Section 10. Conflicts of Interest. Consultant covenants that it presently has no interest and shall not acquire any interest, direct or indirect, which would conflict in any manner or degree with the performance of the services contemplated by this Agreement. No person having such interest shall be employed by or associated with Consultant. Section 11. Copies of Work Product. At the completion of the contract period, Consultant shall have delivered to City at least one (1) copy of any final reports and architectural drawings containing Consultant's findings, conclusions, and recommendations with any support documentation. All reports submitted to the City shall be in reproducible format. All services to be rendered hereunder shall be subject to the direction and approval of the City. 3 0 0 Section 12. Ownership of Documents. All reports, information, data and exhibits prepared or assembled by Consultant in connection with the performance of its services pursuant to this Agreement are confidential to the extent permitted by law, and Consultant agrees that they shall not be made available to any individual or organization without prior written consent of the City. All such reports, information, data, and exhibits shall be the property of the City and shall be delivered to the City upon demand without additional costs or expense to the City. The City acknowledges such documents are instruments of Consultant's professional services. Section 13. Indemnity. Consultant agrees to protect, and hold harmless City, its elected and appointed officials and employees from any and all liabilities, expenses or damages of any nature, including reasonable attorneys' fees, for injury or death of any person or damage to property or interference with use of property resulting from errors and omissions committed by Consultant arising from the negligent acts of Consultant, its agents, employees and subcontractors in carrying out its obligations under this Agreement. Section 14. Insurance. Insurance required herein shall be valid for a minimum of one year, or term of contract, whichever is longer, and it shall be provided by Admitted Insurers in good standing with the State of California and having a minimum Best's Guide Rating of A - Class VII or better. 14.1 Comprehensive General Liability. Throughout the term of this Agreement, Consultant shall maintain in full force and effect Comprehensive General Liability coverage in the following minimum amounts: $500,000 property damage; $500,000 injury to one person/any one occurrence/not limited to contractual period; $1,000,000 injury to more than one person/any one occurrence/not limited to contractual period. 14.2 Comprehensive Automobile Liability. 12 • Throughout the term of this Agreement, Consultant shall maintain in full force and effect Comprehensive Automobile Liability coverage, including owned, hired and non - owned vehicles in the following minimum amounts: $500,000 property damage; $500,000 injury to one person/any one occurrence/not limited to contractual period; $1,000,000 injury to more than one person/any one occurrence/not limited to contractual period 14.3 Worker's Compensation. If Consultant intends to employ employees to perform services under this Agreement, Consultant shall obtain and maintain, during the term of this Agreement, Worker's Compensation Employer's Liability Insurance in the statutory amount as required by state law. 14.4 Proof of Insurance Requirements/Endorsement. Prior to beginning any work under this Agreement, Consultant shall submit the insurance certificates, including the deductible or self -retention amount, and an additional insured endorsement to the Consultant's general liability and umbrella liability policies to the City Clerk's office for certification that the insurance requirements of this Agreement have been satisfied. 14.5 Errors and Omissions Coverage Throughout the term of this Agreement, Consultant shall maintain Errors and Omissions Coverage (professional liability coverage) in an amount of not less than One Million Dollars ($1,000,000). Prior to beginning any work under this Agreement, Consultant shall submit an insurance certificate to the Clerk of the Board's office for certification that the insurance requirements of this Agreement have been satisfied. 14.6 Notice of Cancellation/Termination of Insurance. The above policy/policies shall not terminate, nor shall they be cancelled, nor the coverages reduced, until after thirty (30) days' written notice is given to City, except that ten (10) days' notice shall be given if there is a cancellation due to failure to pay a premium. 14.7 Terms of Compensation. 5 9 Consultant shall not receive any compensation until all insurance provisions have been satisfied. 14.8 Notice to Proceed. Consultant shall not proceed with any work under this Agreement until the City has issued a written "Notice to Proceed" verifying that Consultant has complied with all insurance requirements of this Agreement. Section 15. Termination. City and Consultant shall have the right to terminate this Agreement without cause by giving thirty (30) days' advance written notice of termination to the other party In addition, this Agreement may be terminated for cause by providing ten (10) days' notice to the other party of a material breach of contract. If the other party does not cure the breach of contract, then the agreement may be terminated subsequent to the ten (10) day cure period. Section 16. Notice. All notices shall be personally delivered or mailed to the below listed addresses, or to such other addresses as may be designated by written notice. These addresses shall be used for delivery of service of process: To City: City of San Juan Capistrano 32400 Paseo Adelanto San Juan Capistrano, CA 92675 Attn: Public Works Director To Consultant: Jerome Ruddins RBF Consulting 14725 Alton Parkway Irvine, CA 92618-2027 Section 17. Attorneys' Fees. If any action at law or in equity is necessary to enforce or interpret the terms of this Agreement, the prevailing party shall be entitled to reasonable attorneys' fees, costs and necessary disbursements in addition to any other relief to which he may be entitled. Section 18. Dispute Resolution. In the event of a dispute arising between the parties regarding performance or interpretation of this Agreement, the dispute shall be resolved by binding arbitration under the auspices of the Judicial Arbitration and Mediation Service ("JAMS"). 