16-1101_INTERNATIONAL LINE BUILDERS, INC_Contract Change Order #1CITY OF SAN JUAN CAPISTRANO
32400 Paseo Adelanto
San Juan Capistrano, CA 91675
(949) 493-1171
Contract Change Order # 1
Project: Traffic Signal Rancho Viejo Rd &
Paseo Espada
Contract No.: 1
Contractor: International Line Builders, Inc.
Owner: City of San Juan Capistrano
Change Order No.: 1
Orig. Contract Amt.: $289,000.00 Days 90
Prev. Approved $0 Days 0
Changes:
This Change: $98,650.00 Days 40
Revised Contract Amt.: $387,650.00 Days 130
This Change Order covers changes to the subject contract as described herein. The Contractor
shall construct, furnish equipment and materials, and perform all work as necessary or required
to complete the Change Order items for a lump sum price agreed upon between the Contractor
and City of San Juan Capistrano, otherwise referred to as Owner.
This Contract Change Order consists of 2 pages and any exhibits attached to this Contract Change Order shall not be part of the
Contract Change Order unless specifically initialed by or on behalf of both the Contractor and the City of San Juan Capistrano.
Contract Change Order # 1 Page 1 of 2
61147.021 00\20950242.3 1/2 City of San Juan Capistrano
Increase
Contract
Item
No
Description of Changes
in Contract
Time
Extension,
Amount
Days
Open cut 1200 lineal ft of trench instead of directional bore.
$98,650.00
�
40
Totals
$98,650.00
This Contract Change Order consists of 2 pages and any exhibits attached to this Contract Change Order shall not be part of the
Contract Change Order unless specifically initialed by or on behalf of both the Contractor and the City of San Juan Capistrano.
Contract Change Order # 1 Page 1 of 2
61147.021 00\20950242.3 1/2 City of San Juan Capistrano
The amount of the contract will be increased by the sum of $ 98,650.00 and the contract time
shall be extended by forty (40) calendar days or the calendar days between the submittal of the
change order request by the contractor and the change order approval date by the City, whichever is
greater. The undersigned Contractor approves the foregoing Change Order #1 as to the changes, if
any, in the contract price specified for each item including any and all supervision costs and other
miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for
completion of the entire work on account of said Change Order #1. The Contractor agrees to furnish
all labor and materials and perform all other necessary work, inclusive of the directly or indirectly
related to the approved time extension, required to complete the Change order items. This document
will become a supplement of the contract and all provisions will apply hereto. It is understood that the
Change Order shall be effective when approved by the Owner.
Contractor accepts the terms and conditions stated above as full and final settlement of any and all
claims arising out of or related to the subject of this Change Order and acknowledges that the
compensation (time and cost) set forth herein comprises the total compensation due for the work or
change defined in the Change Order, including all impact on any unchanged work. By signing this
Change Order, the Contractor acknowledges and agrees that the stipulated compensation includes
payment for all Work contained in the Change Order, plus all payment for any acceleration or
interruption of schedules, extended overhead costs, delay, and all impact or cumulative impact on all
Work under this Contract. The signing of this Change Order acknowledges full mutual accord and
satisfaction for the change and that the stated time and/or cost constitute the total equitable
adjustment owed the Contractor as a result of the change. The Contractor hereby releases and
agrees to waive all rights, without exception or reservation of any kind whatsoever, to file any further
claim or request for equitable adjustment of any type, for any reasonably foreseeable cause that shall
arise out of, or as a result of, this Change Order and/or its impact on the remainder of the Work under
the Contract.
Accepted:
Recommended:
Approved:
(Signature) Contractor's Authorized Representative
10
Date
//'Z -l6
Date
Date
Item
Justification for Change(s)
No.
The soil conditions at the job location do not allow directional boring. The soil contains too many rocks
1
and cobbles. Therefore, the conduits need to be installed with an open trench.
This Contract Change Order consists of 2 pages and any exhibits attached to this Contract Change Order shall not be part of the
Contract Change Order unless specifically initialed by or on behalf of both the Contractor and the City of San Juan Capistrano.
Contract Change Order #1
Page 2 of 2
61147.02100\20950242.3 2/2 City of San Juan Capistrano