1988-0517_ZAGROS COMPANY_E12_Agenda ReportAGENDA ITEM May 17, 1988
TO: Stephen B. Julian, City Manager
FROM: W. D. Murphy, Director of Public Works
SUBJECT: Vereda Bikeway, Via Estenaga to Avenida Siega - Resolution, Notice of
Completion and Final Report (Zagros Company)
SITUATION
The construction of the Vereda Bikeway from Via Estenaga to Avenida Siega has been
completed to the satisfaction of the City Engineer and is ready for acceptance by the
City Council and recordation of a Notice of Completion with the County Recorder.
NOTIFICATION
Jennifer Abt, Orange County Transportation Commission
Zagros Company
COMMISSION/BOARD REVIEW, RECOMMENDATIONS
Not Applicable
FINANCIAL CONSIDERATIONS
The contract was awarded to Zagros Company for $39,416.30 and was completed for this
amount. SB 821 funding for the contract amount was received from the Orange County
Transportation Commission after the award of contract. The ten percent (10%) retention
of $3,941.63 will be reduced by $355.00, the cost of additional compaction testing funded
by the City. The revised retention is $3,586.63.
ALTERNATE ACTIONS
1. Accept the improvements.
2. Do not accept the improvements.
3. Refer to Staff for additional information.
RECOMMENDATION
By resolution, determine that the work for Vereda Bikeway from Via Estenaga to Avenida
Siega has been completed and declare the work to be accepted; direct the City Clerk to
forward a Notice of Completion to the County Recorder for recording; and authorize
Staff to release the ten percent (10%) retention in the amount of $3,586.63 thirty-five
(35) days after the recordation of the Notice of Completion.
Respectfully subm.t`t—end,
GW D. Mu�� I
WDM/BP:nb w'q.i15