0 Section 19. Entire Agreement. This Agreement constitutes the entire understanding and agreement between the parties and supersedes all previous negotiations between them pertaining to the subject matter thereof. IN WITNESS WHEREOF, the parties hereto have executed this Agreement. ATTEST: Margaret R. Monahan, City Clerk APPROVED AS TO FORM: gv��z John R. S w, City Attorney 7 CITY OF SAN JUAN CAPISTRANO 0 Joe Soto, Mayor CONSULTANT By(:?vpl-�..e 0 June 2, 2004 Mr. Peter Salgado, PE Associate Engineer Public Works Department CITY OF SAN JUAN CAPISTRANO 32450 Paseo Adelanto San Juan Capistrano, CA 92675 WF � CONSULTING 0 Subject: Proposal to Provide Construction Management Services, Phase Two -Construction Terminal Reservoir No. 2 Replacement Project Dear Mr. Salgado: Over the last 9 months it has been our pleasure to provide the City of San Juan Capistrano with professional construction management services, more specifically constructability review services during the design phase of this important project. RBF Consulting (RBF) is pleased to present our Proposal for phase two, construction management services during construction, to the City of San Juan Capistrano for the Terminal Reservoir No. 2 Replacement Project. The project consists of the replacement of an existing 2 MG reservoir with a new 6 MG cast -in-place, pre- stressed concrete reservior, the construction of two permanent shoring walls for slope stabilization and tank construction, on site chloramination facility, and site improvements. Based upon the site constraints and the amount of site stabilization that is required we anticipate that the project will require 23 months to complete. We have enclosed a work plan schedule in our proposal that identifies the major construction operations for your review. RBF proposes to provide specific services that will include: Project Management, Construction Management, Contract Administration, Construction Inspection, Resident Engineering, Survey Control, Soils/Material Testing, Environmental Support, Electrical Engineering/SCADA Support, Claims Avoidance Support, and Scheduling Support. Byselecting the RBF Team forprofessionalservices, the City of San Juan Capistrano will benefitfrom a local, highly qualified firm experienced in providing cost-effective solutions to municipalities. Specific benefits derived from selecting the RBF Team include: ✓ A Team with extensive experience in cast -in-place, pre -stressed concrete reservoirs; and ✓ A Team with members currently working on the project during the design development phase and which is ready to begin work immediately upon notice to proceed from the City and which will maintain the level of effort required to meet the proposed schedule; and ✓ A Team which includes Registered Construction Managers and Inspectors; Registered Engineers; Structural Engineers, Construction Contractors, Environmental Engineers, Electrical Engineers, Claims Specialists, Licensed Surveyors, ACI and ICBO Certified Testers and Technicians, and which is backed by a firm of over 700 multi -disciplined professional and support personnel; and ✓ A Team with a long-standing history of successfully providing complete construction management and related engineering services to the City of San Juan Capistrano. 1nth- ` _ t1641r R 14725 Alton Parkway, Irvine, CA 92618-2027 • PO. Box 57057, Irvine, CA 92619-7057 • 949.472.3505 • Fax 949.472.8373 Offices located throughout California, Arizona & Nevada • www.RBFcom m.11m--1. ate, 0 Mr. Peter Salgado, PE June 2, 2004 Page 2 0 The following Proposal, which includes all items requested in your RFP (dated August 5, 2003) and your Addendum No. i (dated August 21, 2003), details how the RBF Team will deliver on these commitments and meet the City's goals. RBF Consulting covenants that it presently has no interest and shall not acquire any interest, direct or indirect, which would conflict in any manner or degree with the performance of the services contemplated by this Agreement. No person having such interest shall be employed by or associated with RBF Consulting. As requested in the RFP, upon award of the contract, RBF will comply with the insurance requirements described in the RFP. RBF has reviewed the Agreement attached to the RFP and respectfully makes the following minor modifications to Section 13 on Page 4: Consultant agrees to protect, defend and hold harmless City, its elected and appointed officials and employees from any and all eleims, liabilities, expenses or damages of any nature, including reasonable attorney's fees, for injury or death of any person or damage to property or interference with use of property and for errors and omissions committed by Consultant arising from the negligent acts of Consultant, its agents, employees and subcontractors in carrying out its obligations under this Agreement. RBF has successfully entered into numerous agreements with numerous agencies in the past 60 years and looks forward to doing so, again, with the City of San Juan Capistrano. This proposal remains valid for a period of not less than ninety (90) days from date of submittal. RBF Consulting is an Equal Opportunity Employer and has developed an Affirmative Action Plan for the purpose of achieving equal employment objectives by attaining an employment profile, with respect to race and sex in each job group, which is an approximate reflection of societal availability. Our Project Team looks forward to meeting with you to personally discuss our proposed approach to completing the City of San Juan Capistrano's goals and objectives. We appreciate the opportunity to submit our proposal. Should you have any questions, please contact me at 949.855.3634. Thank you. Sincerely, Jerome A. Ruddins Vice President Construction Management 11.WtlN0105242Um... Wmp mMEVISCD June 2+_gW ,erktar 2W4 M@.am Terminal Reservoir No. 2 ReplacemeAftoject Proposal for Construction Management Se es PROJECT UNDERSTANDING: The City of San Juan Capistrano (City) is requesting proposals from qualified engineering and consulting firms to provide complete Construction Management (CM) and constructability review services for the Terminal Reservoir No. 2 Replacement Project (Project). Most importantly the City is requesting a professional team to work hand-in-hand on this project. We have assembled a team of Constructors, Engineers, Construction Managers, Construction Claim Experts, Geotechnical Experts, to complement the City's management team during this important phase of the project. We look forward to the opportunity to continuing our relationship with the City on this important project. Based upon our understanding of the project, this effort will focus on a two-phase approach to the project. Our proposal reflects information presented in the 90% plans that encompasses a 6 MG tank with extensive tie -back systems. The first phase, which is nearing completion, is to provide a qualified Technical Review/ Constructability Review of the 50, 90 and 100% PSE, with our team, to focus on providing value to the process. Once again our team includes discipline leaders that are currently working on the evaluation of the Preliminary Design Report. Their extensive design and construction experience will add value to the project. As we see the project, early identification of key issues such as remedial grading, staging of excavated materials, shoring and tieback systems will assist in a cost effective project for the City. Our team will bring extensive experience to the project during this phase based upon our expertise in grading, cost estimating, tank construction, and landslide remediation. The Project consists of the replacement of an existing 2 MG reservoir with a new 6 MG cast -in-place, pre -stressed, concrete facility. The City owns two existing reservoirs, located side by side in the Mission Hills Area: Terminal Reservoir No. 1 (Tl) and Terminal Reservoir No. 2 (T2). Tl is a 2 MG cast -in-place, rectangular, partially buried reservoir, that is on standby status. T2 is a 10 MG reservoir that is currently in service, but, it has sustained damage due to differential settlement. This project will replace Tl with a new 6 MG reservoir, Terminal Reservoir No. 3 (T3). T3 will be constructed on the site presently occupied by Tl. This will allow for the continued use of T2 during the construction period, avoiding serious disruptions to domestic water service. T1 will be demolished to allow construction of T3 on over -excavated and recompacted firm and unyielding material, The existing 10 MG 'IR -2 has experienced structural damage due to differential settlement and is in need of replacement. In order to mitigate for documented movement of the existing reservoir due to shallow and deep seated land sliding, the project proposes to over excavate the site, and construct temporary tie-back/earth retaining systems, and permanent reinforced earth fill buttresses. Next, TR -1 will then be replaced with a new 6 MG reservoir, TR -3. The proposed 6 MG reservoir will be constructed adjacent to TR -2, and be constructed of pre -stressed concrete, and will measure 175' in diameter by 40' high. This will allow TR -2 to be operational until TR -3 is constructed and in service; avoiding serious service interruptions. The proposed site for TR -3 is presently occupied by the existing 2 MG TR -1, which is no longer in service, and will be demolished to allow construction of TR -3. Ancillary site work associated with the construction of TR -3 includes: 1) Construction of a small, enclosed structure (approximately 15'x 25') to house reservoir altitude valves, remote SCADA control panel, electrical panel, and Chloramine generator system. This structure, or T3 itself will have a 15' radio antenna on the roof; 2) Paving the existing gravel access road that runs northeast from Mission Hills Drive to the reservoir site; 3) Stockpiling of up to 100,000 CY of excavated dirt in a vacant area, southwest of the reservoir site. It is our understanding that the excavated dirt will be used as re -compacted fill. The City will be obtaining required easements for use of this area; and 4) Replacement of the existing chain link fence with a new 6' high chain link fence topped with three strands of barbed wire, and to be located around the entire perimeter of the site. KEY ISSUES: A key component of a successful project is a work plan. This tool will allow the RBF Project Manager to share the development of the project with the City of San Juan Capistrano. At the kick-off meeting with the City and the RBF Team, a schedule and a preliminary work plan will be presented in a work group session, in order to customize and refine the plan to ultimately produce a plan which meets the projects goals and milestones. Following a detailed review of the Preliminary Design Report, RFP, and conversations with the Project Manager, our team is prepared to address the following key issues during our review and throughout the construction process: 1-1 1 t Terminal Reservoir No. 2 Replacement ect Proposal for Construction Management Sery • Geological constraints / site constraints • Grading • Constructability Reviews with Construction Contractors • Environmental Mitigation including Archeo / Paleo Services • Staging of Materials • Construction Scheduling and Claims Management • Concrete Integrity/ Consolidation/ Shrinkage • Maintain existing TR -2 during construction • Cost analysis • CM Control Documents • Providing Cost Effective Solutions, to add value to the to the design process. Based upon our experience on pre -stressed tanks our RE will focus on the following key components: • firm and unyielding subgrade • planning the concrete placement ie: backup pumps • consolidation • concrete shrinkage • pour windows in forms • waterstops • concrete curing MANAGEMENT APPROACH: RBF believes in a strong Project Management approach to managing the technical resources required to complete the diversified services the City of San Juan Capistrano may need to supplement its staff. RBF will assign a Project Manager to work closely with the City of San Juan Capistrano's Project Manager in resolving issues, determining project goals and objectives, and milestones and constraints of approvals. The Project Manager has the full authority to act on RBF matters pertaining to each assignment identified by the City of San Juan Capistrano. The Project Manager plans, organizes, directs and controls the actions of the Project Team, including RBF personnel, as well as subconsultants. The Project Manager is responsible for establishing and maintaining the project team's schedule, cost and quality goals. The Project Manager serves as the RBF liaison with City of San Juan Capistrano's Project Manager. The Project Manager, Mr. Jerome Ruddins, shall be the prime contact and shall be responsible for coordinating all activities with the City of San Juan Capistrano. A preliminary Work Plan establishes a sequence of events and submittals for the project. The final work plan will be updated every two weeks, thus maintaining the orderly development of the project. Program Management will be key to the success of this project. RBF will develop procedures to define roles and responsibilities. These procedures will also include lines of communication, reporting, document control, progress payment, quality control, coordination with adjacent projects, and construction close-out procedures. During the technical review phase of the project the project manager will coordinate the reviews and monitor the effort to meet the schedule milestones. Our design review report will include an executive summary outlining key issues to be addressed and commented on by the design engineer. Our team includes Lawson & Associates Geotechnical Consulting, the firm that is presently reviewing the 90% drawings, as well as RBF's structural engineers whom are also reviewing the same submittal. This will provide continuity to the process. This process includes review by RBF's general engineering construction team as well as by experts in DYK construction, in order to facilitate a set of plans and specifications that will be complete, and thus reducing costly extra work. During the construction process the weekly meeting will be key to the administration of the project. During these meetings the PM and CM will discuss: construction schedule, look -ahead schedule, RFPs, survey, submittals, CCO's, and old and new business. The meetings will have detailed minutes which will be faxed to attendees and other recipients. Pre -Construction Services Our Work Program details the activities associated with the Pre -Construction Phase. We are prepared to work as a team with the contractor to provide a quality product. This quality product begins with a detailed construction schedule which complies with the project specifications and which is reviewed by the Project Manager (PM) and Resident Engineer (RE) for schedule busters. The schedule must identify the critical path and have enough detail to reflect all the construction activities required to facilitate construction. A kick-off meeting with the City of San Juan Capistrano's Project Manager will identify the project goals and objectives and discuss specials concerns of the City of San Juan Capistrano. At this meeting, the RE will discuss the lines of communication, project controls, frequency of reports, Agency contacts, and the transfer of information. A kick-off meeting will be scheduled with the sub - consultants to discuss permitting issues and sensitive habitat. This will be addressed in the work plan. A pre -construction meeting will be scheduled following approval of the construction schedule. The RE will chair 1-2 FWF Terminal Reservoir No. 2 Replaceme4bDject Proposal for Construction Management SerMKs the meeting, with the support of the PM, and will follow a detailed agenda highlighting the lines of communication, anticipated start of construction, utility coordination, contract requirements, submittal requirements, interaction with the public, and the goals and objectives of the project. At this meeting, the Contractor will submit a copy of the daily report forms, emergency contact list, a sample notice to residents, traffic control plan, materials submittal, and designation of project superintendent. A copy of the minutes generated by the RE, will be distributed the following working day to the attendees. Following the pre - construction meeting the Inspector will take digital images and video tape the project. Two days prior to the notice to proceed the Inspector will distribute approved resident notifications and confirm that all Agencies have been contacted. During these two days the PM, RE, and Inspector will be on-site interacting with the public in order to inform the public of the upcoming construction, thus reducing calls and interruptions to the City of San Juan Capistrano. Construction Services During the first week of construction the PM, RE, and the Inspector will be on-site interacting with the public and observing the construction. The CM will keep in close contact with the City of San Juan Capistrano Project Manager. The RE will chair the weekly site meetings. The RE will generate the following weekly reports: cost management spread sheet, permit activity, complaint resolution log, change order log, statement of working days, and inspection logs. The RE will communicate clarifications to the Inspector and will coordinate inspection and testing. The RE will play a key role during the construction process, reviewing the Contractor's work, identifying corrections when they are discovered, and measuring quantities. During construction the PM will meet with the City of San Juan Capistrano to monitor schedules and budget and to administer the contract with the City of San Juan Capistrano. The CM will also coordinate submittals with the Design Engineer, CDM. The RE will maintain copies of his daily reports, Contractors daily reports, approved deviations to plans, and construction schedules, including a two-week look ahead schedule. The RE will maintain a construction file during the course of construction which will be provided to the City of San Juan Capistrano at the end of the project on CD. The success of the project will rely on the interaction of the Special Inspectors with the RE and the Contractor. During • r e %'t� �r- the project, if a changed condition is encountered, the RE and the Inspector will provide the City PM a draft change order including a memorandum, estimated cost, and a review of how the changes may affect the schedule. The Contractor will commence with the workwhen he receives a final change order prepared by the CM and endorsed by the City Project Manager. The RE will be responsible for quality control of the project, reviewing quality of the construction work, as well as reviewing the project file, comparing quantity calculations and notations to as - constructed quantities. Project Close -Out Project close-out will include the generation of a final punch list, if it is warranted, at substantial completion, with the RE, Inspectors, PM, Design Engineer, and the Contractor in attendance. During the completion of the punch list the RE will provide, through the use of E -Mail, a daily summary of the items that are complete to the City PM. Prior to the final sign -off of the project, the following items must be complete: record drawings, O&M manuals, training, and approved measured final quantities. A final project report will be written which will identify recommendations for cost savings on future projects, change order analysis, and project challenges. The final file will be provided on a CD for the City of San Juan Capistrano. RBF has already provided and looks forward to continuing to provide the City the following special qualifications: • Commitment to serving the needs of Municipal Agencies and maintaining close communications • Extensive experience in providing Construction Management and Inspection Services • Thorough understanding and comprehension of local and state standards and specifications • Local offices throughout California providing unlimited company resources • Dedication to Quality "Continuous Improvement for Success" • In-house public awareness programs to support sensitive construction projects The combination of our experienced field staff, coupled with the vast resources of office support personnel, make the RBF Construction Management Team uniquely qualified to provide the range of services necessary to take a project from bid advertisement to final project acceptance. 1-3 RW Terminal Reservoir No. 2 Replacemen ect Proposal for Construction Management Sery t 9�1i :n'�.l, SCOPE OF SERVICES TO BE PROVIDED BY THE RBF TEAM: RBF will assign and maintain an experienced and qualified Project Manager to be the single point of contact for the City for the duration of the contract. The Project Manager shall ensure that the following Scope of Work is accomplished per the requirements of this contract: 1. Construction a. Project Control i. RBF will monitor contractor's work progress, personnel, equipment, and materials to ensure that adequate resources are available to meet the project schedule. ii. RBF will maintain ability to communicate via telephone, fax and e-mail from the project site. iii. RBF will coordinate with the contractor to ensure that an accurate set of record drawings are kept on site and up to date. At a minimum, contractor's record drawings shall be reviewed on a monthly basis. iv. RBF will prepare monthly progress reports for the City's review. Monthly progress reports shall include the status of the following: work progress, contract payments, RFI's, submittals, executed and potential change orders, and construction issues. The report shall also include progress photographs, and a 4 -week look ahead schedule. V. RBF will coordinate with City Staff to ensure that City activities and responsibilities are addressed and appropriately scheduled so as not to affect the progress of the work. vi. RBF will represent the City's interests among contractor, subcontractors, utility companies, state inspectors, businesses, and general public. vii. RBF will maintain quality control on all work of sub -consultants and construction contractors. RBF will implement a program of claims avoidance and claims management. b. Meetings i. RBF will conduct the pre -construction meeting. ii. RBF will conduct weekly construction progress meetings. iii. RBF will conduct coordination meetings with City Staff, engineer, contractor, subcontractors, utility companies, or any other agency as required. iv. RBF will prepare and distribute meeting minutes for comments within three days and distribute final version within two working days of receipt of comments. c. Inspection i. RBF will maintain a resident engineer and / or special inspectors or geotechnical personnel at the project site at all times that work is progressing. The resident engineer shall be available to work during off hours in concurrence with any required off -hours construction work, and shall be available to respond to emergency call outs during off hours. ii. RBF will provide electrical (including SCADA), mechanical, structural code compliance Inspection, as well as quality assurance and control inspection of all aspects of the project as outlined in the Preliminary Design report (Exhibit E). iii. RBF will ensure the CM Team's health and safety requirements are met. iv. RBF will provide soils and materials testing and inspection services. V. RBF will provide environmental compliance monitoring per the requirements of the Mitigated Negative Declaration (MND), and other environmental permits required for this project. vi. RBF will monitor work to ensure full compliance with NPDES regulations. vii. RBF will prepare detailed daily inspection and progress reports. Reports shall be readily available for review by the City. viii. RBF will engage a consultant to monitor the contractor's lead and asbestos mitigation operation. 1-4 i?G2� Tergtinal Reservoir No. 2 ReplacemeIect • ,� Proposal for Construction Management Se es d. RFI's i. RBF will process Requests for Information (RFI's), and ensure timely distribution to and response by appropriate project team members (City Staff, Engineer, other agencies). Response to RFI's shall take no longer than 7 calendar days. ii. RBF will provide technical support and constructability reviews during preparation of responses to RFI's. iii. RBF will maintain an RFI log tracking closed and outstanding RFPs. RFI log shall be updated weekly at a minimum, and reviewed at weekly progress meetings. e. Submittals i. RBF will ensure that contractor submits a submittal schedule for review within 10 calendar days after the effective date of the construction contract. ii. RBF will provide technical support during review of the submittal schedule to ensure compliance with the contract documents. iii. RBFwill ensure that contractor submittals are submitted per accepted submittal schedule, and the requirements of the contract documents. iv. RBFwill process submittals, and ensure timely distribution to and review by appropriate project team members (City Staff, engineer, other agencies). Submittal reviews shall take no longer than 30 calendar days after submittal is received. V. RBF will provide technical support during submittal reviews. RBF will verify, prior to final approval, that any changes or revisions to any submittal do not result in changes to the contract scope of work. If changes to the contract scope are required, Consultant shall notify the City, and make a recommendation to process a Change Order prior to final approval of the submittal, and distribution to the contractor. vi. RBF will ensure that the contractor's submittal schedule is updated weekly at a minimum, and reviewed at weekly progress meetings. f. Construction Schedule i. RBF will ensure that contractor submits a construction schedule for review within 10 calendar days after the effective date of the construction contract. ii. RBF will provide technical support during review of the construction schedule to ensure compliance with the contract documents. iii. RBF will track contractor's work progress to ensure compliance with accepted baseline construction schedule. RBF will notify both the City and contractor when actual progress is behind schedule by more than 10%. Contractor shall not be allowed to start construction work prior to acceptance of a base line construction schedule. iv. RBF will ensure that the contractor's construction schedule is updated monthly at a minimum, and reviewed at weekly progress meetings. g. Change Orders i. RBF will review and evaluate change order requests, and negotiate final amounts as required. ii. RBF will provide formal Change Order recommendations for the City's review. iii. RBF will maintain a Change Order log tracking executed and potential change orders. Log shall also monitor the total amount of executed and potential change orders against the total construction contract amount. If the total amount of executed and potential change orders exceeds 10% of the construction contract amount, Consultant shall notify the City. Change Order log shall be updated weekly at a minimum, and reviewed at weekly progress meetings. iv. RBF shall not direct the contractor to proceed with any change order workwithout a fully executed change order or prior written authorization from the City. Costs for any change order work performed without a fully executed change order or prior written authorization from the City may be borne by the Consultant. 1-5 Terminal Reservoir No. 2 Replacement et` Proposal for Construction Management Se* Ftp h. Schedule of Values i. RBF shall ensure that contractor submits a schedule of values for review within 10 calendar days after the effective date of the construction contract. ii. RBF shall provide technical support during review of the construction schedule to ensure compliance with the contract documents. iii. RBF shall ensure that contractor payment requests reflect the items and amounts indicated on the accepted schedule of values. Contractor Payment i. RBF shall implement procedure for review, processing, and payment of monthly and final payment requests. ii. RBF shall ensure compliance with the accepted schedule of values and the requirements of the construction documents. iii. RBF shall measure and verify work progress and earned to date percentages. iv. RBF shall review and maintain copies of the contractor's weekly payroll reports, and verify compliance with the contract documents. RBF shall, prior to approval of any progress payments, ensure that contractor's record drawings are current, the construction schedule is updated, and weekly certified payroll reports are submitted and in compliance with the contract documents. The City will not approve payment unless it receives verification these items have been completed. j. Project Completion and Close -Out i. RBF shall determine and issue a letter to the contractor declaring substantial completion of the work or designated phases or portions thereof as outlined in the contract documents. ii. RBF shall develop a Punch List including items that require completion prior to release of final retention. iii. RBF shall ensure that contractor completes all items on the Punch List within 30 calendar days of declaration of substantial completion. iv. RBF shall, upon completion of the Punch List, notify the City that the work is ready for final inspection and coordinate final inspection with the contractor and City Staff. V. RBF shall review contractor's record drawings prior to final project acceptance. vi. RBF shall recommend to the City to accept the project, issue final payment, and file notice of completion. vii. RBF shall prepare and issue required environmental monitoring close-out reports to appropriate agencies. k. Construction Survey i. RBF shall provide the following: a. Two temporary benchmarks and two baselines in the field for the contractor. The contractor will provide all construction staking. 4. Additional Geotechnical Materials and Testing Services Scope of Work - We understand that as -needed geotechnical services will be required during the demolition of the existing reservoir and the construction of the new reservoir. Materials testing services will be utilized during the concrete placement. Services will include: A. Observation and testing during stabilization of adjacent slopes above T-2 and T-3 B. Slope Inclinometer Monitoring C. Inspection during reservoir construction (foundations, backfill, access road construction, concrete tank testing) 5. Additional Quality Control and Claim Avoidance Management Services Scope of Work - RBF will provide a seasoned specialist to ensure that all required Quality Control measures contractually assigned to subconsultants and contractors are fulfilled. This will be accomplished by conducting random spot checks of Quality Control/Quality Assurance (QC/QA) processes as well as making QC/QA requirements a standard agenda item for periodic project management meetings. The assigned QC/QA Specialist has performed similar responsibilities on numerous similar projects and has acted as a QA Manager for one of the nations largest A/E firms. 1-6 Asw Terminal Reservoir No. 2 Replacemeoject Proposal for Construction Management Se es 0 Q RBF will also take a leadership role in formulating an effective claims avoidance and management program. Specifically, what is proposed is a team concept that involves representatives of the Owner, the Designer, the Owner's legal counsel and the Construction Manager. The team would meet periodically during the course of the project, usually monthly during the active period of the project. The team can be referenced to by any name but past projects have used the acronym COST, Change Order Strategy Team. For this project the COST would take a pro -active role in reviewing and evaluating potential disputed matters at the earliest possible time so as to mitigate or eliminate adverse impacts as soon and as much as possible. The CM's Claims Management Specialist would spearhead the meeting and would prepare an agenda for the meeting and follow-up by preparing annotated minutes which would also record and highlight action item responsibilities. The proposed Claims Management Specialist has successfully utilized the COSTprogram on four previous projects ranging in size from $10 to $900 million dollars. All of the projects utilizing the COST concept were able to avoid any protracted litigation. 7. Additional Biological Services Scope of Work - As part of the RBF Team, Merkel & Associates will perform the following Biological Services: This Scope of Work is provided under the assumption that actual resource agency permitting is to be completed as part of the current design phase of the reservoir work, and is not part of the construction management phase. The conditions set forth in these permits will, however, form a major part of the basis for the biological monitoring required in the construction management phase. a. Construction Monitoring Merkel & Associates would provide a qualified biologist to perform on-site monitoring of the construction contractor during the construction phase of the project. It is anticipated that this monitoring will be focused on the demolition and grading phases of construction, when impacts to natural resources will be most impactive. This phase would include a pre -construction meeting; pre -construction staking or fencing of natural habitats designated for preservation; and a pre - construction training briefing with the construction contractor to advise personnel of habitat and resource sensitivity, disturbance limits, and general environmental management practices. During construction the biological monitorwould be on-site to observe the contractor at intervals and/or durations acceptable to the City and construction management services consultant. We anticipate 40 days of part time monitoring. Violations would be reported to the City and/or construction management services consultant, as directed. A final written construction monitoring report would be prepared at the completion of the required monitoring. b. Regulatory Agency Permit Condition Monitoring During the construction management phase described above, the biological monitor would ensure compliance with any special condition imposed on construction by the City or by permits issued by the resource agencies. These requirements are unknown and will remain so until the permits are issued, but are anticipated to cover issues such as maintenance of prescribed construction limits, adherence to environmental management practices, noise suppression, and minimization of impacts to adjacent natural resources. Violations would be reported as described above, and the final written monitoring report would include issues dealing with these permits. c. Sensitive Resource Monitoring Requirements may be mandated by the City or resource agencies to perform a pre -construction California Gnatcatcher survey to determine the presence of any gnatcatchers in adjacent or nearby habitats. The attached fee proposal includes a three -visit pre -construction survey to make such a determination. If gnatcatchers are present in adjacent areas, and construction takes place in the gnatcatcher breeding season, monitoring may be appropriate, and a fee is included in the attachment. Because the final design for the reservoir is not completed and regulatory agency permits are not yet applied for or issued (and special conditions are unknown), monitoring requirements are speculative at this point. The fee proposal is based upon assumptions from other, similar monitoring tasks, and are considered as estimates. Alternative scenarios are used in the calculation of fees, such as full-time monitoring at 40 hours per week (50 hours with 2 hours mob/demob time per day) for the construction duration alternatives, and intermittent monitoring at an arbitrary interval of twice per week, based upon a unit monitoring fee for a 10 -hour day. 1-7 fWF Terminal Reservoir No. 2 Replacement ct Proposal for Construction Management Servi 8. Additional Archeological and Paleontological Services Scope of Work: As part of the RBF Team, SWCA, Inc. Environmental Consultants will perform the following Archeological and Paleontological Services: Task 1. Cultural and Paleontological Resources Literature Reviews. SWCA will complete a review of archaeological literature maintained by the South Central Coastal Information Center located at California State University, Fullerton. In addition to the archaeological inventory records, an examination will be made of historic maps, the National Register of Historic Places, the California State Historic Resources Inventory, and the listing of California Historical Landmarks. The archival research will indicate if the project area was previously examined for cultural resources and if any resources have been recorded within that area. The literature review will include a review of information for known sites within the study area and within a one -mile radius of the study area. The paleontological literature and records review will include an examination of records maintained by the Los Angeles County Museum of Natural History to determine the existence of previously recorded paleontological resources within the project boundaries and vicinity, and to determine geologic formations that will be impacted by the project. Task 2. Cultural Resources Reconnaissance. SWCA will conduct a pedestrian reconnaissance of the project area. This will consist of a thorough examination of the study area for the purpose of identifying cultural resources. It is our understanding that the project area consists of less then five acres, located in San Juan Capistrano, California. If there is has been an earlier Phase I Cultural Resources Study of the project area and that report is made available to use then the literature reviews and reconnaissance will not be necessary. Task 3. Pregrade Conference. SWCA will have a representative present at the pregrade conference in order to establish procedures to temporarily halt or redirect work to permit an assessment of artifactual or fossil material that is found. Task 4. Archaeological and Paleontological Monitoring. According to the approved mitigation and monitoring program, SWCA will perform archaeological and paleontological monitoring during all ground disturbing activities in areas determined to be archaeologically and paleontologically sensitive. Because our archaeologists and paleontologists are cross -trained, we will only need one monitor on site during grading. It is our understanding that the project will require 40 days of grading with part time review while the drilling operation is underway, at about 2 site visits at 2 hours per week during this process. Task 5. Cultural Resources and Paleontological Technical Reports Production. At the conclusion of the monitoring, SWCA will prepare a final cultural resources report detailing the findings of the literature reviews, surface reconnaissance, and documenting the results of the cultural resources and paleontological monitoring program. City of San Juan Capistrano Responsibilities: 1. Assign a City Project Manager to be the primary point of contact for Consultant. 2. Provide the Consultant with access to the project site and existing facilities on the project site. 3. Provide the Consultant with pertinent information regarding operation of the existing facilities on site as well as general information on the water system and its operation. 4. Provide or make available upon request, reports, drawings, specifications, records, data and files deemed useful for the project activities. 5. Provide office and field personnel to operate valves and fire hydrants as required. 6. Client will require any construction contractors to indemnify RBF from any and all losses, damages, claims, expenses, including attorneys fees, and costs arising out of the contractor's work, excepting only losses, damages, claims, expenses including attorneys fees, and costs which are caused by the sole negligence or willful misconduct of RBF in performing it's services under this agreement. Client will require that the construction contractors add RBF (Consultant) as an additional insured in the comprehensive general liability, auto liability, workers compensation and builders risk insurance coverage required by Client. 1-8 Terminal Reservoir No. 2 Replaceme oject Proposal for Construction Management Se s Exclusions: 1. Utility Potholing. Any utility potholing necessary for the completion of this project shall be provided by the serving utility or the City, as necessary, and therefore is not included. 2. Hazardous Waste Investigations. It is assumed that all site assessment / hazardous waste investigations, if necessary, will be provided by the City under a separate contract. 3. Construction survey. All survey is to be provided by the contractor. 4. Monitoring surveys. 5. Video inspection. Miscellaneous: 1. All plans and other documents prepared by the CM on behalf of the OWNER shall become the sole property of the OWNER. 2. The Contractor is to provide the CM with a trailer. 1-9 FWF FBF PROJECT TEAM HOURLY RATE SCHEDULE City of San Juan Capistrano Terminal Reservoir No. 2 Replacement Project RBF ConsultinD PERSONNEL 2004 PrincipalEngineer................................................................................................................................$160.00 ProjectManager.....................................................................................................................................142.00 StructuralEngineer.................................................................................................................................144.00 Construction Manager / Claims Manager / Scheduler............................................................................139.00 0.50/mile ResidentEngineer..................................................................................................................................134.00 SeniorEngineer......................................................................................................................................123.00 Senior Construction Inspector..................................................................................................................89.00 ProjectEngineer.....................................................................................................................................103.00 EnvironmentalSpecialist......................................................................................................................... 97.00 DesignEngineer.....................................................................................................................................102.00 ProjectSurveyor.....................................................................................................................................128.00 2 -Person Survey Crew...........................................................................................................................190.00 SurveyCADD Operator............................................................................................................................98.00 FieldOffice Administrator.........................................................................................................................57.00 Administrative Support / Clerical / Word Processing................................................................................50.00 Consultation Relative to Legal Actions..................................................................................................270.00 VehicleMileage................................................................................................................................. 0.50/mile Merkel & Associates, Inc. (Bio) PERSONNEL ProjectManager....................................................................................................................................$95.00 ProjectCoordinator.................................................................................................................................68.00 ConstructionMonitor................................................................................................................................50.00 WordProcessor.......................................................................................................................................40.00 VehicleMileage................................................................................................................................. 0.50/mile SWCA. Inc. Environmental Consultants (Archeo/Paleo) PERSONNEL ProgramDirector....................................................................................................................................$95.00 Archeologic & Paleologic Project Manager/ Certified Paleontologist ......................................................80.00 Archeologic Field Director........................................................................................................................65.00 FieldMonitor.............................................................................................................................................48.00 WordProcessor.......................................................................................................................................40.00 Lawson Associates (Geotech) PERSONNEL PrincipalGeologist...............................................................................................................................$155.00 Associate Engineer Geologist................................................................................................................115.00 Senior Staff Engineer Geologist...............................................................................................................90.00 FieldTechnician.......................................................................................................................................75.00 DeputyInspector......................................................................................................................................45.00 WordProcessor.......................................................................................................................................45.00 Note: Blueprinting,reproduction, messenger service and other direct expenses will be charged without an additional cost mark-up. ASubconsultant Management Fee of fifteen -percent (15%) will be added to the direct cost of all subconsultant services to provide for the cost of administration, subconsultant consultation and insurance. These rates are good through December 31, 2004. W J_ 0 W U U) Z 0 N J_ F - LL LL F' Fr' U W 0 w EL F- wz L W dao U N Q r 0 Z z OLL 0�0 W W U J Q Z_ W F- OOOm 0010 NC'1 m CmJ O m -m, N V V N 0 m N o m ms N 1` N 1'! lU0ii340 Btlf10H 1tl101 [V of 1p r � Cl 17 fV N N r' N to, iE "@'f"�'yg'P! M� a N m� n' V m v m EL {ZSN1ucW Sylfe VyF�!§j� y�'F 9 � z�" 8 �i yW 2 e�Ol f 1� s4/ugSOW 5 ijw uy fkYk ,�F� �x7i�4 'r �� rf'Vifeh'4�ryn �? o 77 e h N N m N V V m W -0 f •k '�:�. A?�`td L41�4Wy rM', {�!*Iprds&tr hey. e�W $S isa¢¢iq'7¢viJ m mp O W < V VOm' O 10��A1"YfiF ONr mN Nm om m m Om p %fiaBSN J�Y�fF(lIM BWt�hO.•'�N � � 11 WbX o . ppm rp�p Or m NOI 0000 1.�, Nm �� � 0 G y4r I�a�,y34M`i�"`�Li�����' yyyy N m r (O IOOIO �mN N �-VN (7 N O 17mNa-tp O m N m m0 N � 01 N O d O N10 O a1'yI1 ��a� INV sjdGµYl 0 m O WTO y O OJ Z w W 00 � OCL � 2 2 W y O 0 I- Jow 0 C7 K O U' z ~ w Ow (w7 K ? K [L 2 z W t7 W O O O Z 0 CL �cwo z WOE 2> wzz 'zw0Z �aw " Zww�¢ Oc9z�w O Urw Sw> 1=� ryLL JZ?z ¢_0w� 0��0 gQzw O LU 00 4� Z o u~j Q W W ti w U 2 2 W LL J ¢ Z a O F o 0 J R J U � 6 W Z OQWLL Z K U ryW y J w TJ W w Q H U 0 \ d W 3 CryUF-�U` WUQQN 0 " � ZOZ oOiw>w� ❑ w 1 1 0' mmowwo UU O vIJw Kd 0 w wo n200w W❑ oZO O K m WwwJO mC 0 U nLL U9 aaaJw' 0 z N •Z u F U W 0 w O_ (L W W Z J W F W Q N (=.) Q N W Uwwzg W N Q ' LL d ❑ Z n 60U) 'L i LL 1=W cn W 0 Ol W w J Q Z_ w W H • C` oo eoowm000 mm moo om m mm 1SOJ 7n1O1 ls❑J1J3al❑ O N O O O h S301Aa3S mN ........... m m 1Ntl1lnSNOJS05 n o a �p M� in 'n «'<9 1S00 aOStll N N a Sal10N 1V101 m'R$==mmm m +�,�A3AaO�Sy1�NyO�>Sya�3dyLP"" (M14yY��s Si'r`�6i114�f!.TOk'�F 1 {IiYJfSx. Wf S`Z,. ye aOd3AalISJ.J3gj,Oa�d, E } 9�I 4 P,TM OM �41g a33NION3 aOIN3$x`� ."'. $ r�I _ili F °f uap'r OltlalSINIWOY W 3JIii0 Ol3FJ m n a n i,91.e1.;y<f,',�f ��,,,z'l-•'fa17'ixes t NOIlOSa1SN0.0:� $ a33NION31N301S3a,p, ? ry w � ^ e c i a3onNvw'swlnlJl�lS- @ a3oprN��nwla3road �+ � � F f F H F N Lc d S O e E E O E m i= m 2 L c u i q 5 u m y v N o m � o E E f ✓ c_ U' pC J 00 E � N S mur O w Dm O y` L CI _ L _ Wm gm9u01 " u tt Lo _Lo� HE 20 mm O mum uum 'b ccb b a E m AaY £ E c u L° Ql: c E c u C ❑ u" z � a �+q zE Et�nuc�u E 'm u i u°rcil vpi wua` ur u �m NSnl m mho ,mm R4 d 4 _ rJ 9 s d^� ep 5 e� ' ._ ........ ....._...- --....-...--.-_--___-'.. _...-..-_. h c a� R ei E 9 �m F w ' dz i N wr w r w z' r a =' - - w g 31 { W Z a i QzZ i Q�O O K O Y ............ ........ 1..................................................... ..................................... F U awc K K N W Pg _ --- o 3Q a Z j � m di i g8�ggll$s IlE:.LL a _ $$r I UP Id !1 5 IF ag ilk gF e NIS It Al z��. s�.F 3�°la'IF3��='38a',FFa 33,33 F3i33�'333=3.; _, .g a`%'1F§a''; 3';e' '� i §35YOi�a''R i III it �i E � •_ '3 as p 8 3 a I'�� § I E ;• g z EE i jE s I a ¢ . a �3�_��P C �p���j� g3pp¢gg�$j��g5�t�d8-y� '�'p4Iy88�:� 8j5� j�8{°ESPsfixjl§iy§IgpE�E p�y5 �� 1Mrl I ommmM M,' I7 o rlM Mr117 r1MMrl M M M m M Cl m M A 0 rl M'M MIM ri'm m ni Lim�ri o P-1-1-17 m _ _ _ _ _ _ FW IR- R R R R i6 '� R S3 �" 3 Y S yIy� F� ATTACHMENT